This code of practice outlines detailed procedures for the pre-commissioning and commissioning phases of natural gas pipelines in India. It covers essential steps such as mechanical completion verification, cleaning, drying, inertisation, leak testing, and gas introduction to guarantee pipeline safety and operational readiness. The standard serves as a critical reference for professionals responsible for preparing and initiating natural gas pipeline systems.
Overview
This code of practice outlines detailed procedures for the pre-commissioning and commissioning phases of natural gas pipelines in India. It covers essential steps such as mechanical completion verification, cleaning, drying, inertisation, leak testing, and gas introduction to guarantee pipeline safety and operational readiness. The standard serves as a critical reference for professionals responsible for preparing and initiating natural gas pipeline systems.
Audience
Contents
Structure
Overview of Scope
Documentation Requirements (Clause 7.2)
Definitions
| Standard | Description |
|---|---|
| ISO 13623 | Pipeline transportation systems for hydrocarbons |
| ASME B31.8 | Gas transmission and distribution pipelines |
| API RP 1102 | Guidelines for pipeline crossings over railroads and highways |
| API RP 1104 | Welding standards for pipeline construction |
Key Notes:
For specific formulas or tables related to design or testing, please specify the clause or topic needed.
Summary of Referenced Documents
International standards referenced include:
Documentation mandates (Clause 7.2):
Revision and Copyright:
BIS Contact Information:
flowchart LR
A[IS 15663 Part 3] --> B[International Standards]
B --> ISO13623[ISO 13623]
B --> ASME_B31_8[ASME B31.8]
B --> API_RP_1102[API RP 1102]
B --> API_RP_1104[API RP 1104]
A --> C[Documentation Clause 7.2]
C --> HSE[Health, Safety & Environment]
C --> QA_QC[Quality Assurance & Control]
A --> D[BIS Offices & Contacts]
For design formulas or tables, consult the referenced standards as IS 15663 Part 3 mainly directs to these.
Terminology Guidance
Covered Definitions Include:
flowchart LR
A[IS 15663 Part 3] --> B[Definitions]
B --> C[Refer IS 15663 Part 1]
C --> D[International Standards]
D --> E[ISO 13623]
D --> F[ASME B31.8]
D --> G[API RP 1102]
D --> H[API RP 1104]
Summary: Terminology is centralized in Part 1; consult it for all pipeline design and quality assurance terms.
Outline of Pre-commissioning Steps (Clause 5.2)
Important Parameters:
flowchart TD
A[Begin Pre-commissioning] --> B[Dewatering]
B --> C[Flushing & Dry Air Purging]
C --> D[Swabbing]
D --> E[Low Pressure Leak Test]
E --> F[Documentation & Approval]
F --> G[Pipeline Ready for Commissioning]
Refer Clause 6.2 for commissioning procedures following pre-commissioning.
Pre-commissioning Verification (Clause 5.2.1)
Before commissioning, confirm mechanical completion and system readiness through these checks:
| Aspect | Description | Frequency/Notes |
|---|---|---|
| Pipeline Cover Inspection | PCM every 500 m | Continuous monitoring |
| System Verification | Cross-check with design documents | Before commissioning |
| Field Instruments | Physical and functional verification | One-time |
| Pipeline Survey | Confirm supports, CP, markers, fencing | One-time |
| Communication Systems | Confirm uninterrupted operation | One-time |
| Electrical Systems | Power supply and earthing compliance | One-time |
| Instrument Controls & Interlocks | Functional verification | One-time |
| Utilities | Power, UPS, water, air systems check | One-time |
| Alarm Systems | Alarm testing and functionality | One-time |
| Safety Measures | Emergency preparedness verification | One-time |
Note: Document all checks as per Clause 7.1a. Subsequent commissioning includes leak testing and other procedures.
Key Points on Commissioning (Clause 6.2)
Validates the pipeline system's readiness through integrity and functionality tests including pressure and leak checks.
Preceding commissioning steps include cleaning, drying, and inspections as per Clause 5.2.
Activities encompass residual dewatering, swabbing, magnetic cleaning, and low-pressure leak testing with dry air.
Documentation must include records of all pre-commissioning steps, inertisation, and gas introduction.
[ P_{test} = 1.5 , \times , P_{design} ]
Where:
| Activity | Description | Clause Reference |
|---|---|---|
| Pre-commissioning Checks | Inspection, cleaning, drying | 5.2 |
| Dewatering and Swabbing | Removal of residual water and debris | 7.1(b) |
| Low Pressure Leak Testing | Leak test with dry compressed air | 7.1(c) |
| Magnetic Cleaning & EGP | Remove magnetic particles and ground protection | 7.1(d) |
| Inertisation | Use inert gas to prevent oxidation | 7.1(e) |
| Gas Introduction & Testing | Pressurization, leak checks, flow establishment, 72-hour continuous run | 7.1(f) |
flowchart TD
A[Pre-commissioning] --> B[Residual Dewatering & Swabbing]
B --> C[Magnetic Cleaning & EGP]
C --> D[Low Pressure Leak Testing]
D --> E[Inertisation]
E --> F[Gas Introduction & Commissioning]
This sequence ensures pipeline integrity and operational readiness.
Essential Documentation as per Clause 7.1 & 7.2
Documentation must also address:
| Standard | Description |
|---|---|
| ISO 13623 | Pipeline systems for petroleum and natural gas industries |
| ASME B31.8 | Gas transmission and distribution pipelines |
| API RP 1102 | Steel pipeline crossings at railroads and highways |
| API RP 1104 | Pipeline welding standards |
| Documentation Aspect | Description |
|---|---|
| Pre-commissioning Checks | Verification of system readiness |
| Dewatering & Swabbing | Removal of water and contaminants |
| Leak Testing | Low and high pressure leak checks |
| Cleaning & EGP | Magnetic cleaning and grounding protection records |
| Inertisation | Oxygen removal and contamination prevention procedures |
| Commissioning Activities | Pressurization, flow start-up, and operational run records |
flowchart TD
A[Pre-commissioning Checks] --> B[Dewatering & Swabbing]
B --> C[Low Pressure Leak Testing]
C --> D[Magnetic Cleaning & EGP]
D --> E[Inertisation]
E --> F[Gas-in & Commissioning Activities]
F --> G[High Pressure Leak Testing]
G --> H[Flow Establishment & 72 Hr Run]
This flowchart depicts the documentation sequence required for commissioning compliance.
Frequently Asked
Pre-commissioning Inspections as per IS 15663 Part 3 (Clause 5.2.1):
Before initiating pipeline commissioning, confirm the mechanical completion of the pipeline system (up to the first isolation valve) by performing:
Additional Information:
| Check Category | Key Activities |
|---|---|
| Pipeline Cover | PCM inspection every 500 m |
| System Verification | Cross-reference with design documents |
| Field Instrumentation | Physical and functional inspection of valves and meters |
| Pipeline Survey | Confirm supports, cathodic protection, markers |
| Communication Systems | Ensure continuous communication |
| Electrical Systems | Verify power supply, earthing, and classification |
| Controls and Interlocks | Functional verification of instrumentation |
| Utilities | Check power, UPS, water, and air systems |
| Alarm Systems | Test alarms for proper operation |
| Safety Measures | Emergency preparedness and mitigation awareness |
Loading diagram...
These steps ensure the pipeline system is ready and safe for commissioning.
Pipeline Cleaning and Drying Procedures per IS 15663 Part 3:
Magnetic Cleaning (Clause 6.2.1):
Swabbing (Clause 5.2.2.1):
Drying (Clauses 6.2.3.1 & 6.2.3.2):
Loading diagram...
This sequence effectively prevents corrosion and ensures pipeline integrity before commissioning.
Acceptance Criteria for Nitrogen Inertisation (IS 15663 Part 3, Clause 6.2.5.2):
| Parameter | Requirement |
|---|---|
| Residual Oxygen Content | Less than 1% (vol/vol) |
| Nitrogen Slug Length | At least 10% of pipeline length |
| Nitrogen Purity | Adequate to meet oxygen criteria |
| Nitrogen Form | Compressed/vaporized/gaseous at ambient temperature |
| Drying Dew Point Before Inertisation | ≤ -10°C |
Loading diagram...
This ensures the removal of oxygen and moisture to safeguard pipeline integrity during commissioning.
Leak Testing of Above-Ground Piping as per IS 15663 Part 3:
Loading diagram...
The test confirms the integrity of above-ground piping prior to commissioning.
To verify compliance with commissioning processes under IS 15663 Part 3, the following documentation is mandatory:
Acceptance Criteria: The pipeline and associated systems must be leak-free, fully charged with natural gas, and demonstrate stable operation for 72 hours covering all branches and ancillary equipment.
This comprehensive documentation ensures traceability, safety compliance, and operational readiness during commissioning.
Ask AI about any clause, requirement, or provision in IS 15663 PART 3. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required