IS 7634 Part 22012AI Search Enabled✦ AI Generated

Plastics Pipes Selection, Handling, Storage and Installation for Potable Water Supplies Code of Practice, Part 2: Laying and jointing of polyethene (PE) pipes

IS 7634 Part 2:2012 provides detailed guidelines for the selection, handling, storage, laying, jointing, and testing of polyethylene (PE) pipes used in potable water supply systems. It covers installation practices for underground and above-ground pipelines, including trench preparation, pipe support, and various jointing techniques such as butt fusion, electro fusion, compression fittings, and spigot and socket joints. This standard is essential for engineers and contractors involved in water distribution infrastructure to ensure reliable, leak-proof, and durable PE pipe installations up to 45°C water temperature.

13Sections
147Clauses Indexed
AI Search Ready
2012Edition
Plastic Piping SystemCategory
Alternative search terms: IS 7634 Part 2 PDF, IS 7634 Part 2 pdf free download, IS 7634 Part 2 free download pdf, IS7634Part2 PDF, IS-7634-Part-2 PDF, IS 7634 Part 2 2012 PDF, IS 7634 Part 2:2012 PDF, IS 7634 Part 2-2012 PDF, IS 7634 Part 2 (2012) PDF, IS 7634 Part 2 2012 edition PDF, IS 7634 Part 2 edition 2012 PDF

What This Standard Covers

IS 7634 Part 2:2012 provides detailed guidelines for the selection, handling, storage, laying, jointing, and testing of polyethylene (PE) pipes used in potable water supply systems. It covers installation practices for underground and above-ground pipelines, including trench preparation, pipe support, and various jointing techniques such as butt fusion, electro fusion, compression fittings, and spigot and socket joints. This standard is essential for engineers and contractors involved in water distribution infrastructure to ensure reliable, leak-proof, and durable PE pipe installations up to 45°C water temperature.

Who Uses This Standard

  • Civil Engineers
  • Water Supply Engineers
  • Pipeline Installation Contractors
  • Municipal Infrastructure Planners
  • Quality Control Inspectors
  • Construction Supervisors
  • Plastic Pipe Manufacturers

Key Topics Covered

Scope and applicability for potable water supplies
Trench excavation, bedding, and backfilling requirements
Handling, storage, and transportation of PE pipes
Jointing techniques: butt fusion, socket fusion, electro fusion
Compression and insert type fittings
Installation procedures for underground and above-ground pipelines
Pressure testing and field testing of pipelines
Thermal expansion and contraction considerations
Support spacing and pipe clamps for exposed runs
Repair methods for damaged pipes and joints
Protection against environmental factors like sunlight and temperature
Safety and quality assurance during pipe laying
Use of mechanical and electro fusion saddles for service connections

Table of Contents

1Scope

IS 7634 Part 2: Scope — Key Specifications & Tables

1. Trench Dimensions (Clause 6.1 & Table 3)

  • Trench Width & Depth depend on pipe size.

  • Depth measured over pipe crown.

  • Initial backfill: 150 mm minimum.

  • Depth of cover: 900–1100 mm.

  • Width increases with pipe diameter; e.g.,

    Pipe Size (mm)Width (mm)
    20-110300
    200500
    500800
    10001300
  • For mole-plough technique (20-100 mm), 300 mm width not mandatory.

  • Under highways, concrete/hume pipe cover required.

2. Butt Fusion Welding Parameters (Clause 3.2.1.2 & Table 1)

  • Welding parameters vary with nominal wall thickness.
  • Example for 7-12 mm wall thickness:
    • Bead height: 1.5 mm
    • Heating time: 70-120 s
    • Pressure build-up: 6-8 s
    • Cooling under pressure: 10-16 s
    • Cooling during pressure relaxation: 900 s
Wall Thickness (mm)Bead Height (mm)Heating (s)Pressure Build-up (s)Cooling Under Pressure (s)Cooling Relaxation (s)
Up to 4.50.54556300
7 - 121.570-1206-810-16900
50 - 704.0500-70020-2560-802700

Notes:

  • Follow IS 2:1960 for rounding off test values.
  • Initial backfill material must comply with the standard.
  • Consult manufacturers for SDR > 22 under dynamic traffic
2References

IS 7634 Part 2: Key Tables & Specifications Summary


1. Trench Dimensions (Clause 6.1, Table 3)

Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20 - 110300150900 - 1100
125425150900 - 1100
............
10001300150900 - 1100
  • Notes:
    • Width may increase for jointing inside trench.
    • Depth measured over pipe crown.
    • Initial backfill as per standard.
    • For dynamic traffic loads and SDR > 22, consult manufacturers.

2. Butt Fusion Welding Parameters (Clause 3.2.1.2, Table 1)

Wall Thickness (mm)Bead Height (mm)Heating Up (s)Change Over (s)Pressure Build-up (s)Cooling Under Pressure (s)Cooling During Relaxation (s)
Up to 4.50.545556300
4.5 - 71.045 - 705 - 65 - 66 - 10600
.....................
50 - 704.0500 - 70020 - 2525 - 3560 - 802700

3. Rounding Off (IS 2:1960)

  • Final test/analysis values must be rounded per IS 2 rules.
  • Maintain significant digits as per specified values.

flow
3Jointing Techniques

IS 7634 Part 2: Jointing Techniques – Key Points

1. Pressure-Time Control (Clause 3.2.1.3)

  • Follow the pressure-temperature chart and timing table strictly during jointing.
  • Maintain pressures as per Table 1 (typical values in N/mm²):
    • Equalisation Pressure
    • Jointing Pressure
    • Heating Pressure
    • Equalisation Period Pressure
    • Change Over Period Pressure
    • Jointing Build-Up Period Pressure
  • After pressure relief, allow the joint to cool naturally to ambient temperature; no quenching.

2. Insert Type Joint (Clause 3.2.4)

  • Refer to Fig. 6 for configuration and assembly details.
  • Used for specific pipe connection types requiring inserts.

3. Flanged Joints (Clause 3.2.6)

  • Refer to Fig. 9 for flange assembly and bolt tightening sequence.
  • Ensure compliance with local bye-laws for municipal water distribution (Clause 1.4).

Typical Pressure-Time Diagram (Fig. 2) Summary:

graph TD
A[Start Heating] --> B[Equalisation Pressure]
B --> C[Heating Pressure]
C --> D[Equalisation Period]
D --> E[Change Over Period]
E --> F[Jointing Build-Up Period]
F --> G[Pressure Relief & Natural Cooling]

Recommendations:

  • Always check Annex A for referenced standards and latest editions.
  • Ensure local bye-laws compliance for water distribution systems.

This approach ensures safe, durable, and compliant joints in ductile iron piping systems.

4Handling and Storage of Pipes

IS 7634 Part 2: Handling & Storage of Polyethylene Pipes

Key Specifications & Guidelines

  • Handling Large Pipes (>160 mm OD):

    • Use mechanical equipment for loading/unloading.
    • Avoid dumping pipes; roll smoothly off trucks using platforms.
    • Prevent penetration by sharp objects.
  • Storage Conditions:

    • Avoid storage in hot areas (>45°C).
    • If unavoidable, provide continuous support on leveled sand or similar.
    • Pipes must be stored on flat surfaces, avoiding sharp edges.
  • Transportation:

    • Vehicles must have side supports spaced ~2 m apart.
    • Use flat, smooth posts without sharp edges.
    • Secure pipe bundles with strapping to prevent movement.
  • Slack in Laying:

    • Allow up to 2% slack in trench laying to accommodate expansion/contraction.

Summary Table

AspectRequirement
Max Temp for Storage≤ 45°C (avoid higher temps)
Slack in LayingUp to 2% slack permitted
Support SpacingVehicle side supports spaced ~2 m apart
Handling Large PipesMechanical aids; no dumping; roll smoothly

flowchart LR
    A[Loading Pipes] --> B[Use Mechanical Equipment]
    B --> C[Roll Pipes Smoothly]
    C --> D[Store on Level Sand Bed]
    D --> E{Temperature > 45°C?}
    E -- Yes --> F[Avoid Storage or Provide Continuous Support]
    E -- No --> G[Normal Storage]
    G --> H[Transport with Side Supports ~2m Apart]
    H --> I[Secure Bundles with Strapping]

Note: Following these guidelines ensures pipe integrity and safety during handling, storage, and transportation as per IS 7634 Part 2.

5Laying Procedures

IS 7634 Part 2: Key Laying Procedures for Pipes

1. Trench Dimensions (Clause 6.1, Table 3)

Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20 - 110300150900 - 1100
125425150900 - 1100
............
10001300150900 - 1100
  • Width may increase for jointing inside trench.
  • Depth measured over pipe crown.
  • Initial backfill: soft earth/gravel free from stones, roots, etc.

2. Backfilling (Clause 8.1.1)

  • Refill trenches up to 300 mm above pipe crown after laying ~1000 m.
  • Use soft earth or sharp-edge stone-free gravel.
  • Borrowed gravel allowed if excavated soil is insufficient.

3. Slack in Laying (Clause 11.4)

  • For PE pipes, up to 2% slack in length is permitted inside trench to accommodate thermal expansion.

Summary Diagram of Trench Cross-Section

graph TD
    A[Ground Surface]
    B[Depth of Cover: 900-1100 mm]
    C[Initial Backfill: 150 mm]
    D[Pipe]
    E[Trench Width per pipe size]

    A --> B --> C --> D
    D --> E

Note: Always consult manufacturer for SDR > 22 pipes under dynamic loads.

6Earth Work and Pipe Support (Trenching)

IS 7634 Part 2: Earth Work and Pipe Support (Trenching) Key Points

1. Trench Dimensions (Table 3)

Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20-110300150900 - 1100
125425150900 - 1100
............
10001300150900 - 1100
  • Width may be increased for jointing inside trench.
  • Depth measured over pipe crown.
  • Initial backfill: 150 mm compacted screened material free of sharp stones or fine sand.

2. Trench Layout (Fig. 12)

  • For non-rocky soil: No sand bedding required, trench width = pipe diameter + 300 mm.
  • For rocky or unconsolidated soil: Provide 100 mm compacted fine sand bedding under and around pipe.

3. Backfill Specifications (Clause 8.1.1)

  • Refill up to 300 mm above pipe with soft earth or gravel free of boulders, roots.
  • Use borrowed gravel if suitable excavated material is insufficient.

4. Special Notes

  • For pipe sizes 20-100 mm using mole-plough, trench width of 300 mm not mandatory.
  • For gravity lines with SDR > 22, consult manufacturers for deformation under traffic loads.
  • PE pipes allow trenchless installation methods (horizontal drilling, micro tunneling).

Summary Formula for Trench Width:

[ \text{Trench Width} = D + 300 \text{ mm (for normal soil)} ]

Where (D) = Pipe diameter.


flowchart LR
    A[Excavate Trench] --> B{Soil Type}
    B -->|No Rocks| C[Width = D + 300 mm]
    B -->|Sharp Rocks| D[100 mm Sand Bedding]
    C --> E[Place Pipe]
    D --> E
    E --> F[Initial Back
7Pipe Support and Expansion Considerations

IS 7634 Part 2: Pipe Support & Expansion Key Points

1. Thermal Expansion Considerations (Clause 7.2.1 & 7.6.1)

  • Coefficient of linear expansion for PE pipes ≈ 14 × that of metal pipes.
  • Thermal movement causes significant expansion/contraction.
  • Supports must allow free axial movement without gripping or distorting the pipe (see Fig. 16: Typical Pipe Clamp).

2. Support Design (Clause 7.2.1)

  • Use pipe clamps that permit sliding to accommodate thermal elongation.
  • Avoid rigid anchoring that induces stress or deformation.

3. Expansion Accommodation (Clauses 7.6.1.1 & 7.6.1.2)

  • Underground pipes: Directional changes naturally absorb expansion.
  • Exposed straight runs: Use expansion loops, bellows, or sliding gland expansion joints.

4. Thermal Expansion Formula

[ \Delta L = L \times \alpha \times \Delta T ]

ParameterDescription
(\Delta L)Change in pipe length (m)
(L)Original pipe length (m)
(\alpha)Coefficient of linear expansion (≈ (1.4 \times 10^{-4} / ^\circ C) for PE)
(\Delta T)Temperature change (°C)

Summary Diagram: Pipe Support for Thermal Expansion

flowchart LR
    A[Exposed PE Pipe] --> B[Pipe Clamp]
    B --> C{Allows Free Movement?}
    C -- Yes --> D[No Distortion, Free Sliding]
    C -- No --> E[Stress & Deformation Risk]
    A --> F[Expansion Loop/Bellows/Sliding Joint]
    F --> G[Absorbs Thermal Expansion]

Remember: Design supports to avoid pipe stress by allowing axial movement and use expansion devices in long exposed runs. Underground pipes rely on directional changes for expansion relief.

8Backfilling and Trench Refilling

IS 7634 Part 2: Backfilling and Trench Refilling Key Points

1. Trench Dimensions (Table 3)

Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20 - 110300150900 - 1100
125 - 1000425 - 1300150900 - 1100
  • Width: Depends on pipe diameter; may increase for jointing.
  • Initial Backfill: 150 mm compacted layer above pipe crown.
  • Depth of Cover: 900 to 1100 mm over pipe crown.

2. Initial Backfill Specifications (Clause 6.4.1)

  • Use screened excavated material free from sharp stones or fine sand.
  • Compact up to 150 mm above pipe crown.

3. Trench Filling (Clause 8.1.1)

  • Refill up to 300 mm above pipe immediately after laying.
  • Use soft earth or gravel free from boulders, roots, vegetable matter.
  • Borrowed gravel can be used if suitable excavated earth is insufficient.

4. Trench Layout (Fig. 12 Summary)

  • For non-rocky soil: No sand bedding required.
  • For rocky/unconsolidated soil: Use 100 mm compacted fine sand bedding under and around pipe.
  • Trench width = Pipe diameter + 300 mm.

Summary Formula for Trench Width:

[ \text{Trench Width} = D + 300 \text{ mm} ] where (D) = pipe diameter.


flowchart TD
    A[Excavation] --> B[Pipe Laying]
    B --> C[Initial Backfill 150 mm]
    C --> D[Compaction of Backfill]
    D --> E[Refilling up to 300 mm above pipe]
    E --> F[Final Trench Refilling]

Note: Always refer to manufacturer's guidelines for pipes with SDR > 22 under dynamic loads.

9Field Testing of Pipeline

IS 7634 Part 2: Field Testing of Pipeline - Key Points & Specifications

1. Testing Procedure (Clause 9)

  • Filling: Slowly fill pipeline with water; vent air via air valves at high points.
  • Stabilization: Leave filled pipeline for 1 hour at ambient temperature (PE pipes).
  • Pressure Application:
    • Test pressure = 1.5 × rated/max design pressure.
    • Apply pressure by continuous pumping at a constant rate.
    • Maintain pressure by adding make-up water during test.
  • Duration: Pressure must remain steady (±5%) for 1.5 hours.
  • No air is allowed for testing; water only.
  • If leakage occurs: Depressurize, relax for 8 hours, then retest.

2. Backfilling Requirements (Clause 8.1.2)

  • Backfill simultaneously on both sides to avoid unequal pressure.
  • Fill trench in layers of 150 mm, first layer watered and compacted.
  • Load on pipe only after 300 mm cover above pipe.
  • Refill to original ground level, allowing for settlement.

3. Trench Dimensions (Table 3, Clause 6.1)

Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20 - 110300150900 - 1100
125 - 200425 - 500150900 - 1100
225 - 400525 - 700150900 - 1100
450 - 1000750 - 1300150900 - 1100

4. Acceptance Criteria

  • No leakage if pressure steady within ±5% for 1.5 hours.
  • Visual inspection of flanged joints during test.

Summary Formula for Test Pressure:

[ P_{\text{test}} = 1.5 \times P_{\text{rated or design}} ]


Visual Concept: Testing Setup

flowchart LR
    A
10Repair of Damaged Pipes and Joints

IS 7634 Part 2: Repair of Damaged Pipes and Joints - Key Points

Repair Methods (Clause 10.2)

  • Best practice: Cut out damaged pipe section and replace with new pipe or pre-fabricated flanged spool.
  • Connection options:
    • Insert type fittings (pressure limited)
    • Electro-fusion fittings
  • Not recommended: Butt fusion welding inside trench due to difficulty in applying facial pressure.
  • Welded joint repair: Remove entire original weld before re-welding; no patch repairs allowed.

Testing (Clause 1.5)

  • Test pressure: 1.5 × rated or max design pressure.
  • Medium: Water only; air testing prohibited.
  • Acceptance: Pressure steady within ±5% for 1.5 hours; no leakage.
  • If failure: Depressurize, relax 8 hours before retest.
  • Safety: Avoid testing outside trench to prevent rupture hazards.

Additional Notes (Clause 2.3)

  • PE pipes withstand short-term loads up to 2.3× working pressure due to visco-elasticity.
  • For velocities >1.5 m/s, surge checks required.

Summary Table: Repair Options

Repair MethodApplicationLimitations
Cut & Replace with Flanged SpoolDamaged pipe sectionsRequires flanged ends
Insert Type FittingsQuick repairPressure limitations apply
Electro-fusion FittingsPermanent joint repairRequires proper welding equipment
Butt Fusion WeldingNot recommended inside trenchDifficult to maintain weld pressure

flowchart LR
    A[Damaged Pipe] --> B{Repair Method}
    B --> C[Cut & Replace with Flanged Spool]
    B --> D[Insert Type Fittings]
    B --> E[Electro-fusion Fittings]
    B --> F[Butt Fusion Welding (Not Recommended)]
    C --> G[Pressure Test (1.5 × Rated)]
    D --> G
    E --> G
    F --> H[Remove Original Weld Fully Before Re-welding]

Remember: No patchwork repairs; always ensure pressure testing with water and adhere to safety protocols.

11General Guidance

IS 7634 Part 2: General Guidance Key Points

1. Trench Dimensions (Clause 6.1 & Table 3)

  • Width and depth of trenches depend on pipe size.
  • Initial backfill: 150 mm minimum.
  • Depth of cover: 900 to 1100 mm above pipe crown.
  • Width examples:
    • Pipe 20-110 mm → Width = 300 mm
    • Pipe 500 mm → Width = 800 mm
    • Pipe 1000 mm → Width = 1300 mm
Pipe Size (mm)Trench Width (mm)Initial Backfill (mm)Depth of Cover (mm)
20-110300150900-1100
500800150900-1100
10001300150900-1100

2. Butt Fusion Welding Parameters (Clause 3.2.1.2 & Table 1)

  • Bead height, heating, jointing, and cooling times vary by nominal wall thickness.
  • Example for 7-12 mm thickness:
    • Bead height: 1.5 mm
    • Heating up: 70-120 s
    • Pressure build-up: 6-8 s
    • Cooling under pressure: 10-16 s
    • Cooling during pressure relaxation: 900 s
Wall Thickness (mm)Bead Height (mm)Heating Up (s)Pressure Build-up (s)Cooling Under Pressure (s)Cooling During Relaxation (s)
Up to 4.50.54556300
7-121.570-1206-810-16900
50-704.0500-70020-2560-802700

12Supply, Packaging, Handling, Storage and Transportation

IS 7634 Part 2: Key Points on Supply, Packaging, Handling, Storage & Transportation of PE Pipes

1. Slack in Laying (Clause 11.4)

  • Slack permitted: Up to 2% slack in pipe length when laid inside trenches.

2. Transportation (Clause 12.4 & 12.4.2)

  • Vehicle supports: Side supports spaced at ~2 m intervals.
  • Supports: Flat, no sharp edges to avoid pipe damage.
  • Securing pipes: Pipes must be effectively strapped to prevent movement.
  • Bundling: Strapping bundles during transit is recommended.

3. General Handling & Storage Guidelines

  • Avoid sharp edges and point loads.
  • Store pipes on flat surfaces.
  • Protect from direct sunlight and extreme temperatures.
  • Use appropriate lifting gear to prevent damage.

Summary Table: Transportation Support & Securing

ParameterSpecification
Side support spacing~2 meters
Support surfaceFlat, no sharp edges
Pipe securing methodEffective strapping/bundling
Slack in layingUp to 2% allowed
flowchart LR
    A[Loading Pipes] --> B[Place on flat supports every 2m]
    B --> C[Ensure supports have no sharp edges]
    C --> D[Strap pipe bundles securely]
    D --> E[Transport carefully to site]

Note: Follow IS 7634 Part 2 and related codes of practice for potable water supply pipes for detailed handling and installation procedures.

13Annexes and Committee Composition

IS 7634 Part 2: Annexes & Committee Composition Summary

Annex A: List of Referred Indian Standards

  • Covers specifications for HDPE pipes, rubber sealing rings, and HDPE fittings.
  • Includes parts for reducers, pipe ends, sandwich flanges, bends, tees, and end caps.
  • Example:
IS No.Title
4984:1995HDPE pipes for potable water supplies
5382:1985Rubber sealing rings for gas/water mains and sewers
8008 (Parts 1-9):2003HDPE fittings specifications (bends, tees, reducers, etc.)

Annex B: Committee Composition (CED 50)

  • Members from Central Institute of Plastic Engineering & Technology, BIS, Public Health Departments, Municipal Corporations, Industry leaders (Reliance, Finolex, GAIL, etc.).
  • Chaired by Dr. S. K. Nayak.
  • Includes representatives from government, research institutes, and private sector.
  • Ensures comprehensive expertise for standard formulation.

Key Specification Highlight (Clause 12.5.5)

  • Storage of polyethylene pipes: Must be on a flat surface free from sharp objects to avoid damage.

Diagram: Committee Structure Overview

graph TD
  A[Plastic Piping Systems Sectional Committee (CED 50)]
  A --> B[Government Organizations]
  A --> C[Research Institutes]
  A --> D[Industry Representatives]
  A --> E[BIS Directorate General]
  
  B --> B1[Public Health Engineering Dept.]
  B --> B2[Municipal Corporations]
  
  C --> C1[Central Institute of Plastic Engineering]
  C --> C2[Central Building Research Institute]
  
  D --> D1[Reliance Industries]
  D --> D2[Finolex Industries]
  D --> D3[GAIL India Ltd]
  
  E --> E1[Member Secretary]
  E --> E2[Convener]

This summary provides the committee makeup and key referenced standards essential for HDPE piping systems per IS 7634 Part 2:2012. For detailed technical formulas or tables, refer to specific clauses or referenced IS standards.

Popular Questions About IS 7634 Part 2

?What are the recommended jointing methods for polyethylene pipes under this standard?

Recommended Jointing Methods for Polyethylene Pipes (IS 7634 Part 2):

  • For small diameter PE pipes (<110 mm) with working pressure ≤ 1.6 MPa, PP compression fittings are generally recommended over fusion jointing (Clause 3.2.5.6).
  • Jointing can be done inside or outside the trench depending on site conditions (Clause 6.4.4). If inside the trench, trench width must be increased for adequate workspace.
  • The standard implies fusion jointing (but does not prefer it for small diameters under 1.6 MPa).
  • Typical jointing methods include:
    • Electrofusion welding
    • Butt fusion welding
    • Socket fusion welding
    • Mechanical compression fittings (especially PP fittings for small diameters)

Summary Table:

Pipe DiameterMax Working PressureRecommended Jointing Method
< 110 mm≤ 1.6 MPaPP Compression Fittings (preferred)
AnyAnyFusion Jointing (Butt, Socket, Electrofusion)
Loading diagram...

This ensures durable, leak-proof joints suitable for potable water supply lines.

?How should trenches be prepared and backfilled for PE pipe installation?

Trench Preparation & Backfilling for PE Pipe (IS 7634 Part 2)

  • Bedding:

    • No special bedding needed except no sharp objects near pipe (Clause 6.3).
    • In rocky areas, provide sand bedding around pipe and compact it to avoid damage.
  • Trench Dimensions:

    • For bends, excavate trench to the desired bend radius (Clause 7.1.2).
    • If jointing inside trench, increase trench width for workspace (Clause 6.4.4).
  • Backfilling:

    • Use selected granular material free from sharp stones for initial backfill up to pipe spring line.
    • Compact carefully to avoid pipe deformation.
    • Remaining backfill can be native soil, compacted in layers.
  • Safety:

    • Avoid exposing black PE pipe to ambient temperature >30°C during installation (Clause 7.1.2).

Typical Trench Section for PE Pipe

Loading diagram...

Summary: Provide clean, compacted sand bedding in rocky areas, avoid sharp objects, ensure trench width for jointing, and backfill carefully to protect PE pipes.

?What precautions are necessary for handling and storing PE pipes to prevent damage?

Precautions for Handling and Storing PE Pipes (IS 7634 Part 2):

  • Storage:

    • Avoid exposure to elevated temperatures and harmful chemicals (e.g., solvents).
    • Prolonged sunlight does not degrade performance but may cause bending due to heat; store pipes on flat surfaces and support adequately.
  • Handling:

    • Avoid dragging pipes over rough or sharp surfaces to prevent abrasion and cuts.
    • Use mechanical equipment for pipes >160 mm diameter during loading/unloading.
    • Unload large pipes using platforms; roll pipes smoothly, do not drop from height.
  • Transportation:

    • Bundle pipes to prevent scratches during long-distance transport.
    • Wrap coils in jute cloth for protection.
  • General:

    • Prevent penetration by sharp objects.
    • Follow safety precautions during all handling operations.
Loading diagram...

These measures ensure pipe integrity and longevity on site.

?How is electro fusion welding performed according to IS 7634 Part 2?

Electro Fusion Welding as per IS 7634 Part 2 (Clause 3.2.3 & 3.2.3.1):

Electro fusion welding joins polyethylene pipes using fittings with embedded resistance wires heated by electric current. The process melts and fuses pipe and fitting materials together.

Stepwise Procedure:

  1. Pipe Preparation:

    • Cut pipe ends squarely.
    • Remove outer film using a scraper.
    • Clean pipe surfaces with recommended cleaner.
    • Mark insertion depth on the pipe.
  2. Assembly:

    • Remove fitting from packaging without touching fusion surfaces.
    • Push pipe firmly into fitting up to the marked depth.
    • Attach second pipe similarly.
    • Fix integrated clamp to prevent movement.
  3. Welding:

    • Use electro fusion machine calibrated to fitting barcode data.
    • Machine heats resistance wires, melting and fusing materials.
    • Monitor fusion indicator on fitting.
    • Remove cables after welding cycle completes.
  4. Cooling:

    • Allow joint to cool as per supplier/barcode instructions before handling.

Key Points:

  • Machine automatically controls heating & cooling.
  • Voltage and timing must match fitting specifications.
  • Suitable for polyethylene pipes with MFR 0.1-1.2 g/10 min at 190°C.

Loading diagram...

This ensures a strong, leak-proof joint as per IS 7634 Part 2.

?What are the procedures for pressure testing and ensuring pipeline integrity?

Pressure Testing & Pipeline Integrity per IS 7634 Part 2

  1. Preparation:

    • Fill pipeline slowly with water, venting air via open air valves at high points.
    • Restrain pipeline section to prevent movement during test.
    • Allow water-filled pipeline to stabilize for 1 hour (PE pipes).
  2. Test Pressure:

    • Apply test pressure = 1.5 × rated or max design pressure.
    • Use continuous pumping at a constant rate.
    • Never use air for testing (water only).
  3. During Test:

    • Maintain pressure by adding make-up water continuously.
    • Flanged joints remain open for visual inspection; fusion joints may be covered.
  4. Acceptance Criteria:

    • Pressure must remain within ±5% of target for 1.5 hours.
    • No leakage indicated if pressure steady.
    • Visual check of flanged connections mandatory.
  5. If Leakage/Failure:

    • Depressurize and allow 8 hours relaxation before re-testing.
  6. Backfilling:

    • Fill trench in 150 mm layers; first layer watered and compacted.
    • Fill both sides simultaneously to avoid unequal pressure.
    • Load on pipe only after 300 mm cover.

Summary Table for Pressure Test

StepRequirement
Test MediumWater only (no air)
Test Pressure1.5 × rated/max design pressure
Stabilization Time1 hour before pressure application
Test Duration1.5 hours at steady pressure
Pressure VariationWithin ±5%
Post-Failure Wait8 hours before retesting
Loading diagram...

This procedure ensures pipeline integrity and safety during commissioning.

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in IS 7634 Part 2. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required