IS 6061 Part 2 (1981) provides a detailed code of practice for constructing floors and roofs using precast reinforced concrete joists combined with hollow clay filler blocks. It guides engineers and builders on design, materials, casting, handling, and installation to achieve lightweight, thermally insulated, and acoustically efficient floor and roof systems. This standard is essential for professionals involved in building construction where hollow clay filler blocks are preferred for floor and roof assemblies.

7Sections
60Clauses Indexed
AI Search Ready
1981Edition
Building Construction Practices including Painting Varnishing and Allied FinishingCategory
Alternative search terms: IS 6061 Part 2 PDF, IS 6061 Part 2 pdf free download, IS 6061 Part 2 free download pdf, IS6061Part2 PDF, IS-6061-Part-2 PDF, IS 6061 Part 2 1981 PDF, IS 6061 Part 2:1981 PDF, IS 6061 Part 2-1981 PDF, IS 6061 Part 2 (1981) PDF, IS 6061 Part 2 1981 edition PDF, IS 6061 Part 2 edition 1981 PDF

What This Standard Covers

IS 6061 Part 2 (1981) provides a detailed code of practice for constructing floors and roofs using precast reinforced concrete joists combined with hollow clay filler blocks. It guides engineers and builders on design, materials, casting, handling, and installation to achieve lightweight, thermally insulated, and acoustically efficient floor and roof systems. This standard is essential for professionals involved in building construction where hollow clay filler blocks are preferred for floor and roof assemblies.

Who Uses This Standard

  • Structural Engineers
  • Civil Engineers
  • Construction Managers
  • Architects
  • Precast Concrete Manufacturers
  • Building Contractors
  • Quality Control Inspectors

Key Topics Covered

Design and spacing of precast RCC and prestressed concrete joists
Specifications for hollow clay filler blocks
Materials requirements including cement, aggregates, and reinforcement
Casting, curing, and handling of precast concrete joists
Installation procedures for joists and filler blocks
Topping concrete slab design and reinforcement
Storage, transport, and protection of construction materials
Load considerations and span limitations
Thermal and sound insulation benefits
Finishing options for floors and ceilings
Safety and quality control measures
Integration with supporting structural elements
Guidance on joint treatment and openings
References to related Indian Standards for materials and finishes

Table of Contents

1Scope

IS 6061 Part 2 – Scope Summary

Scope:
IS 6061 Part 2 primarily covers specifications and code of practices related to flooring and roofing materials including structural clay products, bitumen mastic flooring, rubber floors, linoleum, terrazzo, cement concrete tiles, epoxy resin toppings, PVC sheet flooring, burnt clay brick flooring, and waterproofing techniques.


Key Points from the Scope:

  • Referenced Standards:

    • IS 2248-1969 (Definitions for structural clay products)
    • IS 3951 (Part I)-1975 (Specifications for hollow clay tiles)
  • Information Exchange:
    Clause 3.3 emphasizes the importance of proper communication between designer, builder, and user throughout construction.

  • Code of Practices Included:

    • Bitumen mastic flooring
    • Rubber floors
    • Linoleum floors
    • Cement concrete flooring tiles
    • Terrazzo floor finish
    • Flat roof finish (Mud Phuska)
    • In situ cement concrete flooring
    • Epoxy resin floor toppings
    • Flexible PVC flooring
    • Burnt clay brick flooring
    • External rendered finishes
    • Cement and cement-lime plaster finishes
    • Waterproofing with bitumen felts and polyethylene film
    • Lime concrete for waterproofed roofs

Typical Application Flow (Mermaid Diagram):

flowchart LR
    A[Designer] --> B[Specify Material & Flooring Type]
    B --> C[Builder]
    C --> D[Construction Stage]
    D --> E[User]
    E --> F[Feedback & Maintenance]
    F --> A

Summary:

  • IS 6061 Part 2 sets material and workmanship standards for various flooring and roofing finishes.
  • Ensures uniformity and quality in construction.
  • Facilitates coordination among stakeholders for successful project delivery.

For detailed formulas or tables, refer to the specific part or code of practice within IS 6061 Part 2 related to the material or flooring type of interest.

2Definitions

IS 6061 Part 2 – Definitions & Key Information

  • Definitions: As per Clause 2.1, definitions are adopted from:

    • IS 2248-1969: Glossary of terms for structural clay products.
    • IS 3951 (Part I)-1975: Specification for structural hollow clay tiles (filler type).
  • Key Information for Design (Clause 3.1): For designing hollow clay filler block roofs/floors, gather:

    • Total area and individual room/column grid sizes.
    • Details of supporting elements (framed structure or load-bearing walls).
    • Superimposed loads.
    • Finished floor/roof level.
    • Junction treatments with walls/parapets.
    • Roof slope for drainage.
    • Fixing provisions for services and ceilings.
    • Openings in the floor/roof.
  • Communication (Clause 3.3): Ensure proper info exchange between designer, builder, and user at all construction stages.


Summary Table: Essential Design Inputs

ParameterDescription
AreaTotal coverage and room sizes
SupportType, dimensions, restrictions
LoadsSuperimposed loads on floor/roof
LevelFinished floor/roof elevation
JunctionsTreatment with walls/parapets
SlopeFor drainage purposes
Fixing ProvisionsFor services, ceiling attachments
OpeningsSize and location in floor/roof
flowchart LR
    A[Designer] --> B[Builder]
    B --> C[User]
    C --> A
    style A fill:#f9f,stroke:#333,stroke-width:2px
    style B fill:#bbf,stroke:#333,stroke-width:2px
    style C fill:#bfb,stroke:#333,stroke-width:2px

This cycle ensures smooth coordination throughout construction per IS 6061 Part 2.

3Necessary Information for Design and Construction

IS 6061 Part 2 – Necessary Information for Design and Construction

For efficient design and construction of hollow clay filler block floors/roofs, the following key information must be provided (Clause 3.1):

  • Total area to be covered
  • Individual room sizes or column grid dimensions
  • Supporting elements: framed structure or load-bearing walls, including their dimensions and restrictions
  • Superimposed loads: live, dead, and imposed loads to be carried
  • Finished floor/roof level
  • Details of junctions: connections with walls or parapets
  • Slope provision: for roof drainage
  • Provisions for fixing: services, ceilings, etc.
  • Openings: size and location in floor or roof

Additional guidelines:

  • Ensure proper exchange of information among designer, builder, and user at all construction stages (Clause 3.3).
  • Follow rounding rules for numerical values as per the standard.

This data ensures safe, functional, and durable floor/roof design per IS 6061 Part 2.

flowchart TD
    A[Design Requirements] --> B[Area & Room Sizes]
    A --> C[Support Details]
    A --> D[Load Specifications]
    A --> E[Finished Level]
    A --> F[Junction Treatments]
    A --> G[Slope for Drainage]
    A --> H[Fixing Provisions]
    A --> I[Openings]
    A --> J[Information Exchange]
4Materials

IS 6061 (Part 2) - 1981: Materials Key Points

This part of IS 6061 primarily references materials related to structural clay products and flooring finishes, with specifications and codes of practice for various materials and finishes.

Key Specifications & References:

  • Structural Hollow Clay Tiles: Specification for filler type tiles used in floors and roofs (Part I, first revision).
  • Material Definitions: As per IS 2248-1969 and IS 3951 (Part I)-1975 for clay products.
  • Flooring Materials: Codes of practice exist for:
    • Bitumen mastic flooring
    • Rubber floors
    • Linoleum floors
    • Cement concrete flooring tiles
    • In situ terrazzo and cement concrete flooring
    • Epoxy resin floor toppings
    • Flexible PVC sheet and tile flooring
    • Burnt clay brick flooring
  • Roof Finishes & Waterproofing:
    • Flat roof finish (Mud Phuska)
    • External rendered finishes
    • Cement and cement-lime plaster finishes
    • Waterproofing with bitumen felts and polyethylene films
    • Lime concrete for waterproofed roof finish

Important Notes:

  • Material exchange between designer, builder, and user is emphasized (Clause 3.3).
  • Rounding off numerical values must follow revised rules.
  • Refer to respective IS codes for detailed material properties and mix designs.

Typical Material Properties for Structural Clay Tiles (from IS 2248):

PropertyValue (Typical)
Compressive Strength≥ 3.5 N/mm²
Water Absorption≤ 15%
Modulus of Rupture≥ 1.0 N/mm²

Example: Bitumen Mastic Flooring Composition

  • Bitumen: 60-70%
  • Filler (sand, stone dust): 30-40%
  • Thickness: 6-10 mm

flowchart LR
    Designer -->|Material specs| Builder
    Builder -->|Material info| User
    User -->|Feedback| Designer

This ensures proper communication of material requirements and quality control during construction.

5Precast Concrete Joists and Hollow Clay Filler Blocks Floor or Roof

IS 6061 Part 2: Precast Concrete Joists & Hollow Clay Filler Blocks Floor/Roof

Key Components (Clause 5.1.1)

  • Precast RCC prestressed joists spaced suitably.
  • Hollow clay filler blocks placed between joists.
  • Cast-in-situ topping concrete with reinforcement.
  • Floor finish on top.
  • Ceiling finish below (optional).

Joist Dimensions (Clause A-1.1)

  • Uniform width.
  • Length & depth vary with span and filler block depth.

Hollow Clay Blocks Placement (Clause 5.5.4)

  • Blocks rest on projecting lips of joists (see Fig. 1).
  • Ensures load transfer and stability.

Typical Section (Fig. 1)

graph TD
    A[Floor Finish] --> B[Topping Concrete (cast-in-situ)]
    B --> C[Hollow Clay Filler Blocks]
    C --> D[Precast RCC Joists]
    D --> E[Ceiling Finish (optional)]

Design & Specifications Reference

  • Use IS 383 for aggregates.
  • Use IS 269/IS 455/IS 1489 for cement types.
  • Use IS 432/IS 1786 for reinforcement steel.
  • Hollow clay blocks per IS 4885 Part I.

Important Notes

  • Joist spacing depends on load & span.
  • Topping thickness typically 40-50 mm.
  • Reinforcement in topping to control cracking.
  • Ensure proper bearing of blocks on joists for load transfer.

For detailed design, refer to IS 6061 Part 2 tables and span charts specific to joist sizes and block dimensions.

6Finishing of Floor and Ceiling

IS 6061 Part 2 (1981) — Finishing of Floor and Ceiling

Key Specifications (Clause 6.1 & 6.1.1)

  • Floors/roofs are finished per relevant IS codes (see table below).
  • Floor finish types and their IS codes:
Finish TypeIS Code
Bitumen masticIS 1196-1971
RubberIS 1197-1970
LinoleumIS 1198-1958
Cement concrete tilesIS 1443-1972
TerrazzoIS 2114-1962
Mud PhuskaIS 2115-1980
In situ cement concreteIS 2571-1970
Epoxy resinIS 4631-1968
PVCIS 5318-1969
BrickIS 5766-1970

Structural Composition (Clause 5.1.1)

  • Precast prestressed concrete joists spaced suitably.
  • Hollow clay filler blocks between joists.
  • In situ topping concrete with reinforcement over blocks.
  • Floor finish applied on top.
  • Ceiling finish optionally applied below.

Typical Floor Section (Mermaid Diagram)

graph TD
    A[Ceiling Finish (optional)] --> B[Precast Prestressed Concrete Joists]
    B --> C[Hollow Clay Filler Blocks]
    C --> D[Topping Concrete with Reinforcement]
    D --> E[Specified Floor Finish]

Notes:

  • Refer to respective IS codes for detailed material specs and application methods.
  • Reinforcement and topping thickness depend on load and span (see IS 456 for concrete design).

This framework ensures durable, standardized floor and ceiling finishes per Indian standards.

Appendix APrecast Reinforced Concrete Joists - Casting, Curing and Handling

Key Specifications for Precast Reinforced Concrete Joists (IS 6061 Part 2)

1. Reinforcement (Clause 2.2)

  • Follow IS 456-1978 for reinforced concrete or IS 1343-1980 for prestressed concrete reinforcement.
  • Reinforcement detailing must ensure adequate bonding, anchorage, and spacing.

2. Dimensions (Clause 1.1)

  • Joists must have uniform width.
  • Length and depth vary based on:
    • Span length
    • Depth of filler blocks

3. Casting, Curing, and Maturing (Clause A-3 & 4.4)

  • Casting: Use proper formwork ensuring dimensional accuracy.
  • Curing: Maintain moisture for at least 7 days (preferably 14) to achieve desired strength.
  • Maturing: Allow adequate time before handling or stressing (for prestressed joists).

4. Handling and Placement (Clause 5.5.1)

  • Place joists at designed spacing.
  • Joists should span between supporting elements like walls or beams.
  • Use proper lifting devices to avoid damage.

Typical Curing Time & Strength Gain (IS 456 Reference):

Age (Days)% of 28-day Strength
340-50%
765-75%
1490-95%
28100%

Basic Handling Guidelines:

  • Avoid sudden shocks.
  • Support joists uniformly during storage.
  • Stack with spacers to prevent deformation.
flowchart LR
    A[Casting] --> B[Curing (7-14 days)]
    B --> C[Maturing]
    C --> D[Handling & Storage]
    D --> E[Placement at Site]

For detailed reinforcement and mix design, refer to IS 456 and IS 1343.

Popular Questions About IS 6061 Part 2

?What are the recommended dimensions and spacing for precast concrete joists?

IS 6061 Part 2 provides the following guidance on precast concrete joists:

  • Width: Joists shall be of uniform width (Clause 1.1).
  • Length & Depth: Vary according to the span and the depth of filler blocks (Clause 1.1).
  • Spacing: Joists must be placed at the designed spacing to span between supporting elements like walls and beams (Clause 5.5.1).
  • Design: Follow IS 456-1978 for reinforced concrete and IS 1343-1980 for prestressed concrete joists (Clause 5.2.3).
  • Detailed Dimensions: Refer to Appendix A of IS 6061 Part 2 for specific dimensional recommendations.

Typical Practice (based on IS 6061 & IS 456):

ParameterTypical Range
Width of Joist100 mm to 150 mm (uniform)
Depth of JoistDepends on span (e.g., 150 mm to 300 mm)
Spacing between Joists450 mm to 600 mm (center to center)
SpanUsually up to 4.5 m for precast joists

Note: Exact dimensions depend on load, span, and filler block depth.

Loading diagram...

For detailed design, always consult Appendix A of IS 6061 Part 2 and relevant IS codes.

?Which Indian Standards specify the quality requirements for hollow clay filler blocks?

Quality requirements for hollow clay filler blocks are specified in:

  • IS 3951 (Part 1) - 1975: This standard covers the specifications for hollow clay blocks or tiles used as filler blocks in floor and roof construction.

  • IS 6061 (Part 2) - 1981: Code of practice for construction of floor and roof with joists and filler blocks specifically using hollow clay filler blocks. It references IS 3951 for quality requirements and provides construction guidelines.

Summary:

StandardPurpose
IS 3951 (Part 1)Quality and specifications for hollow clay blocks
IS 6061 (Part 2)Code of practice for floors/roofs with hollow clay filler blocks

Key points from IS 6061 Part 2:

  • Hollow clay filler blocks must conform to IS 3951.
  • Construction method involves RCC joists spaced and gaps filled with hollow clay blocks.
  • Provides lighter weight, thermal and sound insulation.
  • Not recommended for floors subjected to impact or vibration.
Loading diagram...

In brief: Use IS 3951 for block quality and IS 6061 Part 2 for construction practice with hollow clay filler blocks.

?How should the precast joists be cast, cured, and handled to ensure durability?

To ensure durability of precast joists per IS 6061 Part 2, follow these steps:

Casting

  • Cast joists on a level, shaded platform protected from sun and wind (Clause 3.1).
  • Treat inner mould surfaces and bottom to aid removal and ensure smooth finish (Clause 3.3).
  • Place and secure reinforcement correctly for proper concrete cover.
  • Fill mould gradually and compact using vibration.
  • Leave stirrups projecting above mould top for bonding with concrete topping.

Curing

  • Do not release mould sides before 24 hours; remove carefully without shock (Clause 3.4).
  • Keep joists damp by spraying water for 24 hours at casting location.
  • After initial strength gain, move joists to curing yard.
  • Maintain continuous moisture for at least 7 days from casting date.

Handling and Storage

  • After curing, store joists in a shady place.
  • Allow drying for minimum 3 weeks before use (Clause 3.5).

Summary Table

StepTime/Condition
Mould release≥ 24 hours after casting
Initial curingKeep damp 24 hours at casting site
Main curingMoist curing for ≥ 7 days
DryingStore shaded, dry for ≥ 3 weeks

This process ensures strength development, surface quality, and durability of precast joists.

?What reinforcement is required for the topping concrete slab over the filler blocks?

According to IS 6061 Part 2, Clause 5.5.5 and referencing IS 456-1978, the reinforcement for the topping concrete slab over filler blocks should be:

  • Along the joists: Minimum 0.15% steel area
  • Across the joists: Minimum 0.20% steel area
  • Bar spacing: Not more than 300 mm
  • Reinforcement over supports: Should be tied to stirrups projecting from the joists to ensure composite action

Additional points:

  • Welded wire mesh can be used as an alternative to mild steel bars.
  • Minimum topping thickness is 50 mm (Clause 5.2.5).
  • Blocks must be wetted before placing topping concrete and cured for at least 7 days (Clause 5.5.6).

This reinforcement ensures the topping acts structurally with joists, functioning as a T-beam system.

Loading diagram...
?Are there any limitations on the maximum span and load conditions for this construction method?

IS 6061 Part 2 - Maximum Span and Load Limitations

  • Maximum Span: As per Clause 5.2.2, the maximum span of precast reinforced or prestressed concrete joists shall not normally exceed 6 m.
  • Load Conditions: Joists must be placed at designed spacing and span between supporting elements like walls or beams (Clause 5.5.1). Load design should consider:
    • Self-weight of joists and hollow clay filler blocks.
    • Topping concrete and floor finishes.
    • Imposed loads as per relevant IS codes (e.g., IS 875 for live loads).
  • Handling & Storage: Careful lifting and stacking to avoid damage (Clause 4.1) is essential to maintain structural integrity.

Summary Table:

ParameterLimit/Condition
Max Joist Span6 m (normally)
Joist SpacingAs per design
SupportsWalls, beams
Load TypesSelf-weight + imposed loads
HandlingFollow designer's instructions

This ensures safe, durable construction using precast joists per IS 6061 (Part 2).

Loading diagram...

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in IS 6061 Part 2. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required