IS MORD 30:2015 provides comprehensive guidelines for the design, installation, and maintenance of road signages under the Pradhan Mantri Gram Sadak Yojana (PMGSY) in India. It specifies standards for signage materials, dimensions, placement, and information display to ensure effective communication and safety on rural roads. This standard is essential for engineers, contractors, and government agencies involved in rural road development and maintenance under PMGSY.
Overview
IS MORD 30:2015 provides comprehensive guidelines for the design, installation, and maintenance of road signages under the Pradhan Mantri Gram Sadak Yojana (PMGSY) in India. It specifies standards for signage materials, dimensions, placement, and information display to ensure effective communication and safety on rural roads. This standard is essential for engineers, contractors, and government agencies involved in rural road development and maintenance under PMGSY.
Audience
Contents
Structure
| Sr | Activity | Frequency |
|---|---|---|
| 1 | Trimming grass & rolling strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Plugging potholes & sealing cracks | As required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of minor drainage structures | Twice a year |
| 7 | Maintenance of road-side furniture | As required |
| 8 | Whitewashing parapets of CD works | Once a year |
Signage Specifications:
Information Boards:
Financial Provision (Example):
| Year | Provision (Lakh Rs) | Expenditure (Lakh Rs) |
|---|---|---|
| 2012-13 | 3.82 | 3.48 |
| 2013-14 | 4.91 | 4.01 |
| 2015-16 | 5.09 | - |
| Total | 21.25 | 19.45 |
flowchart TD
A[After Rain] --> B[Trim Grass & Roll Strata]
B --> C[Restore Fan Cub]
General Guidelines for Signage Design and Materials (MORD 30)
Logo Boards:
Materials & Structure:
Letter Height:
Language:
Placement:
| Activity | Frequency |
|---|---|
| Trimming grass & clearing strata | After every rain |
| Restoration of fan cub | Once after rains |
| Maintenance of earthen shoulders | As required |
| Filling potholes & sealing cracks | As required |
| Maintenance of roadside drainage | Twice a year |
| Maintenance of embankment structures | Twice a year |
| Maintenance of road furniture | As required |
| Whitewashing parapets of CD works | Once a year |
flowchart LR
A[Road Length > 2 km] --> B[1 Logo Board at Finishing Point]
C[Road Length < 2 km] --> D[Logo Board every ~2 km including finishing point]
References:
This ensures visibility, durability, and local relevance of road signage.
Specifications for Logo Boards (MORD 30)
| Component | Dimension/Height |
|---|---|
| Heading Bar | 100 mm height |
| Heading Text | 25 mm height |
| Subheading Text | 25 mm height |
| Matter Information | 17 mm height |
| Steel Plate Size | ~635 × 870 mm (Info area) |
| Steel Plate Thickness | 1.6 mm |
graph LR
A[Steel Frame 75x75 mm] --> B[1.6 mm Steel Plate]
B --> C[Orange Background]
C --> D[Black Road Symbol]
D --> E[White Text: Logo + Info (both sides)]
E --> F[PCC Base 450x450x600 mm]
Summary:
Logo boards are mandatory on roads, sized and colored per specifications, installed at defined intervals based on road length, and must display information clearly on both sides in local language. Steel tubular frames with 1.6 mm steel
Information Boards: Types and Content (MORD 30, Clause 1700.1 & related)
Board A (Flexible Pavement Details)
Board B (Rigid/Semi-rigid Pavement Details)
Logo Boards
| Board Type | Location | Content Highlights | Material & Size |
|---|---|---|---|
| Board A | Start / every 5 Km (if >5 Km) | Flexible pavement details, cross-section | 1.6 mm steel plate, 635×870 mm |
| Board B | Start of rigid/semi-rigid road | Rigid pavement details | 1.6 |
Signage Placement and Frequency (MORD 30 - Clause 3.2 & Related Clauses)
Logo Boards:
Information Boards (Pradhan Mantri Gram Sadak Yojana):
General Guidelines:
| Maintenance Activity | Frequency |
|---|---|
| Trimming grass and clearing strata | After every rain |
| Restoration of fan cub | Once after rains |
| Maintenance of earthen shoulders | As required |
| Filling potholes & sealing cracks | As required |
| Maintenance of roadside drains | Twice a year |
| Maintenance of embankment storage structures | Twice a year |
| Maintenance of road side furniture | As required |
| Whitewashing of parapets | Once a year |
flowchart LR
A[Road Length > 2 km] --> B[Logo Board at Finishing Point]
C[Road Length < 2 km] --> D[Logo Boards every 2 km including finishing point]
References:
Key Specifications:
Letter Height:
Board Types & Placement:
Language:
Material & Structure:
| Sr. | Maintenance Activity | Frequency |
|---|---|---|
| 1 | Trimming grass & clearing strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Sealing cracks | As required |
| 5 | Maintenance of road drainage | Twice a year |
| 6 | Maintenance of embankment structures | Twice a year |
| 7 | Maintenance of road furniture | As required |
| 8 | Whitewashing parapets | Once a year |
flowchart TD
A[Start of Road] --> B[Logo Board]
B --> C{Road Length > 5 km?}
C -- Yes --> D[Board A every 5 km]
1. Sub-base & Base Layers:
2. Bituminous Layer:
3. Concrete Foundations for Sign Boards:
4. Maintenance Guidelines (Clause 11.00):
| Maintenance Activity | Frequency |
|---|---|
| Trimming grass and clearing strata | After every rain |
| Restoration of fan cub | Once after rains |
| Maintenance of earthen shoulders | As required |
| Patching & sealing cracks | As required |
| Maintenance of roadside drains | Twice a year |
| Maintenance of embankment drainage | Twice a year |
| Maintenance of road furniture | As required |
| Whitewashing of parapets of CD works | Once a year |
| Layer | Thickness (mm) | Material | Remarks |
|---|---|---|---|
| Sub-base | As per design | Granular material, WBM | Watered & rolled |
| Bituminous Carpet | 20 | Pre-mix bituminous carpet | Primer + tack coat applied |
| Concrete Foundation | 600-750 height | PCC M15 | For signage foundation |
| Steel Frame | 75×75 mm | Mild steel tube | For sign board support |
Maintenance of Signages and Roadside Furniture (MORD 30 - Clause 11.00 & related)
| Sr | Activity | Frequency |
|---|---|---|
| 1 | Trimming grass and clearing strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Placing pulirules & sealing cracks | As required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of emission storage structures | Twice a year |
| 7 | Maintenance of roadside furniture | As required |
| 8 | Whitewashing parapets of CD works | Once a year |
| Year | Provision (Rs. in Lakhs) | Expenditure (Rs. in Lakhs) |
|---|---|---|
| 2018-19 | 3.48 | 2.96 |
| 2012-13 | 3.82 | 3.48 |
| 2013-14 | 4.91 | 4.01 |
| 2014-15 | 4.63 | - |
| 2015-16 | 5.09 | - |
| Total | 21.25 | ** |
Key Maintenance Activities & Frequency:
| Sr | Activity | Frequency |
|---|---|---|
| 1 | Trimming of grass and clearing strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Filling of potholes & sealing cracks | As required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of emergency drainage structures | Twice a year |
| 7 | Maintenance of roadside furniture | As required |
| 8 | Whitewashing of parapets of CD works | Once a year |
Yearwise Financial Provision & Expenditure (Rs. in Lakhs):
| Year | Provision Rate | Expenditure |
|---|---|---|
| 2011-12 | 3.48 | 2.96 |
| 2012-13 | 3.82 | 3.48 |
| 2013-14 | 4.91 | 4.01 |
| 2014-15 | 4.63 | - |
| 2015-16 | 5.09 | - |
| Total | 21.93 | 19.45 |
flowchart TD
A[Maintenance Activities] --> B[
Key Points from MORD 30 related to IRC:
Informative Boards:
Material & Dimensions:
Letter Heights:
Maintenance Frequency (per IRC/MORD):
| Activity | Frequency |
|---|---|
| Trimming grass & rolling strata | After rains |
| Restoration of fan cub | Once after rains |
| Maintenance of earthen shoulders | As required |
| Sealing cracks & patching | As required |
| Maintenance of roadside drainage | Twice a year |
| Maintenance of embankment | Twice a year |
| Maintenance of road furniture | As required |
| Whitewashing parapets | Once a year |
Cross-section & Pavement Layers:
| Aspect | Specification / IRC Reference |
|---|---|
| Board Placement | IRC: 67-2001 Clause 3 |
| Steel Plate Thickness | 1.6 mm (Mild Steel) |
| Steel Tube Frame | 75 mm × 75 mm |
| Concrete Foundation | 600×600×750 mm or 60×60×75 cm |
| Letter Heights | Headings: 25 mm, Sub |
Key Points from Clause 1700.1 & Related Clauses:
Information Boards:
Materials & Layers (Flexible Pavement):
Rigid Pavement Layers:
| Layer | Thickness (mm) | Notes |
|---|---|---|
| Granular Sub-base | 150 | Well compacted |
| WBM (2 layers) | 150 (2x75) | Each layer rolled separately |
| Bituminous Premix | 20 | Final wearing course |
| Layer | Thickness (mm) | Notes |
|---|---|---|
| Granular Sub-base | 150 | Compacted |
| Cement Concrete (M15) | 150-200 | Pavement slab thickness |
| Activity | Frequency
Material & Dimensions:
Colour Scheme:
Text Heights:
| Text Type | Height (mm) |
|---|---|
| Heading | 25 |
| Sub-heading | 25 |
| Matter Information | 17 |
| Maintenance Board | 32 (title), 20 (details) |
Board Types & Placement:
2 km road: 1 at finishing point
Typical Foundation Detail:
Installation Guidelines:
| Component | Dimension (mm) |
|---|---|
| Steel Plate Thickness | 1.6 |
| Steel Tube Frame | 75 × 75 |
| PCC Foundation | 450 × 450 × 600 |
| Info Area Plate | 635 × 870 × 5 |
| Concrete Foundation | 600 × 600 × 750 |
flowchart TD
A[Road Length Check] -->|>2 km| B[Logo Board at Finish Point]
A -->|<2 km|
Quality Control and Compliance (MORD 30 - Clause 7.6 & related)
Layer Construction:
Material Quantities:
Maintenance Frequency (Years):
| Activity | Frequency |
|---|---|
| Trimming grass & clearing strata | After every rain |
| Restoration of fan cub | Once after rains |
| Maintenance of earthen shoulders | As required |
| Sealing cracks & filling potholes | As required |
| Maintenance of roadside drainage | Twice a year |
| Maintenance of masonry structures | Twice a year |
| Maintenance of road furniture | As required |
| Washing parapets of CD works | Once a year |
Volume to Trucks Conversion: [ \text{No. of trucks} = \frac{\text{Volume (Cu.m.)}}{\text{Truck capacity (Cu.m.)}} ]
Bituminous Primer Application: [ \text{Litres of primer} = \text{Area (m}^2) \times \text{Primer rate (litres/m}^2) ]
Key Specifications & Tables from MORD 30 Annexures and Illustrative Figures
| Board Type | Location | Size & Material | Letter Height | Details Displayed |
|---|---|---|---|---|
| Board A (Flexible Pavement) | Start point or every 5 km if road >5 km | 635 × 870 mm, 5 mm thick steel plate | Heading: 25 mm, Matter: 17 mm | Road length, pavement details, culverts, causeways |
| Board B (Rigid/Semi-rigid Pavement) | At start of such pavement | 600 × 600 × 750 mm concrete foundation + steel frame | Heading: 25 mm, Matter: 17 mm | Concrete pavement layers, sub-base, materials |
| Maintenance Board | At project site | Steel plate with frame | Letters: 32 mm (main), 20 mm (details) | 5-year maintenance schedule, contractor info |
| Sr. | Activity | Frequency |
|---|---|---|
| 1 | Trimming grass and clearing strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Filling potholes & sealing cracks | As required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of emergency drainage | Twice a year |
| 7 | Maintenance of roadside furniture | As required |
| 8 | Whitewashing parapets of CD works | Once a year |
References and Related Standards for MORD 30 (Pradhan Mantri Gram Sadak Yojana)
| Sr | Activity | Frequency |
|---|---|---|
| 1 | Trimming grass and cutting strata | After every rain |
| 2 | Restoration of fan curb | Once after rains |
| 3 | Maintenance of earthen shoulders | As required |
| 4 | Plugging of potholes & sealing cracks | As required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of emergency drainage | Twice a year |
| 7 | Maintenance of road-side furniture | As required |
| 8 | Whitewashing of parapets | Once a year |
graph LR
A[Subgrade] --> B[Granular Sub-base]
B --> C[WBM Layers (2 layers, each 7.6 cm thick)]
C --> D[Bituminous Layer (Primer + Pre-mix Carpet 20 mm
Frequently Asked
PMGSY Road Signages: Materials & Dimensions Summary
Loading diagram...
This ensures durability, visibility, and compliance with PMGSY guidelines.
Frequency of Installation of Logo and Information Boards on Rural Roads (MORD 30)
Logo Boards:
Information Boards (Clause 1700.1):
General Notes:
This ensures visibility and clarity for road users and citizens along rural roads.
According to Clause 3.2 and General Guidelines of MORD 30:
This ensures effective communication and maximizes the utility of signages for local users.
Loading diagram...
Summary: Use local language primarily; English only if locally understood. Display info on both sides for maximum visibility.
Maintenance Activities & Schedule for Road Signages (MORD 30)
Based on Clause 11.00 and related guidelines under PMGSY:
| Sr. | Maintenance Activity | Frequency |
|---|---|---|
| 1 | Trimming of grass & clearing strata | After every rain |
| 2 | Restoration of fan cub | Once after rains |
| 3 | Maintenance of earthen shoulders | As and when required |
| 4 | Plugging of potholes & sealing cracks | As and when required |
| 5 | Maintenance of roadside drains | Twice a year |
| 6 | Maintenance of minor drainage structures | Twice a year |
| 7 | Maintenance of road side furniture | As and when required |
| 8 | Whitewashing of parapets & CD works | Once a year |
Additional Signage Details:
Loading diagram...
This schedule ensures visibility, durability, and safety of road signages.
Coordination of MORD 30 with IRC Guidelines for Signage Placement
Signage Types & Placement: MORD 30 mandates Logo Boards at start, intermediate (every 2 km if road <2 km), and finishing points. IRC:67-2001 regulates informatory sign placement relative to carriageway edge, ensuring visibility and safety.
Language & Design: MORD 30 requires local language for clarity; IRC also emphasizes legibility and standard design for traffic signs.
Materials & Structure: Both standards prefer durable materials (welded tubular steel or masonry) for sign frames.
Information Boards: MORD 30 specifies flexible pavement details boards every 5 km per PMGSY, aligning with IRC’s emphasis on informative signage for road users.
Installation Height & Letter Size: MORD 30 suggests letter heights of 16-23 mm and concrete foundations (60x60x75 cm), consistent with IRC for readability and stability.
| Aspect | MORD 30 | IRC 67-2001 |
|---|---|---|
| Logo Board Frequency | Every 2 km (<2 km road length) | As per road design, visibility |
| Language | Local language preferred | Clear, legible language |
| Materials | Steel frame or masonry | Durable, weather-resistant |
| Letter Height | 16-23 mm | Standardized for legibility |
| Placement | As per clause 3.2 & PMGSY | Distance from carriageway edge |
Loading diagram...
In essence, MORD 30 complements IRC guidelines by detailing signage frequency, content, and local language use, while IRC ensures placement and visibility standards.