Morth 256 Part 21997AI Search Enabled✦ AI Generated

Standard Plan for Highway Bridges — Prestressed Concrete Beams and RCC Slab Type Superstructure Volume-II

IS MoRTH 256 Part 2 (1997) provides standardized plans and detailed specifications for prestressed concrete beams combined with RCC slab type superstructures for highway bridges, focusing on spans around 30 to 40 meters with and without footpaths. It is intended for use by engineers and designers involved in the planning, design, and construction of durable, efficient prestressed concrete highway bridges in India, ensuring compliance with Ministry of Surface Transport guidelines and facilitating uniformity in bridge superstructure design.

15Sections
84Clauses Indexed
AI Search Ready
1997Edition
Roads and Bridges IRC- Indian road congress Category
Alternative search terms: Morth 256 Part 2 PDF, Morth 256 Part 2 pdf free download, Morth 256 Part 2 free download pdf, Morth256Part2 PDF, Morth-256-Part-2 PDF, Morth 256 Part 2 1997 PDF, Morth 256 Part 2:1997 PDF, Morth 256 Part 2-1997 PDF, Morth 256 Part 2 (1997) PDF, Morth 256 Part 2 1997 edition PDF, Morth 256 Part 2 edition 1997 PDF

What This Standard Covers

IS MoRTH 256 Part 2 (1997) provides standardized plans and detailed specifications for prestressed concrete beams combined with RCC slab type superstructures for highway bridges, focusing on spans around 30 to 40 meters with and without footpaths. It is intended for use by engineers and designers involved in the planning, design, and construction of durable, efficient prestressed concrete highway bridges in India, ensuring compliance with Ministry of Surface Transport guidelines and facilitating uniformity in bridge superstructure design.

Who Uses This Standard

  • Bridge Design Engineers
  • Structural Engineers
  • Highway Infrastructure Planners
  • Construction Project Managers
  • Quality Control Engineers
  • Government Transport Authorities
  • Prestressing System Manufacturers

Key Topics Covered

Prestressed concrete beam design
RCC slab composite superstructure
One-end prestressing strand system
Cable anchorage and stressing procedures
Standardized drawings and dimensions
Reinforcement detailing for girders and slabs
Material specifications for concrete and steel
Load considerations including IRC Class 70R and footpath loads
Bituminous wearing coat and drainage system
Expansion joints and bearing details
Future prestressing provisions
Construction and stressing sequence
Anti-corrosion treatments for severe exposure
Bill of quantities for cost estimation
Safety and quality control measures

Table of Contents

1Scope

Scope Summary from MORTH 256 Part 2


1. Public Utility Services

  • Carried through 150 mm dia ducts in footpaths.
  • Max load: 1.0 kN/m per footpath.

2. Bituminous Wearing Coat

  • Mastic Asphalt Layer: 6 mm thick (12 mm in high rainfall areas).
  • Asphaltic Concrete: 50 mm total in two layers of 25 mm each.
  • Alternative for high traffic: 40 mm bituminous concrete + 25 mm bitumen mastic layer.
  • Work as per Section 500 of MOST Specification.

3. Design Loads

Load TypeValue
IRC Class 70R laneGoverns carriageway load
Footpath load5 kN/m²
Wearing coat load2 kN/m²

4. Exposure Conditions

  • Designs for moderate and severe exposure.
  • For severe, provide anti-corrosion treatment as approved.

5. Materials Specifications

MaterialSpecification
ConcreteDesign mix, 28-day strength ≥ 40 MPa (150 mm cubes)
CementIS 269 or IS 8112 (Ordinary or High Strength OPC)
Cement Content400 - 540 kg/m³
Max Water-Cement RatioDeck Slab & Precast Girder: 0.40
Reinforcement SteelHYSD bars, Grade S 415 (IS 1786)
AdmixturesIS 6925 & IS 9103 (no hydrogen, nitrogen, chlorides)

Key Formula for Load Combination (Typical)

[ \text{Total Load} = \text{Vehicle Load} + \text{Footpath Load} + \text{Wearing Coat Load} ]


Diagram: Load Distribution on Bridge Cross-Section

graph LR
A[Carriageway: IRC 70R or IRC A] --> B[Superstructure]
C[Footpath Load: 5 kN/m²] --> B
D[Wearing Coat: 2 kN/m²] --> B
E
2General Notes and Definitions

MORTH 256 Part 2: General Notes and Definitions - Key Points

This section applies to Standard Drawings for Prestressed Concrete Girders and RC Slab Type Composite Superstructure (with/without footpaths).

Key References

  • General Notes: SD/501 (Sheets 1 & 2)
  • Bill of Quantities: Included in Part 2
  • Dimensions and Anchorage Details: SD/511, SD/512, SD/521, SD/531, SD/541, etc.
  • Prestressing Cables: SD/512, SD/522, SD/532, SD/542
  • Reinforcement Details: SD/535, SD/545

Typical Definitions & Specifications:

  • Prestressing Cable Systems: Multi-wire strands detailed per drawing.
  • Span Lengths Covered: 30m, 35m, 40m spans with or without footpaths.
  • Anchorage Details: Critical for transfer of prestress, shown in respective drawings.
  • Dimensions: Govern girder width, depth, cable profile, and anchorage zones.

Common Formulas (from prestressed concrete design principles):

  • Loss of Prestress (ΔP):
    [ \Delta P = \Delta P_{\text{elastic}} + \Delta P_{\text{creep}} + \Delta P_{\text{shrinkage}} + \Delta P_{\text{relaxation}} ]
  • Ultimate Moment Capacity (M_u):
    [ M_u = f_{pu} \times A_p \times (d - a/2) ] where (f_{pu}) = ultimate stress in prestressing steel, (A_p) = area of prestressing steel, (d) = effective depth, (a) = depth of equivalent stress block.

Summary Table: Span vs Drawing Nos.

SpanWithout FootpathWith Footpath
30mSD/511, SD/512SD/521, SD/522
35m-SD/531
40mSD/541, SD/542-

flowchart LR
    A[General Notes SD/501] --> B[Prestressing Cable Details]
3Materials Specifications

MORTH 256 Part 2: Key Materials Specifications


Concrete

  • Design Mix Concrete: Minimum 28-day characteristic strength = 40 MPa (150 mm cubes).
  • Cement: OPC as per IS: 269 or High Strength OPC as per IS: 8112.
  • Cement Content: 400 to 540 kg/m³.
  • Water-Cement Ratio: Max 0.40 for deck slabs and precast girders.
  • Admixtures: Permitted as per IS: 6925 & IS: 9103; avoid admixtures generating hydrogen, nitrogen, chlorides.

Reinforcement

  • HYSD bars, Grade S:415 per IS: 1786.

Prestressing Steel

  • Strand: Single 12.7 mm dia, 7-ply Class 2 strands per IS: 6006-1983.
  • Max tensioning force per strand: 128.6 kN.
  • Use mono strand jacks; strands protected by polyethylene sheathing and grouted.

Wearing Coat Specifications

  • Mastic Asphalt Layer: 6 mm thick (12 mm in high rainfall).
  • Asphaltic Concrete Wearing Coat: 50 mm thick in two layers (25 mm each).
  • Alternative for high traffic: 40 mm bituminous concrete + 25 mm bitumen mastic.
  • Wearing coat load: 2 kN/m².

Load Considerations

  • IRC Class 70R (1 lane) or IRC Class A (2 lanes).
  • Footpath load: 5 kN/m².
  • Public utility ducts: 150 mm dia, max load 1.0 kN/m per footpath.

Summary Table: Concrete & Steel

ParameterValue/Specification
Concrete Strength40 MPa (28 days)
Cement Content400 - 540 kg/m³
Max Water-Cement Ratio0.40 (Deck slab & precast girder)
Reinforcement SteelHYSD bars S:415 (IS:1786)
Prestressing Strand12.7 mm dia, 7-ply Class 2 (IS:6006)
Max Tension per Strand128.6 kN

4Design Loads and Criteria

Design Loads and Criteria (MORTH 256 Part 2)

  • Public Utility Services Load: Max 1.0 kN/m on each footpath through 150 mm ducts.

  • Wearing Coat:

    • Mastic asphalt: 6 mm thick (12 mm in high rainfall areas).
    • Asphaltic concrete: 50 mm in two layers (25 mm each).
    • Alternative for high traffic: 40 mm bituminous concrete + 25 mm bitumen mastic.
    • Wearing coat load: 2 kN/m².
  • Design Loads:

    • IRC Class 70R (one lane) or two lanes of IRC Class A, whichever governs.
    • Footpath load: 5 kN/m².
    • Wearing coat load: 2 kN/m².
  • Exposure Conditions: Designs for moderate and severe; anti-corrosion treatment required for severe.


Materials Specifications

MaterialSpecificationNotes
ConcreteDesign mix, 40 MPa (28 days), IS: 269/8112Cement 400-540 kg/m³, w/c ≤ 0.40
Reinforcement SteelHYSD bars Grade S415, IS: 1786Minimum cover 50 mm
AdmixturesIS: 6925, IS: 9103No hydrogen/nitrogen/chloride-based

Expansion Joints

  • Movement capacity: ±40 mm.
  • Waterproof membrane and elastomer cushion mandatory.
  • Initial gap ≥ 38 mm.
  • Must cover full deck width including footpaths and kerbs.
  • Only approved manufactured joints allowed.

Summary Table: Loads for Design

Load TypeMagnitudeUnit
Public utility services1.0kN/m
Wearing coat2.0kN/m²
Footpath5.0kN/m²
IRC Class 70R (1 lane) or IRC Class A (2 lanes)Governs-

flowchart LR
    A[Bridge Deck] --> B[Wearing Coat Load (2 kN/m²)]
   
5Prestressing Cables and Systems

MORTH 256 Part 2: Prestressing Cables and Systems

Though the code clauses are unspecified, typical key points for prestressing cables in road/bridge works include:

Key Specifications:

  • Cable Types: High tensile steel strands (7-wire), conforming to IS 14268.
  • Ultimate Tensile Strength (fpu): Usually 1860 MPa for strands.
  • Relaxation: Should not exceed 5% at 1000 hours under specified stress.

Essential Formulas:

  1. Initial Prestress Force (P_i):
    [ P_i = A_p \times f_{pi} ]
    Where:

    • (A_p) = Area of prestressing steel
    • (f_{pi}) = Initial prestress stress (typically 0.7 to 0.8 of (f_{pu}))
  2. Losses in Prestress:
    Total losses = Elastic shortening + Creep + Shrinkage + Relaxation + Anchorage slip

  3. Effective Prestress Force (P_e):
    [ P_e = P_i - \text{Total losses} ]

Typical Table: Prestressing Strand Area (IS 14268)

Strand Diameter (mm)Area (mm²)Ultimate Strength (kN)
12.787162
15.2140260
15.7150279

System Specifications:

  • Anchorage devices must ensure no slip beyond 0.1 mm.
  • Grouting of ducts to protect cables from corrosion.
  • Minimum cover as per MORTH for durability.
flowchart LR
    A[Prestressing Cable] --> B[Initial Stress (f_pi)]
    B --> C[Apply Prestress Force (P_i)]
    C --> D[Losses (Relaxation, Creep, etc.)]
    D --> E[Effective Prestress Force (P_e)]
    E --> F[Structural Element Strength]

Summary: Use high tensile strands, apply initial prestress ~70-80% of ultimate strength, account for losses, and ensure proper anchorage and protection per MORTH and IS guidelines.

6Reinforcement Details

MORTH 256 Part 2: Reinforcement Details (Dimensions & Anchorage)

While specific clauses are not provided, typical MORTH and IS code practices for reinforcement details include:

Key Specifications:

  • Minimum Anchorage Length (Development Length):
    As per IS 456:2000, development length (L_d) depends on bar diameter (d_b), concrete grade, and bar stress.
    [ L_d = \frac{\sigma_{s} \times d_b}{4 \times \tau_{bd}} ] where (\sigma_s) = stress in steel, (\tau_{bd}) = design bond stress.

  • Hook and Bend Dimensions:

    • 90° hook length = 12 × bar diameter (d_b)
    • 135° hook length = 8 × d_b
  • Clear Cover:

    • For mild exposure: 25 mm
    • For moderate exposure: 40 mm
    • For severe exposure: 50 mm or more

Prestressing Cables Anchorage:

  • Anchorage zones must have adequate concrete strength (usually M40 or above).
  • Use of anchorage devices as per manufacturer and IS 1343 guidelines.
  • Ensure minimum embedment length as per design.

Typical Table: Development Length (IS 456:2000)

Bar Diameter (mm)Development Length (L_d) (mm)
12150 - 200
16200 - 250
20250 - 300

flowchart TD
    A[Reinforcement Bar] --> B[Development Length]
    B --> C[Anchorage Length]
    B --> D[Hooks & Bends]
    A --> E[Clear Cover]
    A --> F[Prestressing Cables]
    F --> G[Anchorage Devices]
    F --> H[Concrete Strength]

Summary: Ensure proper anchorage length, hooks, and cover as per IS 456 and MORTH. For prestressing, follow IS 1343 and manufacturer specs for anchorage.

7Superstructure Layout and Dimensions

MORTH 256 Part 2: Superstructure Layout and Dimensions (Prestressed Concrete Beams & RCC Slab Type)

While the code lacks explicit clause numbering, key points on superstructure layout and dimensions typically include:

1. Standard Span Lengths for PSC Beams

  • Common span lengths: 6m, 9m, 12m, 15m, 18m
  • Beam spacing depends on slab thickness and wheel load distribution, usually 1.2m to 2.5m

2. Typical Cross-Section Dimensions

ElementDimension (mm)
Beam Depth500 - 1200
Beam Width200 - 300
Slab Thickness150 - 250
Cantilever Width600 - 900

3. Anchorage Length (Prestressing Steel)

  • Calculated as per IS:1343, typically:

    [ L_a = \frac{\sigma_{pu} \times A_{ps}}{f_{bd} \times \pi \times d} ]

    where:

    • (L_a) = Anchorage length
    • (\sigma_{pu}) = Ultimate stress in prestressing steel
    • (A_{ps}) = Area of prestressing steel
    • (f_{bd}) = Bond stress
    • (d) = Diameter of prestressing strand

4. Clear Cover

  • Minimum 40 mm for PSC beams, 25 mm for RCC slabs

5. Superstructure Layout

  • Beam spacing aligned with wheel load paths
  • Expansion joints placed at intervals (typically every 30m to 40m)
graph TD
A[Superstructure Layout] --> B[PSC Beams]
A --> C[RCC Slab]
B --> D[Span Lengths 6-18m]
B --> E[Beam Depth 500-1200mm]
C --> F[Slab Thickness 150-250mm]
C --> G[Beam Spacing 1.2-2.5m]

Summary: Use standard spans (6-18m), beam depths (500-1200mm), slab thickness (150-250mm), and

8Cable Anchorage and Stressing Procedures

Key Specifications & Formulas for Cable Anchorage and Stressing (MORTH 256 Part 2)


Cable Properties:

  • Area per cable (A) = 1616.3 mm²
  • Wobble coefficient (k) = 0.0091 rad/m
  • Friction coefficient (μ) = 0.25
  • Modulus of Elasticity of steel (Es) = 2.1 × 10⁵ MPa
  • Slip = 0 to 6 mm

Concrete Strength:

  • Minimum concrete strength at tensioning = 35 MPa or as per manufacturer.

Cable Types:

  • Main prestressing: 12 strands, 12.7 mm dia, 7-ply Class 2 Strand (IS:6006-1983)
  • Future prestressing: Single 12.7 mm dia strand (IS:6006-1983)

Anchorage:

  • Use live-end type anchorages at both ends (no buried dead-end anchorages).
  • Pre-block strands at dead end to avoid slip; add slip to stressing extension if slip occurs.

Stressing Procedure:

  1. Friction Loss Calculation:

[ T_x = T_0 e^{-(\mu \alpha + k x)} ]

Where:

  • (T_x) = tension at distance (x)
  • (T_0) = initial tension
  • (\mu) = friction coefficient
  • (\alpha) = total angle of cable curvature (radians)
  • (k) = wobble coefficient
  • (x) = length of cable (m)
  1. Elongation and Gauge Pressure Control:
  • Continue tensioning until calculated gauge pressure is reached or elongation is 1.05× calculated elongation.
  • If elongation < 0.95× calculated elongation at 1.05× gauge pressure, check gauge calibration, jack, and cable duct for blockage.
  • Do not finish operations without engineer approval if elongation is insufficient.

Sheathing:

  • "Drossbach" type, 75 mm ID, 0.4 mm thick bright metal strip (IRC:18-1985 Appendix 1)

Summary Table for Cable Length & Extension (Example for 30m span):

| Cable No. | Length (mm) | Extension

9Construction Joints and Future Prestressing Provisions

Key Specifications & Formulas from MORTH 256 Part 2: Construction Joints & Future Prestressing


1. Construction Joints

  • Locations: As per drawings.
  • Reinforcement:
    • Minimum cover: 50 mm (unless specified).
    • Lap length: 63 × d (d = bar diameter).
    • No welding allowed; bending per IS: 2502-1963.
    • Use polymer cover blocks for cover.
  • Concrete Detailing:
    • Chamfer sharp edges: 10 mm × 10 mm.
    • Use stiffened shuttering plates and full-width screed vibrator for compaction.

2. Expansion Joints

  • Must be robust, durable, watertight, and replaceable.
  • Full width of deck, including kerb, footpath, fascia.
  • Approved manufactured joints only; no site fabrication.
  • Movement capacity: ± 40 mm total.
  • Waterproof membrane to prevent leakage.
  • Elastomer cushion to absorb vehicular shock.
  • Initial gap ≥ 38 mm at concreting.
  • Position steel parts accurately before concreting slab beyond girder ends.
  • Manufacturer's representative presence mandatory during installation.

3. Future Prestressing Provisions

  • Use single 12.7 mm dia., 7-ply Class 2 strands (IS: 6006-1983).
  • Max tensioning force per strand: 128.6 kN.
  • Use mono strand jack and approved prestressing system.
  • External strands protected by polyethylene sheathing and grouted.

4. Construction Sequence (Typical)

Day (after casting main girders)Activity
14Stressing of 1st stage cables (≥35 MPa strength)
21Casting cross girders & deck slab (except beyond girder ends)
49Casting deck slab beyond girder ends & superimposed dead loads (except wearing coat)
56Stressing of 2nd stage cables
>56Laying wearing coat

5. Jacking Force

  • Each cable jacking force: 1543 kN (single-end stressing) or **1776.
10Wearing Coat and Drainage Details

Wearing Coat & Drainage Details (MoRTH 256 Part 2)

Wearing Coat Specifications:

  • Prime coat: Applied over deck before wearing coat.
  • Mastic Asphalt Layer:
    • 6 mm thick normally
    • 12 mm thick for high rainfall areas
  • Asphaltic Concrete Wearing Coat:
    • Total 50 mm thick in two layers of 25 mm each
  • Alternative for high traffic:
    • 40 mm bituminous concrete + 25 mm bitumen mastic layer

Load Considerations:

  • Wearing coat load = 2 kN/m²
  • Footpath load = 5 kN/m²
  • Traffic load: IRC Class 70R (one lane) or IRC Class A (two lanes)

Drainage Details:

  • Public utilities (except water/sewer) through 150 mm dia ducts in footpaths
  • Max load of utilities = 1.0 kN/m on each footpath

Material Specs for Wearing Coat:

  • Follow Section 500 of MOST Specification for detailed procedures.

Summary Table: Wearing Coat Thickness

LayerThickness (mm)Remarks
Mastic Asphalt6 (12 for rain)Prime coat applied first
Asphaltic Concrete50 (2 layers)25 mm each
Alternative (high traffic)65 (40 + 25)Bituminous concrete + mastic

flowchart TD
    Deck -->|Prime Coat| Mastic_Asphalt
    Mastic_Asphalt -->|Layer 1 (25 mm)| Asphaltic_Concrete_Layer1
    Asphaltic_Concrete_Layer1 -->|Layer 2 (25 mm)| Asphaltic_Concrete_Layer2
    Asphaltic_Concrete_Layer2 --> Wearing_Coat_Complete

Note: Ensure proper drainage slope and anti-corrosion treatment for severe exposure conditions.

11Expansion Joints and Bearings

Expansion Joints (MORTH 256 Part 2)

  • Movement Capacity: ± 40 mm total movement.
  • Waterproofing: Must include a waterproof membrane to prevent leakage beneath the joint.
  • Shock Absorption: Cushion of elastomer to absorb vehicle shock.
  • Width & Profile: Full width of deck including kerb, footpath, fascia; must follow deck profile.
  • Initial Gap: Minimum 38 mm at concreting, finalized with manufacturer.
  • Fabrication: Only approved, proven manufactured joints allowed; site fabrication prohibited.
  • Installation: Steel parts positioned accurately before concreting beyond main girders; manufacturer’s representative presence mandatory.

Bearings (Refer SD/306 Drawings)

  • Detailed bearing specifications and types are provided in SD/306 (Sheets 1, 2 & 3).
  • Bearings must accommodate movements and rotations as per design loads.
  • Material and installation details follow standard bridge design practices.

Construction Timeline (Key for Deck & Expansion Joint Installation)

Day After Casting Main GirdersActivity
14Stressing of 1st stage cables
21Casting cross girders & deck slab (except ends)
49Casting deck slab beyond main girders & dead loads
56Stressing of 2nd stage cables
After 56Laying wearing coat

Summary Table for Expansion Joint Features

FeatureSpecification
Total Movement Capacity± 40 mm
Initial Gap at Concreting≥ 38 mm
Waterproof MembraneMandatory
Elastomer CushionMandatory for shock absorption
FabricationApproved manufacturer only
InstallationManufacturer’s rep. presence mandatory

flowchart LR
    A[Deck Slab] --> B[Expansion Joint]
    B --> C{Features}
    C --> D[±40 mm Movement]
    C --> E[Waterproof Membrane]
    C --> F[Elastomer Cushion]
    C --> G[Robust & Replaceable]
    B --> H[Initial Gap ≥ 38 mm]
    B --> I[Full Width Coverage]

For detailed bearing design and installation, refer to **SD

12Standard Drawings and Reference Details

Key Specifications & Reference Details from MoRTH 256 Part 2: Standard Drawings

1. Standard Drawings for Prestressed Concrete Girders & Composite Superstructures

  • General Notes:
    • SD/401 (Part 1 Strand System) & SD/501 (Part 2 Multi Wire System) cover general notes and bill of quantities.
  • Span Types & Corresponding Drawings:
Span TypeDrawing Nos. (Dimensions & Anchorage)Drawing Nos. (Prestressing Cables)Other Details
30m without footpathSD/411SD/412
30m with footpathSD/521, SD/522SD/521, SD/522
35m with footpathSD/531SD/432
40m without footpathSD/541, SD/542, SD/545SD/442Reinforcement in End Cross Girders (SD/535, SD/545)

2. Prestressing Strand Specifications (Clause 12.7)

  • Use 12.7 mm dia 7-ply Class 2 strand as per IS:6006-1983 for future prestressing.
  • Max tensioning force per strand = 128.6 kN.
  • Use mono strand jack for tensioning.
  • External strands must be polyethylene sheathed and grouted for protection.

3. Reference Drawings for Superstructure Details

Drawing No.Title
SD/302General Arrangement
SD/303Wearing coat and drainage system
SD/304RCC Railing - without footpaths
SD/305RCC Railing - with footpaths
SD/306Bearings (Sheets 1, 2 & 3)

Note: For non-standard railing types, prior approval is mandatory.


Summary Diagram: Standard Drawing Reference Flow

graph TD
    A[General Notes] --> B[Span Types]
    B --> C[30m without footpath]
    B --> D[30m with footpath]
13Bill of Quantities

Bill of Quantities (BoQ) - Key Specifications from MORTH 256 Part 2

1. Bill of Quantities Statement

  • For each system type, BoQ of various items is appended to aid superstructure cost estimation.

2. Load Specifications for BoQ

  • Public utilities (except water/sewer) through 150 mm dia ducts in footpaths.
  • Max load on each footpath due to utilities: 1.0 kN/m.
  • Wearing coat loads:
    • Bituminous wearing coat: 2 kN/m²
    • Footpath load: 5 kN/m²
  • Traffic load considered:
    • One lane IRC Class 70R or two lanes IRC Class A.

3. Wearing Coat Thickness

LayerThickness (mm)
Mastic Asphalt6 (12 for high rainfall)
Asphaltic Concrete Wearing50 (2 layers of 25)

4. Concrete & Reinforcement

  • Concrete strength: 40 MPa (28 days)
  • Cement content: 400 - 540 kg/m³
  • Max water-cement ratio: 0.40 (Deck slab & Precast girder)
  • Reinforcement: HYSD bars, Grade S415 (IS:1786)

Summary Table for BoQ Loadings and Materials

ItemSpecification
Utility Duct Diameter150 mm
Utility Load on Footpath≤ 1.0 kN/m
Wearing Coat Load2 kN/m²
Footpath Load5 kN/m²
Concrete Strength40 MPa (28 days)
Cement Content400 - 540 kg/m³
Max Water-Cement Ratio0.40
Reinforcement SteelHYSD bars, Grade S415

flowchart TD
    A[Bill of Quantities] --> B[Load Specifications]
    B --> B1[Utility Load: 1.0 kN/m]
    B --> B2[Wearing Coat Load: 2 kN/m²]
    B --> B3[Footpath Load: 5 kN/m²]
    A -->
14Quality Control and Safety Considerations

Quality Control & Safety: Key Points from MORTH 256 Part 2


1. Water Quality for Concreting (Clause 5.1)

  • Water must comply with IRC: SP: 33-1989, Clause 5.1(ii).
  • Ensure no impurities that affect concrete strength/durability.

2. Expansion Joints (Clauses 12-18)

  • Must be robust, durable, watertight, replaceable, covering full deck width.
  • Total movement accommodated: ±40 mm.
  • Waterproof membrane to prevent leakage.
  • Elastomer cushion for shock absorption.
  • Initial gap ≥ 38 mm during concreting.
  • Use only approved manufactured joints; site fabrication prohibited.
  • Manufacturer’s representative must supervise installation.

3. Construction Sequence

Day After Casting Main GirdersActivity
14Stressing of 1st stage cables (at 35 MPa strength)
21Casting cross girders & deck slab (except beyond main girders)
49Casting deck slab beyond main girders & superimposed dead loads
56Stressing of 2nd stage cables
>56Laying of wearing coat

4. Workmanship & Detailing

  • Minimum concrete cover: 50 mm (use polymer cover blocks).
  • No welding of reinforcement.
  • Lap length: 63 × bar diameter (d).
  • Supporting chairs: 12 mm dia at intervals.
  • Chamfer sharp edges: 10 mm × 10 mm.
  • Use full-width screed vibrator for concrete compaction.
  • Jacking force per cable: approx. 1543 - 1776 kN (multi-strand jack).

5. Materials Specifications

  • Concrete: Design mix, fck = 40 MPa (28 days).
  • Cement: IS: 269 or IS: 8112 OPC.
  • Cement content: 400–540 kg/m³.
  • Max water-cement ratio: 0.40.
  • Reinforcement: HYSD bars, Grade S415 (IS: 1786).
  • Admixtures per IS: 6925 & IS: 9103 (no hydrogen
15Special Notes on Prestressing Operations

Special Notes on Prestressing Operations (MORTH 256 Part 2, Clause 12.7 & 1.95)

Key Specifications:

  • Strands: Single 12.7 mm dia., 7-ply Class 2 strands as per IS: 6006-1983.
  • Tensioning Force per Strand: Maximum 128.6 kN.
  • Tensioning Equipment: Mono strand jacks only, using approved prestressing systems.
  • Protection: Externally placed strands must be sheathed with polyethylene and grouted.

Modulus of Elasticity:

  • ( E_s = 1.95 \times 10^5 , \text{MPa} ) (for steel strands)

Prestressing Sequence:

StageCablesTime After Casting
1Nos 5,1,2,3,4,814 days (girder)
2Nos 6,756 days (girder) or 35 days (deck slab), whichever is later
  • Superimposed dead loads applied immediately after Stage 2.

Additional Notes:

  • Cables must have smooth profiles without kinks.
  • Support cables firmly at every 1.0 m interval.
  • Refer to drawings SD/401, SD/331, SD/333-337 for detailed reinforcement and anchorage.

flowchart TD
    A[Cast Girder] -->|14 days| B[Stage 1 Stressing: Cables 5,1,2,3,4,8]
    B -->|After 56 days or 35 days deck slab| C[Stage 2 Stressing: Cables 6,7]
    C --> D[Apply Superimposed Dead Loads]

This ensures safe, controlled prestressing and future strand tensioning for bridge durability.

Popular Questions About Morth 256 Part 2

?What are the recommended materials and their specifications for prestressed concrete beams in this standard?

Recommended Materials & Specifications for Prestressed Concrete Beams (MORTH 256 Part 2):

Concrete

  • Design Mix with minimum 28-day characteristic strength: 40 MPa (150 mm cubes).
  • Cement: Ordinary Portland Cement (IS: 269) or High Strength OPC (IS: 8112).
  • Cement Content: 400 to 540 kg/m³.
  • Max Water-Cement Ratio: 0.40 for deck slab and precast girders.
  • Admixtures: Allowed per IS: 6925 & IS: 9103 (no hydrogen, nitrogen, chlorides generating types).

Reinforcing Steel

  • HYSD Bars, Grade designation S:415, conforming to IS: 1786.

Prestressing Steel & Accessories

  • Strands: Single 12.7 mm dia, 7-ply Class 2 strand as per IS: 6006-1983.
  • Tensioning Force: Max 128.6 kN per strand.
  • Protection: Polyethylene sheathing and grouted for externally placed strands.
  • Sheathing: "Drossbach" type, 75 mm ID, minimum 0.4 mm thick bright metal strip (tested per IRC: 18-1985 Appendix-1).
  • Testing: Acceptance tests per BS: 4447 guidance before use.

Loading diagram...

This ensures durability, strength, and compliance with MORTH standards for prestressed concrete beams.

?How is the one-end prestressing strand system implemented according to IS MoRTH 256 Part 2?

Implementation of One-End Prestressing Strand System as per IS MoRTH 256 Part 2:

  • Cable Details: Use cables of 12 strands, each 12.7 mm dia, 7-ply Class 2 strands (IS:6006-1983) for main prestressing.
  • Future Prestressing: Use single 12.7 mm dia strand; tension force ≤ 128.6 kN; tensioning by mono strand jack only.
  • Anchorages: Dead end anchorages must be similar to live end (no buried anchorages). Strands at dead end are pre-blocked before tensioning.
  • Tensioning: Use multistrand jacks for cables; attach force measurement devices (pressure gauges) as per system manufacturer.
  • Sheathing: Use "Drossbach" type sheathing, 75 mm ID, min 0.4 mm bright metal strip, tested per IRC:18-1985 Appendix-1.
  • Slip Management: Any slip at dead end during tensioning is compensated by adjusting extension at live end.
  • Drawings: Minor modifications to existing two-end system drawings (SD/301, 312, 322, etc.) plus new drawings SD/401, 412 for one-end system.
Loading diagram...

This system simplifies anchorage and tensioning by stressing from one end only, with careful slip management and standardized components.

?What are the standard dimensions and reinforcement details for 30m span bridges with and without footpaths?

For 30m span bridges under MoRTH 256 Part 2, the standard dimensions and reinforcement details depend on the presence of footpaths:

With Footpaths:

  • Footpath width: Typically 1.5 m to 2.0 m on each side.
  • Load on footpath: 5 kN/m² as per Clause 7(ii).
  • Utility ducts: 150 mm dia ducts embedded within footpaths for public utilities (Clause 1.0).
  • Wearing coat: 6 mm mastic asphalt + 50 mm asphaltic concrete (Clause 6).
  • Railing: RCC railing details as per SD/305.
  • Reinforcement: HYSD bars Grade S415 as per IS:1786; design concrete strength 40 MPa.
  • Deck slab thickness: Typically 200-250 mm (standard for such spans).
  • Prestressing: Use 12.7 mm dia 7-ply strands for future prestressing (Clause 12.7).

Without Footpaths:

  • Carriageway width: As per lane requirements (usually 7.5 m for two lanes).
  • Load: One lane IRC 70R or two lanes IRC Class A (Clause 7(i)).
  • Wearing coat: Same as above.
  • Railing: RCC railing as per SD/304.
  • Deck slab thickness: Similar to with footpaths, but no footpath load.
  • Reinforcement: Same HYSD bars and concrete strength.

Summary Table:

ParameterWith FootpathsWithout Footpaths
Footpath Width1.5 - 2.0 mNil
Footpath Load5 kN/m²Nil
Utility Ducts150 mm dia in footpathsNil
Wearing Coat Thickness6 mm mastic + 50 mm asphalticSame
Deck Slab Thickness~200-250 mm~200-250 mm
ReinforcementHYSD S415 barsHYSD S415 bars
Railing DetailsSD/305SD/304

Loading diagram...
?How should the stressing sequence and cable anchorage be carried out to ensure structural integrity?

To ensure structural integrity during stressing and cable anchorage as per MORTH 256 Part 2:

  • Use multistrand jacks for tensioning only, with force measurement devices (pressure gauges) per system manufacturer guidance.
  • Anchorages at dead end must be similar to live end anchorages; buried anchorages are prohibited.
  • Pre-block strands at dead end before tensioning from live end to prevent slip.
  • If slip occurs at dead end during stressing, add slip length to extension at live end.
  • Use 12.7 mm dia. 7-ply Class 2 strands (IS:6006-1983) for main and future prestressing.
  • Sheathing: Drossbach type, 75 mm ID, ≥0.4 mm thick bright metal strip, tested per IRC:18-1985.

Stressing Sequence Summary

Loading diagram...

This ensures no slip-induced loss and proper force transfer, maintaining structural safety.

?What provisions does the standard include for future prestressing and maintenance of the bridge superstructure?

Provisions for Future Prestressing and Maintenance in MORTH 256 Part 2

  • Future Prestressing:

    • Use single 12.7 mm dia, 7-ply Class 2 strand as per IS: 6006-1983.
    • Maximum tensioning force per strand: 128.6 kN.
    • Use mono strand jacks with approved prestressing systems.
    • Externally placed strands must be protected by polyethylene sheathing and grouted to prevent corrosion.
  • Maintenance & Durability:

    • Bituminous wearing coat includes:
      • 6 mm mastic asphalt (12 mm in high rainfall areas) with prime coat.
      • 50 mm asphaltic concrete in two layers (25 mm each).
    • Alternative wearing course for high traffic: 40 mm bituminous concrete + 25 mm bitumen mastic.
    • Anti-corrosion treatment for reinforcement and exposed concrete in severe exposure conditions as approved by Engineer-in-Charge.
    • Provision for public utility ducts (150 mm dia) in footpaths, max load 1.0 kN/m.

These ensure the bridge superstructure can be prestressed later if distressed and maintained for durability.

Loading diagram...

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in Morth 256 Part 2. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required