IS 7272 Part 1 (1974) provides recommended labour output constants specifically for general building work in the North Zone of India, covering Punjab, Haryana, Delhi, Uttar Pradesh, and Rajasthan. It offers standardized labour time estimates for various construction activities such as excavation, concrete work, brickwork, plastering, joinery, and finishing, facilitating accurate planning, cost estimation, and productivity assessment for construction professionals operating in this region.
Overview
IS 7272 Part 1 (1974) provides recommended labour output constants specifically for general building work in the North Zone of India, covering Punjab, Haryana, Delhi, Uttar Pradesh, and Rajasthan. It offers standardized labour time estimates for various construction activities such as excavation, concrete work, brickwork, plastering, joinery, and finishing, facilitating accurate planning, cost estimation, and productivity assessment for construction professionals operating in this region.
Audience
Contents
Structure
IS 7272 Part 1 - Scope & Key Specifications
This part of IS 7272 provides recommended labour output constants for various building works in the North Zone, expressed in man-days per unit of work (8 working hours/day).
| Work Description | Unit | Labour Type | Recommended Constant (Days) | Remarks |
|---|---|---|---|---|
| Excavation in hard/dense soil (depth ≤ 1.5 m) | m³ | Mate Mazdoor | 0.06 | Includes removal up to 1 m from edge |
| Excavation in soft/loose soil (trenches ≤ 1.5 m width) | m³ | Mate Mazdoor | 0.05 | Removal up to 1 m away from edge |
| Additional depth 1.5 m to 3 m (hard soil) | m³ | Mate Mazdoor | 0.01 | Extra over base excavation |
| Additional lead beyond 1 m (per 25 m up to 250 m) | m³ | Mate Mazdoor | 0.12 | Extra labour for transport |
| Returning, filling, ramming (layers ≤ 20 cm) | m³ | Mate Mazdoor + Bhisti | 0.02 + 0.02 | Includes watering and levelling |
| Hand mixing cement concrete (40 mm aggregate) | m³ | Mazdoor + Bhisti | 1.0 + 0.1 | Lead assumed up to 30 m |
[ \text{Labour Days} = \text{Quantity of Work} \times \text{Recommended Constant} ]
This standard aids in planning, scheduling, and costing of building projects by providing reliable labour productivity norms.
IS 7272 Part 1: Labour Output Constants Summary
This standard provides labour output constants (in days) for various building tasks, useful for estimating labour requirements.
| Description of Work | Unit | Labour Type | Recommended Constant (Days) | Remarks |
|---|---|---|---|---|
| Excavation & Earthworks | ||||
| a) Excavation in hard/dense soil, depth ≤ 1.5 m | m³ | Mate, Mazdoor | 0.06 (Mate), 0.62 (Mazdoor) | Removal up to 1 m from edge |
| b) Excavation in trenches (soft soil), width ≤ 1.5 m | m³ | Mate, Mazdoor | 0.05 (Mate), 0.50 (Mazdoor) | Removal up to 1 m from edge |
| c) Extra for additional depth 1.5 m to 3 m (hard) | m³ | Mate, Mazdoor | 0.01 (Mate), 0.11 (Mazdoor) | Over item (a) |
| d) Extra for additional depth 1.5 m to 3 m (soft) | m³ | Mate, Mazdoor | 0.01 (Mate), 0.08 (Mazdoor) | Over item (b) |
| e) Extra for lead beyond 1 m up to 50 m | m³ | Mate, Mazdoor | 0.02 (Mate), 0.25 (Mazdoor) | Additional transport lead |
| f) Returning, filling, ramming in layers ≤ 20 cm | m³ | Mate, Mazdoor, Bhisti | 0.02 (Mate), 0.25 (Mazdoor), 0.02 (Bhisti) | Includes watering and levelling |
| Concrete Work | | | | | | a) Hand mixing cement concrete (40 mm agg.) | m³ | Mazdoor, Bhisti | 1.0 (Mazdoor), 0.1 (Bhisti) | Lead of mix assumed up to 30 m | |
IS 7272 Part 1: Recommended Labour Output Constants for General Building Work (North Zone)
This standard provides labour output constants (in days) for various building activities, useful for estimating labour requirements.
| Description of Work | Unit | Labour Type | Recommended Constant (Days) | Remarks |
|---|---|---|---|---|
| Excavation and Earth Works | ||||
| a) Excavation over areas (Hard/dense soil), depth up to 1.5 m, removal up to 1 m from edge | m³ | Mate Mazdoor | 0.06 | - |
| b) Excavation in trenches (Soft/loose soil) for foundations ≤1.5 m width, shafts, wells ≤10 m² plan, depth up to 1.5 m, removal up to 1 m from edge | m³ | Mate Mazdoor | 0.05 | - |
To estimate labour days for excavating 100 m³ of hard soil:
[ \text{Labour Days} = 100 \times 0.06 = 6 \text{ days} ]
For full details, refer to IS 7272 Part 1 Table 1 for other work items and labour constants.
| Description of Work | Unit | Labour (Mate + Mazdoor) | Recommended Constant (Days/ m³) | Remarks |
|---|---|---|---|---|
| a) Excavation in hard/dense soil, depth up to 1.5 m, removal up to 1 m from edge | m³ | Mate + Mazdoor | 0.06 + 0.62 | - |
| b) Excavation in soft/loose soil trenches for foundations ≤1.5 m width, shafts, wells ≤10 m², depth ≤1.5 m, removal up to 1 m from edge | m³ | Mate + Mazdoor | 0.05 + 0.50 | - |
| c) Extra for additional depth 1.5 m to 3 m (hard soil) | m³ | Mate + Mazdoor | 0.01 + 0.11 | Extra over (a) |
| d) Extra for additional depth 1.5 m to 3 m (soft soil) | m³ | Mate + Mazdoor | 0.01 + 0.08 | Extra over (b) |
| e) Extra lead for every additional 25 m beyond 1 m up to 250 m | m³ | Mate + Mazdoor | 0.12 | For soil transport |
| f) Returning, filling, and ramming excavated earth in layers ≤20 cm depth, watering, levelling, lead up to 25 m | m³ | Mate + Mazdoor + Bhisti | 0.02 + 0.25 + 0.02 | Includes watering and well ramming |
[ \
IS 7272 Part 1 (1974) - Key Concrete Works Labour Output Constants
| Work Description | Unit | Labour Type | Recommended Constant (Days) | Remarks |
|---|---|---|---|---|
| Mixing by hand at banker, cement concrete (40mm aggregate) | m³ | Mazdoor, Bhisti | 1.0, 0.1 | Lead of concrete mix assumed up to 30 m |
| Mixing by machine (mixer), cement concrete (20mm aggregate) | m³ | Mazdoor, Bhisti, Mixer operator | 0.50, 0.10, 0.07 | |
| Unreinforced concrete in foundations (hand mixed) | m³ | Mason, Mazdoor, Bhisti | 0.10, 2.13, 0.70 | Includes mixing, pouring, consolidating, curing |
| Reinforced cement concrete in situ (foundations, footings, bases) | m³ | Mason, Mazdoor, Bhisti, Mixer operator, Vibrator | 0.17, 2.00, 0.90, 0.07, 0.07 | Includes mixing, pouring, consolidating, curing; excludes formwork & reinforcement |
| Reinforced cement concrete in beams, columns, stairs | m³ | Various | 0.20 to 0.30 (Mason), 3.0 to 4.3 (Mazdoor), others as above | Same exclusions as above |
| Mortars (hand mixed cement mortar) | m³ | Mazdoor, Bhisti | 0.75, 0.07 | Labour approx. same for different mix proportions |
| Mortars (hand mixed cement-lime mortar) | m³ | Mazdoor, Bhisti, Bullock with driver | 1.33, 0.10, 0.33 |
| Description | Unit | Mason (days) | Mazdoor (days) | Bhisti (days) | Remarks |
|---|---|---|---|---|---|
| Brick work in walls > 1 brick thick, in cement/lime mortar | m³ | 0.94 | 1.80 | 0.20 | Includes labour |
[ \text{Brick Work Volume} = \text{Length} \times \text{Height} \times \text{Thickness} ]
[ \text{Labour Days} = \text{Volume} \times \text{Labour Constant (days/m}^3) ]
Where labour constant for mason = 0.94 days/m³ (from IS 7272 Part 1)
flowchart TD
A[Brick Work Volume] --> B[Calculate Labour Days]
B --> C{Labour Constants}
C -->|Mason| D[0.94 days/m³]
C -->|Mazdoor| E[1.80 days/m³]
C -->|Bhisti| F[0.20 days/m³]
D & E & F --> G[Total Labour Estimation]
Summary: Use labour constants from IS 7272 Part 1 Table 1 (Mason 0.94 days/m³) for straight brick walls
IS 7272 Part 1 - Plastering and Pointing: Key Specifications & Labour Constants
| Work Description | Unit | Mason (days) | Mazdoor (days) | Remarks |
|---|---|---|---|---|
| 15 mm thick cement plaster on ceilings | m² | ~0.07 | ~0.10 | Includes mixing mortar |
| 15 mm thick cement plaster on brick walls (ext.) | m² | ~0.10 | ~0.15 | Includes mixing mortar |
| Struck pointing to brickwork | m² | ~0.05 | ~0.07 | Includes mixing mortar |
| Tuck pointing to rubble masonry | m² | ~0.06 | ~0.08 | Includes mixing mortar |
[ \text{Labour Days} = \text{Area (m}^2) \times \text{Labour Constant (days/m}^2) ]
flowchart LR
A[Surface Preparation] --> B[Mixing Mortar]
B --> C[Applying Plaster/Pointing]
C --> D[Finishing & Curing]
This concise guide helps estimate labour and understand plastering/pointing specifications per IS 7272 Part 1.
IS 7272 Part 1 (1974) - Paving and Floor Finish: Key Labour Output Constants
| Description of Work | Unit | Labour Type | Recommended Constant (Days per m²) | Remarks |
|---|---|---|---|---|
| Laying PCC 25 mm thick in alternate bays with side forms and templates, finished smooth | m² | Mason | 0.07 | - |
| Mazdoor | 0.10 | - | ||
| Bhisti | 0.10 | - | ||
| Laying 40 mm thick in situ terrazzo flooring (30 mm cement concrete underlayer + 10 mm marble chips top layer with dividing strips) including cutting, grinding, polishing | m² | Mason | 0.22 | - |
| Mazdoor | 0.22 | - | ||
| Bhisti | 0.10 | - | ||
| Cutting, grinding, and polishing terrazzo flooring | m² | Mazdoor | 0.50 | - |
| Machine Operator | 0.40 | - | ||
| Laying 20 mm thick in situ terrazzo skirting/dado (13 mm cement plaster underlayer + 7 mm marble chips top layer) including rounding junctions, cutting, grinding, polishing | m² | Mason | 0.30 | - |
| Mazdoor | 0.90 | - | ||
| Bhisti | 0.10 | - | ||
| Cutting, grinding, and polishing terrazzo skirting/dado | m² | Mazdoor | 0.70 | - |
| Precast terrazzo tile flooring 20 mm thick laid over 10 mm cement mortar | m² | Mason | 0.12 | - |
| Mazdoor | 0.20 | - | ||
| Bhisti | 0.10 | - | ||
| Cutting, grinding, and polishing precast terrazzo tiles | m² | Mason | 0.50 | - |
| Mazdoor | 0.40 | - |
Additional Notes:
IS 7272 Part 1 - Damp-proof Course (DPC) Key Specifications & Labour Constants
DPC Thickness:
Materials:
Work Includes:
| Work Description | Unit (m²) | Mason (days) | Mazdoor (days) | Bhisti (days) | Remarks |
|---|---|---|---|---|---|
| a) Laying 10 mm thick cement concrete DPC | m² | 0.10 | 0.10 | 0.01 | Includes formwork |
| b) Laying 20 mm thick cement mortar DPC with integral waterproofing | m² | 0.10 | 0.10 | 0.01 | Includes mixing |
flowchart TD
A[Excavation for DPC] --> B[Mixing Cement Concrete/Mortar]
B --> C[Laying DPC Layer (10 or 20 mm)]
C --> D[Finishing Edges & Surface]
D --> E[Curing & Protection]
Summary:
Use 10 mm cement concrete or 20 mm cement mortar with waterproofing compound as DPC. Labour constants per m² are approx. 0.10 days for masons and mazdoors, 0.01 days for bhisti. Follow proper mixing, laying, finishing, and curing for effective damp-proofing.
IS 7272 Part 1 (1974) - Joinery Key Specifications and Labour Constants
| Description of Work | Unit (m²) | Labour Type | Recommended Labour Constant (Days) | Remarks |
|---|---|---|---|---|
| a) Door & window CHOKHATS (coniferous & teak, wrought & rebated) | m² | Carpenter | 20.00 | Labour excludes Mazdoor |
| Mazdoor | 2.00 | - | ||
| b) Panelled/glazed joinery (30 to 10 mm thick, tenoned joints) | m² | Carpenter | 0.90 | Includes Mazdoor: 0.10 days |
| c) Fixing readymade shutters to frames with fittings | m² | Carpenter | 0.25 | Includes Mazdoor: 0.25 days |
flowchart TD
A[Prepare Door/Window Frames] --> B[Panelled/Glazed Joinery]
B --> C[Fixing Shutters]
C --> D[Fixing Fittings]
D --> E[Final Inspection]
This table and workflow assist in scheduling and resource allocation for joinery tasks per IS 7272 Part 1.
Glazing Work (Clause xi):
| Description | Unit | Labour Category | Labour Constant (Days) |
|---|---|---|---|
| Fixing glass panes with putty | m² | Glazier | 0.20 |
| Mazdoor | 0.10 |
flowchart TD
A[Prepare Frame] --> B[Apply Putty Bed]
B --> C[Place Glass Pane]
C --> D[Press Glass into Putty]
D --> E[Apply Finishing Putty]
E --> F[Curing & Cleaning]
For detailed glass specifications (thickness, size limits), refer to IS 2553 and IS 1038 series. IS 7272 Part 1 primarily provides labour constants for estimating man-days in glazing work.
IS 7272 Part 1 (1974) - Painting and Polishing Key Details
| Description of Work | Unit | Labour Category | Recommended Constant (Days per m²) |
|---|---|---|---|
| French polishing including wood filler coat | m² | Painter | 0.35 |
| White washing (lime, 3 coats on new surface) | m² | Washer, Mazdoor | 0.02, 0.01 |
| Colour washing (2 coats over white wash) | m² | Washer, Mazdoor | 0.03, 0.01 |
| Distempering (dry distemper, 3 coats incl. priming) | m² | Painter, Mazdoor | 0.08, 0.04 |
| Cement-based paint (2+ coats on new work) | m² | Painter, Mazdoor, Bhisti | 0.15, 0.01, 0.10 |
| Work Type | Labour (Painter) | Labour (Mazdoor) | Labour (Bhisti) | Remarks |
|-----------------------|------------------|------------------|-----------------|------------------------|
| French Polishing | 0.35 | - | - | Includes wood filler |
| White Washing (3 coats)| 0.02 | 0.01 | - | New surface |
| Colour Washing (2 coats)| 0.03 | 0.01 | - | Over white wash |
| Distempering (3 coats) | 0.08 | 0.04 | - | Includes priming coat |
| Cement Paint (per coat)| 0.15 | 0.01 | 0.10
IS 7272 Part 1 - White Washing and Colour Washing
| Work Description | Unit (m²) | Labour Type | Labour Constant (Days) |
|---|---|---|---|
| a) White washing with lime (3 coats) on new surface | m² | Washer | 0.02 |
| Mazdoor | 0.01 | ||
| b) Two coats of colour wash over an undercoat of white wash on new work | m² | Washer | 0.03 |
| Mazdoor | 0.01 |
[ \text{Lime required} = 1.5 \text{ kg per m}^2 \text{ per coat} ]
For 3 coats:
[ \text{Total lime} = 1.5 \times 3 = 4.5 \text{ kg/m}^2 ]
flowchart TD
A[Surface Preparation] --> B[Apply 3 coats Lime White Wash]
B --> C[Allow Drying Between Coats]
C --> D[Apply 2 coats Colour Wash]
D --> E[Finished Surface]
Summary:
IS 7272 Part 1 provides labour output constants for white and colour washing as 0.02 and 0.03 days per m² respectively for washers, with additional labour for mazdoors. Use 3 coats lime white wash and 2 coats colour wash over it for new surfaces.
IS 7272 Part 1 Amendment No. 1 (Feb 1979) - Key Specifications & Labour Output Constants
This amendment revises labour output constants and clarifies units in IS 7272 Part 1 (1974) for North Zone building work.
Units Correction:
Labour Output Constants (Selected Examples):
| Work Description | Unit | Labour Type | Recommended Constant (days) | Remarks |
|---|---|---|---|---|
| Excavation in hard/dense soil (depth ≤ 1.5 m) | m³ | Mate + Mazdoor | 0.06 (Mate), 0.62 (Mazdoor) | Removal up to 1 m from edge |
| Excavation in soft/loose soil (trenches ≤1.5 m width) | m³ | Mate + Mazdoor | 0.05 (Mate), 0.50 (Mazdoor) | Removal up to 1 m from edge |
| Extra lead for excavation (per 25 m beyond 1 m) | m³ | Mate + Mazdoor | 0.02 (Mate), 0.25 (Mazdoor) | Lead up to 250 m |
| Returning, filling, ramming in layers ≤ 20 cm, watering | m³ | Mate + Mazdoor + Bhisti | 0.02 (Mate), 0.25 (Mazdoor), 0.02 (Bhisti) | Lead up to 50 m |
| Mixing cement concrete by hand (with 40 mm aggregate) | m³ | Mazdoor + Bhisti | 1.0 (Mazdoor), 0.1 (Bhisti) | Lead assumed up to 30 m |
| Unreinforced concrete in foundations (mixing, pouring) | m³ | Mason + Mazdoor + Bhisti | 0.10 (Mason), 2.13 (Mazdoor), 0.70 (Bhisti) | Depth up to 3 m |
| Formwork with wooden pl |
Frequently Asked
Detailed content not available.
Detailed content not available.
According to IS 7272 Part 1 (1974), Clause 1.5, Table 1, the recommended labour times for mixing and placing reinforced concrete are as follows (per cubic meter):
| Activity | Labour Category | Labour Constant (Days) |
|---|---|---|
| Mixing by hand at banker (cement concrete, 40 mm aggregate) | Mazdoor + Bhisti | 1.0 + 0.1 |
| Mixing by machine at banker (cement concrete, 20 mm aggregate) | Mazdoor + Bhisti + Mixer operator + Mixer | 0.50 + 0.10 + 0.07 + 0.07 |
| Reinforced cement concrete in situ in foundations, footings, bases (excluding formwork and reinforcement) | Mason + Mazdoor + Bhisti + Mixer operator + Mixer + Vibrator | 0.17 + 2.00 + 0.90 + 0.07 + 0.07 + 0.07 |
Notes:
This provides a practical guide to estimate labour days for reinforced concrete works on-site.
Yes, IS 7272 Part 1 provides labour constants separately for different trades such as masons, carpenters, painters, mazdoors, bhistis, and glaziers.
| Work Description | Unit | Labour Type | Labour Constant (Days) |
|---|---|---|---|
| Door and window CHOKHATS | m² | Carpenter | 20.00 |
| 15 mm cement plaster on brick walls | m² | Mason | 0.10 - 0.30 |
| French polishing | m² | Painter | 0.35 |
| White washing 3 coats | m² | Washer | 0.02 |
If you need constants for a specific trade or work item, please specify!
To improve construction project planning in the North Zone using IS 7272 Part 1 labour output constants:
[ \text{Labour Required} = \frac{\text{Total Quantity of Work}}{\text{Labour Output Constant (units per worker per day)}} ]
This systematic approach enhances resource allocation, reduces delays, and controls costs for projects in the North Zone.
Ask AI about any clause, requirement, or provision in IS 7272 Part 1. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required