IS 802 Part 3 (1978) provides the code of practice for testing prototype self-supporting structural steel lattice towers used in overhead transmission lines. It outlines detailed procedures for load application, deflection measurement, bolt slip testing, destruction testing, and reporting requirements to ensure tower mechanical strength and safety. This standard is essential for engineers and manufacturers involved in the design validation and quality assurance of steel transmission towers.
Overview
IS 802 Part 3 (1978) provides the code of practice for testing prototype self-supporting structural steel lattice towers used in overhead transmission lines. It outlines detailed procedures for load application, deflection measurement, bolt slip testing, destruction testing, and reporting requirements to ensure tower mechanical strength and safety. This standard is essential for engineers and manufacturers involved in the design validation and quality assurance of steel transmission towers.
Audience
Contents
Structure
Scope of IS 802 Part 3: Testing of Steel Transmission Line Towers
Purpose: Specifies procedures for testing steel transmission line towers, focusing on load application, measurement, and reporting.
Key Points:
Rounding Off: Test results rounded per IS 2-1960, matching significant figures of specified values (Clause 0.4).
References: Practices align with ASCE Guide and IEC draft on overhead line tower loading tests (Clause 0.3).
| Item | Description |
|---|---|
| Tower Type | Type of tested tower |
| Manufacturer & Client | Names and addresses |
| Test Details | Dates, location, personnel |
| Drawings | Assembly/shop drawings, modifications |
| Load Diagrams | Dimensioned line diagram with load points |
| Rigging Arrangement | Diagram of load application setup |
| Test Facility | Equipment details, calibration, accuracy |
| Load Tables | Loads per point and step |
| Deflection Tables | Recorded deflections |
| Failure Analysis | Max load, failure description, failed elements |
| Photographs | Structure and failure details |
This scope ensures comprehensive, standardized testing and documentation for steel transmission towers.
IS 802 Part 3 — General Testing Guidelines Summary
The code emphasizes detailed documentation and accuracy in testing overhead transmission line towers:
| Load Point | Load Direction | Load Step 1 (kN) | Load Step 2 (kN) | ... |
|---|---|---|---|---|
| Point A | Vertical | 50 | 100 | ... |
| Point B | Horizontal | 30 | 60 | ... |
| Load Step | Deflection at Point A (mm) | Deflection at Point B (mm) | ... |
|---|---|---|---|
| 1 | 2.5 | 1.8 | ... |
| 2 | 5.0 | 3.6 | ... |
flowchart LR
A[Test Setup] --> B[Load Application]
B --> C[Measurement of Loads & Deflections]
C --> D[Data Recording & Tabulation]
D --> E[Failure Analysis (if any)]
E --> F[Report Compilation]
This structured approach ensures clarity, repeatability, and compliance with IS 802 Part 3 testing requirements.
Calibration of Instruments as per IS 802 Part 3
Plumb Tolerance: The test tower must be erected within a tolerance of 1 in 360 (Clause 2.3).
Calibration Procedure (Clause 3.1):
Load Application & Measurement Accuracy:
| Applied Load (Standard Weight) | Instrument Reading | Correction Factor (Applied - Reading) |
|---|---|---|
| 0 | 0 | 0 |
| Load 1 | Reading 1 | Load 1 - Reading 1 |
| Load 2 | Reading 2 | Load 2 - Reading 2 |
| ... | ... | ... |
| Max Load | Reading Max | Max Load - Reading Max |
Use this table to plot the calibration curve and adjust readings accordingly.
graph LR
A[Standard Weights] --> B[Instrument Calibration]
B --> C[Calibration Curve]
C --> D[Load Correction]
D --> E[Accurate Test Results]
Summary: Calibrate instruments with standard weights up to max test load, plot correction curves, ensure tower plumb within 1:360, and use precise scales for reliable load measurements.
IS 802 Part 3 - Method of Load Application: Key Points
| Step | Load Applied (% of Ultimate Load) |
|---|---|
| 1 | 25% |
| 2 | 50% |
| 3 | 75% |
| 4 | 90% |
| 5 | 95% |
| 6 | 100% |
flowchart LR
A[Start Calibration] --> B[Calibrate Instruments up to Max Load]
B --> C[Draw Calibration Curves]
C --> D[Apply Loads Gradually]
D --> E[Load Steps: 25%, 50%, 75%, 90%, 95%, 100%]
E --> F[Use Rigging Diagram for Load Application]
F --> G[Ensure Safe Rigging]
G --> H[Complete Test]
This ensures accurate, safe, and systematic load application during tower testing as per IS 802 Part 3.
IS 802 Part 3: Load and Deflection Measurement Summary
Loading Cases (Clause 4.3):
Load Measurement (Clause 5.1):
Deflection Measurement (Clause 5.2 & 8.1):
| Stage | Measurement Tool | Location | Notes |
|---|---|---|---|
| Before Load | Theodolite, Scale | Top cross arm (front/transverse) | Baseline deflection |
| Load On | Theodolite, Scale | Same as above | Maximum deflection |
| Load Off | Theodolite, Scale | Same as above | Residual deflection (if any) |
flowchart LR
A[Load Application] --> B[Load Measurement]
B --> C{Pulley Friction?}
C -- Yes --> D[Measure & Correct]
C -- No --> E[Record Load]
E --> F[Apply Load to Tower]
F --> G[Deflection Measurement]
G --> H[Before Load, Load On, Load Off]
H --> I[Analyze Deflection]
For detailed deflection limits and load cases, refer to client specifications and IS 802 Part 3 annexures.
IS 802 Part 3 - Normal Load / Broken Wire Load Tests
| Load Step (%) | Observation Time (minutes) |
|---|---|
| 25, 50, 75, 90, 95 | 2 (each) |
| 100 | 5 |
| >100 (Destruction Test) | Increment by 5%, observe until failure |
[ \text{Ultimate Design Load} = \text{Design Load} \times \text{Factor of Safety (F.O.S.)} ]
flowchart TD
A[Start Load Test] --> B{Apply Load Steps}
B -->|25%, 50%, 75%, 90%, 95%| C[Observe 2 min each]
C --> D[Apply 100% Load]
D --> E[Observe 5 min]
E --> F{Destruction Test?}
F -->|Yes| G[Increase load by 5% steps]
G --> H[Observe until failure]
F -->|No| I[End Test]
This ensures safe, gradual loading and reliable verification of tower strength per IS 802 Part 3.
IS 802 Part 3 - Observation Periods & Testing Key Points
Loads are applied gradually to the ultimate design load (Design Load × Factor of Safety) in steps:
| Step | % of Ultimate Load |
|---|---|
| 1 | 25% |
| 2 | 50% |
| 3 | 75% |
| 4 | 90% |
| 5 | 95% |
| 6 | 100% |
Loads must be applied and released gradually in the same sequence.
Reports must include:
graph LR
A[0% Load] --> B[25% Load]
B --> C[50% Load]
C --> D[75% Load]
D --> E[90% Load]
E --> F[95% Load]
F --> G[100% Load]
G --> F
F --> E
E --> D
D --> C
C --> B
B --> A
Note: Observation duration at each load step is typically defined by project specifications or test procedures, as IS 802 Part 3 does not specify it explicitly.
Deflection Recording per IS 802 Part 3
Measurement Points (Clause 5.2):
Deflections are to be recorded at the top cross arm level on the front sides of transverse and longitudinal faces or front & rear sides of transverse faces.
Load Conditions (Clause 5.2):
Record deflections at three stages:
Instrumentation & Calibration (Clause 3.1):
Load Cases (Clause 4.3):
Client provides load values, directions, and points of application.
| Stage | Action | Measurement Location |
|---|---|---|
| Before Load | Measure initial position | Top cross arm, front sides |
| Load On | Measure deflection under load | Same points |
| Load Off | Measure residual deflection | Same points |
Deflection Δ can be calculated as:
[
\Delta = L_{loaded} - L_{unloaded}
]
where (L) is the measured length or displacement from a fixed reference.
Use theodolite for angular displacement converted to linear deflection via geometry.
flowchart LR
A[Start: Tower Setup] --> B[Calibrate Instruments]
B --> C[Apply Load as per Client Specs]
C --> D[Measure Deflection at Top Cross Arm]
D --> E[Record Deflection: Before Load, Load On, Load Off]
E --> F[Analyze & Correct Data Using Calibration Curves]
F --> G[Complete Test]
This ensures accurate deflection monitoring for structural safety verification during load tests.
IS 802 Part 3 – Destruction Test Key Points
| Parameter | Details |
|---|---|
| Graduated Scale Length (Clause 8.2) | ~1 meter with markings up to 5 mm accuracy |
| Load Increment (Post Ultimate Load) | 5% increments until destruction |
| Test Conditions | Normal or broken wire (as agreed) |
graph LR
A[Start with Ultimate Design Load] --> B{Increase Load by 5% Steps?}
B -- Yes --> C[Apply Load Increment]
C --> D{Structure Fails?}
D -- No --> B
D -- Yes --> E[Test Ends]
Note: This test ensures the tower's mechanical strength beyond design loads, validating safety margins.
IS 802 Part 3: Mechanical Strength Check of Tower
Ultimate Load Testing (Clause 9.3 & 2.1.1):
Load Application (Clause 4.1):
Failure & Replacement (Clause 11.1):
[ P_{n} = P_u \times (1 + 0.05 \times n) ]
| Step (n) | Load Applied (P_n) (% of (P_u)) |
|---|---|
| 0 | 100% (Ultimate load) |
| 1 | 105% |
| 2 | 110% |
| ... | ... |
flowchart TD
A[Start Load Test] --> B[Apply Load up to 100% Ultimate Load]
B --> C{Load Held?}
C -- Yes --> D[Increase Load by 5%]
D --> E{Load > Failure?}
E -- No --> C
E -- Yes --> F[Test Ends]
C -- No --> G[Replace Failed Part]
G --> H[Retest at 100% Ultimate Load]
H --> F
Summary: IS 802 Part 3 mandates incremental load testing beyond ultimate design load in 5% steps, safe rigging, and retesting after part replacement to ensure mechanical strength of towers.
IS 802 Part 3: Remedial Measures for Premature Failure
Clause 11.1:
Clause 10.3:
Clause 10.2:
| Step | Action | Requirement |
|---|---|---|
| 1. Identify failure part | Inspect and locate failed member | Visual & test data |
| 2. Replace failed part | Use member with higher mechanical strength | Confirm via material tests (coupon) |
| 3. Retest structure | Apply 100% ultimate load again | Must pass ultimate load test |
| 4. Document & report | Prepare detailed test report as per Clause 12 | Include failure analysis |
flowchart TD
A[Premature Failure Detected] --> B[Identify Failed Part]
B --> C[Replace with Stronger Member]
C --> D[Retest at 100% Ultimate Load]
D -->|Pass| E[Approve Structure]
D -->|Fail| B
E --> F[Prepare Detailed Test Report]
Note: Always ensure material properties meet or exceed original specifications to prevent repeat failure.
IS 802 Part 3 — Test Report Key Requirements (Clause 12.1 & 12.2)
The Test Report for tower testing must include:
Additional Notes:
| Load Point | Load Step 1 (kN) | Load Step 2 (kN) | ... | Deflection Step 1 (mm) | Deflection Step 2 (mm) | ... |
|---|---|---|---|---|---|---|
| Point A | 50 | 100 | ... | 2.5 | 5.0 | ... |
| Point B | 40 | 80 | ... | 1.8 | 3.6 | ... |
flowchart TD
A[Test Setup] --> B[Load Application]
B --> C[Measurement of Loads & Deflections]
C --> D[Data Recording]
D --> E[Test Report Compilation]
E --> F[Review & Certification]
This ensures clarity, traceability, and compliance with IS 802 Part 3 standards.
Frequently Asked
According to IS 802 Part 3 (1978):
Normal Load/Broken Wire Load Tests (Clause 6.2):
Loads are applied gradually up to ultimate design load (Design Load × F.O.S) in these increments:
25%, 50%, 75%, 90%, 95%, 100% of ultimate design load.
Loads are released in the same steps.
Destruction Test (Clause 9.3):
After reaching the ultimate design load, increase loads in 5% increments until failure.
| Test Type | Load Steps (% of Ultimate Load) | Observation Time per Step |
|---|---|---|
| Normal/Broken Wire Test | 25, 50, 75, 90, 95, 100 | 2 minutes (up to 95%) |
| Destruction Test | 100%, then increments of 5% until failure | Not specified |
This ensures controlled loading and safety verification during testing.
Deflection Measurement & Recording as per IS 802 Part 3
Measurement Points: Deflections must be measured at the top cross arm level on:
Instruments: Use a theodolite and graduated scales for precise deflection readings (Clause 8.1).
Stages for Recording:
Plumb Condition: The tower must be erected within 1 in 360 plumb tolerance before testing (Clause 2.3).
Load Details: Loading values, directions, and application points are provided by the client (Clause 4.3).
| Stage | Measurement Location | Instrument | Notes |
|---|---|---|---|
| Before Load | Top cross arm (specified faces) | Theodolite, scales | Baseline deflection |
| Load On | Same as above | Theodolite, scales | Deflection under load |
| Load Off | Same as above | Theodolite, scales | Residual deflection |
| Intermediate | Same as above | Theodolite, scales | For multi-stage loading tests |
Loading diagram...
This procedure ensures accurate and repeatable deflection measurement during tower testing as per IS 802 Part 3.
According to IS 802 Part 3 (Clause 3.1), the recommended calibration procedure for testing instruments is:
Additional points:
| Step | Description |
|---|---|
| 1. Calibration Setup | Use standard weights covering max load range |
| 2. Calibration Curve | Plot instrument response vs. known loads |
| 3. Load Correction | Adjust test readings using calibration curve |
| 4. Record Deflections | Measure and record at specified points |
This ensures accuracy and reliability in load and deflection measurements during tower testing.
According to IS 802 Part 3, Clause 12.1, the test report for a tower must include:
Additionally, Clause 12.2 requires certified steel producer and physical test reports for members used.
This ensures comprehensive documentation of the test process and results for verification and traceability.
According to IS 802 Part 3 (Clause 6.1), the bolt slip test is conducted as follows:
This ensures the bolts' slip resistance under design load conditions is verified.
| Step | Action |
|---|---|
| 1 | Gradually apply load to design load |
| 2 | Hold load constant for 2 minutes |
| 3 | Gradually release load |
| 4 | Measure initial & final readings with theodolite |
| 5 | Calculate slip = Final - Initial reading |
Loading diagram...
This method confirms bolt tightness and slip resistance per IS 802 Part 3.
Ask AI about any clause, requirement, or provision in IS 802 Part 3. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required