IS MoRTH 256 Part 2 (1997) provides standardized plans and detailed specifications for prestressed concrete beams combined with RCC slab type superstructures for highway bridges, focusing on spans around 30 to 40 meters with and without footpaths. It is intended for use by engineers and designers involved in the planning, design, and construction of durable, efficient prestressed concrete highway bridges in India, ensuring compliance with Ministry of Surface Transport guidelines and facilitating uniformity in bridge superstructure design.
Overview
IS MoRTH 256 Part 2 (1997) provides standardized plans and detailed specifications for prestressed concrete beams combined with RCC slab type superstructures for highway bridges, focusing on spans around 30 to 40 meters with and without footpaths. It is intended for use by engineers and designers involved in the planning, design, and construction of durable, efficient prestressed concrete highway bridges in India, ensuring compliance with Ministry of Surface Transport guidelines and facilitating uniformity in bridge superstructure design.
Audience
Contents
Structure
Scope Summary from MORTH 256 Part 2
| Load Type | Value |
|---|---|
| IRC Class 70R lane | Governs carriageway load |
| Footpath load | 5 kN/m² |
| Wearing coat load | 2 kN/m² |
| Material | Specification |
|---|---|
| Concrete | Design mix, 28-day strength ≥ 40 MPa (150 mm cubes) |
| Cement | IS 269 or IS 8112 (Ordinary or High Strength OPC) |
| Cement Content | 400 - 540 kg/m³ |
| Max Water-Cement Ratio | Deck Slab & Precast Girder: 0.40 |
| Reinforcement Steel | HYSD bars, Grade S 415 (IS 1786) |
| Admixtures | IS 6925 & IS 9103 (no hydrogen, nitrogen, chlorides) |
[ \text{Total Load} = \text{Vehicle Load} + \text{Footpath Load} + \text{Wearing Coat Load} ]
graph LR
A[Carriageway: IRC 70R or IRC A] --> B[Superstructure]
C[Footpath Load: 5 kN/m²] --> B
D[Wearing Coat: 2 kN/m²] --> B
E
MORTH 256 Part 2: General Notes and Definitions - Key Points
This section applies to Standard Drawings for Prestressed Concrete Girders and RC Slab Type Composite Superstructure (with/without footpaths).
| Span | Without Footpath | With Footpath |
|---|---|---|
| 30m | SD/511, SD/512 | SD/521, SD/522 |
| 35m | - | SD/531 |
| 40m | SD/541, SD/542 | - |
flowchart LR
A[General Notes SD/501] --> B[Prestressing Cable Details]
MORTH 256 Part 2: Key Materials Specifications
| Parameter | Value/Specification |
|---|---|
| Concrete Strength | 40 MPa (28 days) |
| Cement Content | 400 - 540 kg/m³ |
| Max Water-Cement Ratio | 0.40 (Deck slab & precast girder) |
| Reinforcement Steel | HYSD bars S:415 (IS:1786) |
| Prestressing Strand | 12.7 mm dia, 7-ply Class 2 (IS:6006) |
| Max Tension per Strand | 128.6 kN |
Design Loads and Criteria (MORTH 256 Part 2)
Public Utility Services Load: Max 1.0 kN/m on each footpath through 150 mm ducts.
Wearing Coat:
Design Loads:
Exposure Conditions: Designs for moderate and severe; anti-corrosion treatment required for severe.
| Material | Specification | Notes |
|---|---|---|
| Concrete | Design mix, 40 MPa (28 days), IS: 269/8112 | Cement 400-540 kg/m³, w/c ≤ 0.40 |
| Reinforcement Steel | HYSD bars Grade S415, IS: 1786 | Minimum cover 50 mm |
| Admixtures | IS: 6925, IS: 9103 | No hydrogen/nitrogen/chloride-based |
| Load Type | Magnitude | Unit |
|---|---|---|
| Public utility services | 1.0 | kN/m |
| Wearing coat | 2.0 | kN/m² |
| Footpath | 5.0 | kN/m² |
| IRC Class 70R (1 lane) or IRC Class A (2 lanes) | Governs | - |
flowchart LR
A[Bridge Deck] --> B[Wearing Coat Load (2 kN/m²)]
MORTH 256 Part 2: Prestressing Cables and Systems
Though the code clauses are unspecified, typical key points for prestressing cables in road/bridge works include:
Initial Prestress Force (P_i):
[
P_i = A_p \times f_{pi}
]
Where:
Losses in Prestress:
Total losses = Elastic shortening + Creep + Shrinkage + Relaxation + Anchorage slip
Effective Prestress Force (P_e):
[
P_e = P_i - \text{Total losses}
]
| Strand Diameter (mm) | Area (mm²) | Ultimate Strength (kN) |
|---|---|---|
| 12.7 | 87 | 162 |
| 15.2 | 140 | 260 |
| 15.7 | 150 | 279 |
flowchart LR
A[Prestressing Cable] --> B[Initial Stress (f_pi)]
B --> C[Apply Prestress Force (P_i)]
C --> D[Losses (Relaxation, Creep, etc.)]
D --> E[Effective Prestress Force (P_e)]
E --> F[Structural Element Strength]
Summary: Use high tensile strands, apply initial prestress ~70-80% of ultimate strength, account for losses, and ensure proper anchorage and protection per MORTH and IS guidelines.
MORTH 256 Part 2: Reinforcement Details (Dimensions & Anchorage)
While specific clauses are not provided, typical MORTH and IS code practices for reinforcement details include:
Minimum Anchorage Length (Development Length):
As per IS 456:2000, development length (L_d) depends on bar diameter (d_b), concrete grade, and bar stress.
[
L_d = \frac{\sigma_{s} \times d_b}{4 \times \tau_{bd}}
]
where (\sigma_s) = stress in steel, (\tau_{bd}) = design bond stress.
Hook and Bend Dimensions:
Clear Cover:
| Bar Diameter (mm) | Development Length (L_d) (mm) |
|---|---|
| 12 | 150 - 200 |
| 16 | 200 - 250 |
| 20 | 250 - 300 |
flowchart TD
A[Reinforcement Bar] --> B[Development Length]
B --> C[Anchorage Length]
B --> D[Hooks & Bends]
A --> E[Clear Cover]
A --> F[Prestressing Cables]
F --> G[Anchorage Devices]
F --> H[Concrete Strength]
Summary: Ensure proper anchorage length, hooks, and cover as per IS 456 and MORTH. For prestressing, follow IS 1343 and manufacturer specs for anchorage.
MORTH 256 Part 2: Superstructure Layout and Dimensions (Prestressed Concrete Beams & RCC Slab Type)
While the code lacks explicit clause numbering, key points on superstructure layout and dimensions typically include:
| Element | Dimension (mm) |
|---|---|
| Beam Depth | 500 - 1200 |
| Beam Width | 200 - 300 |
| Slab Thickness | 150 - 250 |
| Cantilever Width | 600 - 900 |
Calculated as per IS:1343, typically:
[ L_a = \frac{\sigma_{pu} \times A_{ps}}{f_{bd} \times \pi \times d} ]
where:
graph TD
A[Superstructure Layout] --> B[PSC Beams]
A --> C[RCC Slab]
B --> D[Span Lengths 6-18m]
B --> E[Beam Depth 500-1200mm]
C --> F[Slab Thickness 150-250mm]
C --> G[Beam Spacing 1.2-2.5m]
Summary: Use standard spans (6-18m), beam depths (500-1200mm), slab thickness (150-250mm), and
[ T_x = T_0 e^{-(\mu \alpha + k x)} ]
Where:
| Cable No. | Length (mm) | Extension
Key Specifications & Formulas from MORTH 256 Part 2: Construction Joints & Future Prestressing
| Day (after casting main girders) | Activity |
|---|---|
| 14 | Stressing of 1st stage cables (≥35 MPa strength) |
| 21 | Casting cross girders & deck slab (except beyond girder ends) |
| 49 | Casting deck slab beyond girder ends & superimposed dead loads (except wearing coat) |
| 56 | Stressing of 2nd stage cables |
| >56 | Laying wearing coat |
Wearing Coat & Drainage Details (MoRTH 256 Part 2)
| Layer | Thickness (mm) | Remarks |
|---|---|---|
| Mastic Asphalt | 6 (12 for rain) | Prime coat applied first |
| Asphaltic Concrete | 50 (2 layers) | 25 mm each |
| Alternative (high traffic) | 65 (40 + 25) | Bituminous concrete + mastic |
flowchart TD
Deck -->|Prime Coat| Mastic_Asphalt
Mastic_Asphalt -->|Layer 1 (25 mm)| Asphaltic_Concrete_Layer1
Asphaltic_Concrete_Layer1 -->|Layer 2 (25 mm)| Asphaltic_Concrete_Layer2
Asphaltic_Concrete_Layer2 --> Wearing_Coat_Complete
Note: Ensure proper drainage slope and anti-corrosion treatment for severe exposure conditions.
| Day After Casting Main Girders | Activity |
|---|---|
| 14 | Stressing of 1st stage cables |
| 21 | Casting cross girders & deck slab (except ends) |
| 49 | Casting deck slab beyond main girders & dead loads |
| 56 | Stressing of 2nd stage cables |
| After 56 | Laying wearing coat |
| Feature | Specification |
|---|---|
| Total Movement Capacity | ± 40 mm |
| Initial Gap at Concreting | ≥ 38 mm |
| Waterproof Membrane | Mandatory |
| Elastomer Cushion | Mandatory for shock absorption |
| Fabrication | Approved manufacturer only |
| Installation | Manufacturer’s rep. presence mandatory |
flowchart LR
A[Deck Slab] --> B[Expansion Joint]
B --> C{Features}
C --> D[±40 mm Movement]
C --> E[Waterproof Membrane]
C --> F[Elastomer Cushion]
C --> G[Robust & Replaceable]
B --> H[Initial Gap ≥ 38 mm]
B --> I[Full Width Coverage]
For detailed bearing design and installation, refer to **SD
| Span Type | Drawing Nos. (Dimensions & Anchorage) | Drawing Nos. (Prestressing Cables) | Other Details |
|---|---|---|---|
| 30m without footpath | SD/411 | SD/412 | |
| 30m with footpath | SD/521, SD/522 | SD/521, SD/522 | |
| 35m with footpath | SD/531 | SD/432 | |
| 40m without footpath | SD/541, SD/542, SD/545 | SD/442 | Reinforcement in End Cross Girders (SD/535, SD/545) |
| Drawing No. | Title |
|---|---|
| SD/302 | General Arrangement |
| SD/303 | Wearing coat and drainage system |
| SD/304 | RCC Railing - without footpaths |
| SD/305 | RCC Railing - with footpaths |
| SD/306 | Bearings (Sheets 1, 2 & 3) |
Note: For non-standard railing types, prior approval is mandatory.
graph TD
A[General Notes] --> B[Span Types]
B --> C[30m without footpath]
B --> D[30m with footpath]
1. Bill of Quantities Statement
2. Load Specifications for BoQ
3. Wearing Coat Thickness
| Layer | Thickness (mm) |
|---|---|
| Mastic Asphalt | 6 (12 for high rainfall) |
| Asphaltic Concrete Wearing | 50 (2 layers of 25) |
4. Concrete & Reinforcement
| Item | Specification |
|---|---|
| Utility Duct Diameter | 150 mm |
| Utility Load on Footpath | ≤ 1.0 kN/m |
| Wearing Coat Load | 2 kN/m² |
| Footpath Load | 5 kN/m² |
| Concrete Strength | 40 MPa (28 days) |
| Cement Content | 400 - 540 kg/m³ |
| Max Water-Cement Ratio | 0.40 |
| Reinforcement Steel | HYSD bars, Grade S415 |
flowchart TD
A[Bill of Quantities] --> B[Load Specifications]
B --> B1[Utility Load: 1.0 kN/m]
B --> B2[Wearing Coat Load: 2 kN/m²]
B --> B3[Footpath Load: 5 kN/m²]
A -->
Quality Control & Safety: Key Points from MORTH 256 Part 2
| Day After Casting Main Girders | Activity |
|---|---|
| 14 | Stressing of 1st stage cables (at 35 MPa strength) |
| 21 | Casting cross girders & deck slab (except beyond main girders) |
| 49 | Casting deck slab beyond main girders & superimposed dead loads |
| 56 | Stressing of 2nd stage cables |
| >56 | Laying of wearing coat |
| Stage | Cables | Time After Casting |
|---|---|---|
| 1 | Nos 5,1,2,3,4,8 | 14 days (girder) |
| 2 | Nos 6,7 | 56 days (girder) or 35 days (deck slab), whichever is later |
flowchart TD
A[Cast Girder] -->|14 days| B[Stage 1 Stressing: Cables 5,1,2,3,4,8]
B -->|After 56 days or 35 days deck slab| C[Stage 2 Stressing: Cables 6,7]
C --> D[Apply Superimposed Dead Loads]
This ensures safe, controlled prestressing and future strand tensioning for bridge durability.
Frequently Asked
Recommended Materials & Specifications for Prestressed Concrete Beams (MORTH 256 Part 2):
Loading diagram...
This ensures durability, strength, and compliance with MORTH standards for prestressed concrete beams.
Implementation of One-End Prestressing Strand System as per IS MoRTH 256 Part 2:
Loading diagram...
This system simplifies anchorage and tensioning by stressing from one end only, with careful slip management and standardized components.
For 30m span bridges under MoRTH 256 Part 2, the standard dimensions and reinforcement details depend on the presence of footpaths:
| Parameter | With Footpaths | Without Footpaths |
|---|---|---|
| Footpath Width | 1.5 - 2.0 m | Nil |
| Footpath Load | 5 kN/m² | Nil |
| Utility Ducts | 150 mm dia in footpaths | Nil |
| Wearing Coat Thickness | 6 mm mastic + 50 mm asphaltic | Same |
| Deck Slab Thickness | ~200-250 mm | ~200-250 mm |
| Reinforcement | HYSD S415 bars | HYSD S415 bars |
| Railing Details | SD/305 | SD/304 |
Loading diagram...
To ensure structural integrity during stressing and cable anchorage as per MORTH 256 Part 2:
Loading diagram...
This ensures no slip-induced loss and proper force transfer, maintaining structural safety.
Provisions for Future Prestressing and Maintenance in MORTH 256 Part 2
Future Prestressing:
Maintenance & Durability:
These ensure the bridge superstructure can be prestressed later if distressed and maintained for durability.
Loading diagram...
Ask AI about any clause, requirement, or provision in Morth 256 Part 2. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required