IS 15663 PART 32006AI Search Enabled✦ AI Generated

Design and installation of natural gas pipelines – Code of Practice: Part 3 Pre-commissioning and commissioning of pipelines
2006 Edition

This code of practice outlines detailed procedures for the pre-commissioning and commissioning phases of natural gas pipelines in India. It covers essential steps such as mechanical completion verification, cleaning, drying, inertisation, leak testing, and gas introduction to guarantee pipeline safety and operational readiness. The standard serves as a critical reference for professionals responsible for preparing and initiating natural gas pipeline systems.

7Sections
76Clauses Indexed
AI Search Ready
2006Edition
Structural Engineering and structural sectionsCategory
Alternative search terms: natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 pdf free download, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 free download pdf, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006:2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006-2006 PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 (2006) PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 2006 edition PDF, natural-gas-pipeline-pre-commissioning-and-commissioning-practice-2006 edition 2006 PDF

What This Standard Covers

This code of practice outlines detailed procedures for the pre-commissioning and commissioning phases of natural gas pipelines in India. It covers essential steps such as mechanical completion verification, cleaning, drying, inertisation, leak testing, and gas introduction to guarantee pipeline safety and operational readiness. The standard serves as a critical reference for professionals responsible for preparing and initiating natural gas pipeline systems.

Who Uses This Standard

  • Pipeline Design Specialists
  • Commissioning Technicians
  • Construction Supervisors for Pipelines
  • Quality Assurance and Control Inspectors
  • Safety Compliance Officers
  • Operations and Maintenance Personnel
  • Oil and Gas Infrastructure Project Leads

Key Topics Covered

Mechanical completion verification before commissioning
Procedures for pipeline cleaning and swabbing
Application of magnetic cleaning and electronic geometry pigging
Techniques for drying and dewatering pipelines
Leak testing protocols for above-ground piping
Nitrogen inertisation processes
Criteria for gas introduction and commissioning
Standards for acceptance of pre-commissioning activities
Checks on instrumentation and control systems
Safety measures and emergency readiness during commissioning
Requirements for commissioning documentation
Verification of communication and electrical systems

Table of Contents

1Scope and Overview

Overview of Scope

  • Encompasses pipeline systems used in petroleum, natural gas, and associated facilities.
  • Incorporates references to international standards such as ISO 13623, ASME B31.8, API RP 1102, and API RP 1104 for comprehensive guidance.

Documentation Requirements (Clause 7.2)

  • Mandates preparation of documents covering:
    • Health, Safety, and Environmental (HSE) policies
    • Quality Assurance (QA) frameworks
    • Quality Control (QC) measures

Definitions

  • Adopts terminology as defined in IS 15663 Part 1.

Important Standards Referenced

StandardDescription
ISO 13623Pipeline transportation systems for hydrocarbons
ASME B31.8Gas transmission and distribution pipelines
API RP 1102Guidelines for pipeline crossings over railroads and highways
API RP 1104Welding standards for pipeline construction

Key Notes:

  • Always use the most recent versions of referenced standards.
  • Usage of symbols, dimensions, and grades as per BIS copyright is permitted for application.
  • Comprehensive documentation covering HSE, QA, and QC is essential.

For specific formulas or tables related to design or testing, please specify the clause or topic needed.

2Referenced Standards and Documentation

Summary of Referenced Documents

  • International standards referenced include:

    • ISO 13623: Pipeline transportation systems for petroleum and natural gas.
    • ASME B31.8: Standards for gas transmission and distribution.
    • API RP 1102: Steel pipeline crossings of railroads and highways.
    • API RP 1104: Pipeline welding practices.
  • Documentation mandates (Clause 7.2):

    • Preparation of documents addressing HSE, QA, and QC requirements.
  • Revision and Copyright:

    • Confirm usage of latest editions of referenced standards.
    • BIS copyright applies; reproduction requires permission except for implementation purposes.
  • BIS Contact Information:

    • Head Office: Manak Bhavan, New Delhi.
    • Regional offices located in Kolkata, Chandigarh, Chennai, Mumbai, plus other branches nationwide.

Practical Guidance:

  • Use referenced standards for detailed design, welding, and safety.
  • Maintain updated documentation per Clause 7.2.
  • Refer to IS 15663 Part 1 for detailed definitions.
flowchart LR
  A[IS 15663 Part 3] --> B[International Standards]
  B --> ISO13623[ISO 13623]
  B --> ASME_B31_8[ASME B31.8]
  B --> API_RP_1102[API RP 1102]
  B --> API_RP_1104[API RP 1104]
  A --> C[Documentation Clause 7.2]
  C --> HSE[Health, Safety & Environment]
  C --> QA_QC[Quality Assurance & Control]
  A --> D[BIS Offices & Contacts]

For design formulas or tables, consult the referenced standards as IS 15663 Part 3 mainly directs to these.

3Terminology and Definitions

Terminology Guidance

  • Definitions are adopted from IS 15663 Part 1; no new terms introduced here.
  • For pipeline-related terms, consult IS 15663 Part 1.
  • Aligns terminology with international standards such as ISO 13623, ASME B31.8, API RP 1102, and API RP 1104.

Covered Definitions Include:

  • Pipeline transportation systems
  • Welding and inspection vocabulary
  • Quality assurance and control terms
  • Health, safety, and environmental (HSE) concepts

Recommended Actions:

  • Refer to IS 15663 Part 1 for comprehensive definitions.
  • Cross-check terminology with international standards for consistency.
  • Ensure documentation complies with Clause 7.2 covering HSE and QA/QC.

flowchart LR
  A[IS 15663 Part 3] --> B[Definitions]
  B --> C[Refer IS 15663 Part 1]
  C --> D[International Standards]
  D --> E[ISO 13623]
  D --> F[ASME B31.8]
  D --> G[API RP 1102]
  D --> H[API RP 1104]

Summary: Terminology is centralized in Part 1; consult it for all pipeline design and quality assurance terms.

4Pre-Commissioning Procedures

Outline of Pre-commissioning Steps (Clause 5.2)

  • Dewatering: Eliminate residual water inside the pipeline to prevent corrosion.
  • Flushing and Dry Air Purging: Clean above-ground piping at stations such as dispatch, receiving, valves, pigging, and hook-up points.
  • Swabbing: Remove moisture and debris using swabs propelled through the pipeline.
  • Low-Pressure Leak Testing: Perform leak tests on above-ground piping sections using air.
  • Documentation: Prepare comprehensive procedures and records for all pre-commissioning activities.

Important Parameters:

  • Leak test pressure usually 1.1 times the design pressure or as project specifies.
  • Flushing velocity maintained at a minimum (e.g., 1.5 m/s) to ensure debris removal.
  • Use clean, dry air at slightly above atmospheric pressure for drying.

Pre-commissioning Process Flow

flowchart TD
  A[Begin Pre-commissioning] --> B[Dewatering]
  B --> C[Flushing & Dry Air Purging]
  C --> D[Swabbing]
  D --> E[Low Pressure Leak Test]
  E --> F[Documentation & Approval]
  F --> G[Pipeline Ready for Commissioning]

Refer Clause 6.2 for commissioning procedures following pre-commissioning.

5Pre-commissioning Verification Checks

Pre-commissioning Verification (Clause 5.2.1)

Before commissioning, confirm mechanical completion and system readiness through these checks:

  • Pipeline Cover Inspection: Measure every 500 meters using tools like Pipe Current Measurement (PCM) to assess coating and cathodic protection.
  • System Verification: Cross-verify all facilities against engineering drawings and specifications; record and rectify any deviations.
  • Inspection of Field Instruments and Equipment: Check actuated valves, control valves, shutdown valves, transmitters, solenoid valves, alarms, meters, and gauges for proper operation.
  • Pipeline Route Survey: Confirm installation of supports, cathodic protection, route markers, safety fencing, and protective barriers.
  • Communication and Electrical Systems: Test communication channels, ensure uninterrupted power supply, measure earth resistance, and verify equipment complies with area classification.
  • Instrumentation Controls and Interlocks: Validate that all control systems and interlocks function correctly.
  • Utilities and Alarm Systems: Check availability and operability of power, UPS, water, air, and alarm systems.
  • Safety Preparedness: Identify potential emergency scenarios and verify mitigation strategies.

Summary Table of Pre-commissioning Checks

AspectDescriptionFrequency/Notes
Pipeline Cover InspectionPCM every 500 mContinuous monitoring
System VerificationCross-check with design documentsBefore commissioning
Field InstrumentsPhysical and functional verificationOne-time
Pipeline SurveyConfirm supports, CP, markers, fencingOne-time
Communication SystemsConfirm uninterrupted operationOne-time
Electrical SystemsPower supply and earthing complianceOne-time
Instrument Controls & InterlocksFunctional verificationOne-time
UtilitiesPower, UPS, water, air systems checkOne-time
Alarm SystemsAlarm testing and functionalityOne-time
Safety MeasuresEmergency preparedness verificationOne-time

Note: Document all checks as per Clause 7.1a. Subsequent commissioning includes leak testing and other procedures.

6Commissioning Procedures

Key Points on Commissioning (Clause 6.2)

  • Validates the pipeline system's readiness through integrity and functionality tests including pressure and leak checks.

  • Preceding commissioning steps include cleaning, drying, and inspections as per Clause 5.2.

  • Activities encompass residual dewatering, swabbing, magnetic cleaning, and low-pressure leak testing with dry air.

  • Documentation must include records of all pre-commissioning steps, inertisation, and gas introduction.


Leak Test Pressure Formula

[ P_{test} = 1.5 , \times , P_{design} ]

Where:

  • (P_{test}) is the test pressure
  • (P_{design}) is the pipeline’s design pressure

Summary of Major Activities

ActivityDescriptionClause Reference
Pre-commissioning ChecksInspection, cleaning, drying5.2
Dewatering and SwabbingRemoval of residual water and debris7.1(b)
Low Pressure Leak TestingLeak test with dry compressed air7.1(c)
Magnetic Cleaning & EGPRemove magnetic particles and ground protection7.1(d)
InertisationUse inert gas to prevent oxidation7.1(e)
Gas Introduction & TestingPressurization, leak checks, flow establishment, 72-hour continuous run7.1(f)

flowchart TD
  A[Pre-commissioning] --> B[Residual Dewatering & Swabbing]
  B --> C[Magnetic Cleaning & EGP]
  C --> D[Low Pressure Leak Testing]
  D --> E[Inertisation]
  E --> F[Gas Introduction & Commissioning]

This sequence ensures pipeline integrity and operational readiness.

7Documentation and Records

Essential Documentation as per Clause 7.1 & 7.2

  • Records of all pre-commissioning checks.
  • Evidence of residual dewatering and swabbing.
  • Results of low-pressure leak tests on above-ground piping.
  • Documentation of magnetic cleaning and electrochemical ground protection (EGP).
  • Procedures and results of inertisation.
  • Detailed records of gas-in and commissioning activities including pressurization, high-pressure leak testing, flow establishment, and a minimum 72-hour operational run.

Documentation must also address:

  • Health, Safety, and Environmental (HSE) considerations.
  • Quality Assurance (QA) and Quality Control (QC) plans.

Related International References

StandardDescription
ISO 13623Pipeline systems for petroleum and natural gas industries
ASME B31.8Gas transmission and distribution pipelines
API RP 1102Steel pipeline crossings at railroads and highways
API RP 1104Pipeline welding standards

Summary Table of Documentation Components

Documentation AspectDescription
Pre-commissioning ChecksVerification of system readiness
Dewatering & SwabbingRemoval of water and contaminants
Leak TestingLow and high pressure leak checks
Cleaning & EGPMagnetic cleaning and grounding protection records
InertisationOxygen removal and contamination prevention procedures
Commissioning ActivitiesPressurization, flow start-up, and operational run records

flowchart TD
  A[Pre-commissioning Checks] --> B[Dewatering & Swabbing]
  B --> C[Low Pressure Leak Testing]
  C --> D[Magnetic Cleaning & EGP]
  D --> E[Inertisation]
  E --> F[Gas-in & Commissioning Activities]
  F --> G[High Pressure Leak Testing]
  G --> H[Flow Establishment & 72 Hr Run]

This flowchart depicts the documentation sequence required for commissioning compliance.

Popular Questions About IS 15663 PART 3

?What pre-commissioning inspections are required prior to pipeline commissioning?

Pre-commissioning Inspections as per IS 15663 Part 3 (Clause 5.2.1):

Before initiating pipeline commissioning, confirm the mechanical completion of the pipeline system (up to the first isolation valve) by performing:

  • Pipeline Cover Inspection: Use Pipe Current Measurement (PCM) every 500 meters to verify coating and cathodic protection status.
  • System Verification: Cross-check all installed components against design drawings and specifications, noting and correcting any inconsistencies.
  • Field Instrumentation and Equipment Check: Physically and functionally inspect actuated valves, control valves, solenoid valves, transmitters, shutdown devices, alarms, meters, and gauges.
  • Pipeline Route Survey: Verify installation of fittings, supports, cathodic protection systems, route markers, fencing, and protective barriers.
  • Communication System Tests: Ensure uninterrupted communication capability.
  • Electrical System Checks: Confirm reliable power supply, earth resistance measurements, and compliance with area classifications.
  • Instrumentation Controls and Interlocks: Validate functional operation according to design.
  • Utilities Assessment: Check availability and operability of power, UPS, water, air, and instrument air conditioning systems.
  • Alarm System Verification: Test alarm triggering and response functionality.
  • Safety Preparedness Review: Identify potential emergency scenarios and verify mitigation readiness.

Additional Information:

  • Pre-commissioning activities commence after hydrostatic testing, backfilling, instrument installation, and cathodic protection installation are complete.
  • Procedures must prevent contamination or introduction of incompatible materials into the pipeline.

Summary Table of Pre-commissioning Checks

Check CategoryKey Activities
Pipeline CoverPCM inspection every 500 m
System VerificationCross-reference with design documents
Field InstrumentationPhysical and functional inspection of valves and meters
Pipeline SurveyConfirm supports, cathodic protection, markers
Communication SystemsEnsure continuous communication
Electrical SystemsVerify power supply, earthing, and classification
Controls and InterlocksFunctional verification of instrumentation
UtilitiesCheck power, UPS, water, and air systems
Alarm SystemsTest alarms for proper operation
Safety MeasuresEmergency preparedness and mitigation awareness
Loading diagram...

These steps ensure the pipeline system is ready and safe for commissioning.

?What methods are recommended for cleaning and drying pipelines according to the standard?

Pipeline Cleaning and Drying Procedures per IS 15663 Part 3:

  1. Magnetic Cleaning (Clause 6.2.1):

    • Utilize bi-directional magnetic brush pigs to remove metallic debris.
    • Conduct cleaning after swabbing and pipeline tie-in.
    • Propulsion is achieved using super dry air.
    • Prepare and approve a detailed procedure prior to execution.
  2. Swabbing (Clause 5.2.2.1):

    • Perform after dewatering to extract residual water.
    • Use absorbent pigs propelled by oil-free compressed dry air.
    • Air supply should be treated via compressors, after-coolers, and driers.
  3. Drying (Clauses 6.2.3.1 & 6.2.3.2):

    • Dry underground and above-ground pipelines plus station piping before gas charging.
    • Employ super dry air or vacuum drying techniques.
    • Drying is complete when the water dew point reaches -10°C at atmospheric pressure.
    • Maintain pipeline pressure at 2.0 kg/cm² with dry air at the specified dew point until inertisation.
    • Alternatively, nitrogen may be used to break the vacuum post-drying if gas introduction follows immediately.

Loading diagram...

This sequence effectively prevents corrosion and ensures pipeline integrity before commissioning.

?What are the acceptance parameters for inertisation using nitrogen gas?

Acceptance Criteria for Nitrogen Inertisation (IS 15663 Part 3, Clause 6.2.5.2):

  • Residual Oxygen Level: Must be below 1% (volume/volume) in the pipeline and above-ground piping at dispatch, receipt, valve, pigging, and hook-up stations.
  • Nitrogen Volume: The nitrogen slug length introduced should be at least 10% of the total pipeline length, separated by batching pigs, to ensure effective inertisation.
  • Nitrogen Purity: Nitrogen must be sufficiently pure to achieve the required oxygen level.
  • Nitrogen State: Use compressed, vaporized, or gaseous nitrogen at ambient temperature; avoid use of liquid nitrogen unless proper precautions are in place.
  • Pre-Condition: Pipeline should be dried to a dew point of -10°C or lower before inertisation.

Summary Table

ParameterRequirement
Residual Oxygen ContentLess than 1% (vol/vol)
Nitrogen Slug LengthAt least 10% of pipeline length
Nitrogen PurityAdequate to meet oxygen criteria
Nitrogen FormCompressed/vaporized/gaseous at ambient temperature
Drying Dew Point Before Inertisation≤ -10°C
Loading diagram...

This ensures the removal of oxygen and moisture to safeguard pipeline integrity during commissioning.

?How should leak tests be conducted on above-ground piping as per the standard?

Leak Testing of Above-Ground Piping as per IS 15663 Part 3:

  • Scope: Focuses on above-ground piping sections such as flanges, equipment interfaces, and instrument impulse lines.
  • Test Medium: Utilize dry, oil-free compressed air for pressurization.
  • Leak Detection Method: Apply soap solution or employ digital pressure gauges to identify leaks by visual bubble formation or pressure drop.
  • Test Pressure: Conduct tests at a pressure of 6.0 kg/cm² (approximately 0.6 MPa).
  • Acceptance: The system must exhibit no leaks at the specified pressure to pass.

Loading diagram...

The test confirms the integrity of above-ground piping prior to commissioning.

?What documentation is required to prove adherence to commissioning procedures?

To verify compliance with commissioning processes under IS 15663 Part 3, the following documentation is mandatory:

  • Records of all pre-commissioning inspections (Clause 7.1a).
  • Evidence of residual dewatering and swabbing (Clause 7.1b).
  • Results of low-pressure leak tests on above-ground piping conducted with dry compressed air (Clause 7.1c).
  • Documentation related to magnetic cleaning and electrochemical ground protection (EGP) procedures (Clause 7.1d).
  • Records of inertisation activities (Clause 7.1e).
  • Detailed accounts of gas introduction and commissioning steps, including:
    • Pipeline pressurization
    • High-pressure leak testing
    • Flow establishment
    • Continuous operation test lasting at least 72 hours under stable conditions (Clauses 7.1f and 6.2.6.2).

Acceptance Criteria: The pipeline and associated systems must be leak-free, fully charged with natural gas, and demonstrate stable operation for 72 hours covering all branches and ancillary equipment.

This comprehensive documentation ensures traceability, safety compliance, and operational readiness during commissioning.

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in IS 15663 PART 3. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required