Code of practice for laying flexible PVC sheets and tile flooring
IS 5318-1969 provides comprehensive guidelines for the proper laying of flexible PVC sheets and tile flooring, focusing on preparation of sub-floors, selection of adhesives, installation techniques, and maintenance practices. This code of practice is essential for engineers, contractors, and flooring specialists involved in installing resilient PVC flooring in residential, commercial, and institutional buildings to ensure durability, moisture resistance, and aesthetic quality.
9Sections
111Clauses Indexed
✓AI Search Ready
1969Edition
Flooring Wall Finishing and RoofingCategory
Alternative search terms: IS 5318 PDF, IS 5318 pdf free download, IS 5318 free download pdf, IS5318 PDF, IS-5318 PDF, IS 5318 1969 PDF, IS 5318:1969 PDF, IS 5318-1969 PDF, IS 5318 (1969) PDF, IS 5318 1969 edition PDF, IS 5318 edition 1969 PDF
Overview
What This Standard Covers
IS 5318-1969 provides comprehensive guidelines for the proper laying of flexible PVC sheets and tile flooring, focusing on preparation of sub-floors, selection of adhesives, installation techniques, and maintenance practices. This code of practice is essential for engineers, contractors, and flooring specialists involved in installing resilient PVC flooring in residential, commercial, and institutional buildings to ensure durability, moisture resistance, and aesthetic quality.
Audience
Who Uses This Standard
Civil Engineers
Flooring Contractors
Architects
Interior Designers
Building Maintenance Professionals
Construction Project Managers
Quality Inspectors
Contents
Key Topics Covered
✓Sub-floor preparation and moisture control
✓Types of suitable adhesives for PVC flooring
✓Laying and fixing procedures for PVC sheets and tiles
✓Handling and acclimatization of PVC flooring materials
✓Alignment and joint treatment techniques
✓Damp-proofing and waterproofing methods
✓Surface finishing and protective edging
✓Cleaning and maintenance of PVC floors
✓Testing methods for sub-floor dryness
✓Use of underlays and screed toppings
✓Treatment of timber, concrete, and metal sub-floors
✓Guidelines for air-conditioned environments
Structure
Table of Contents
1Scope▼
IS 5318: Scope and Key Specifications
Scope: IS 5318 covers specifications for PVC (vinyl) asbestos floor tiles and flexible PVC flooring, focusing on materials, thickness, and testing requirements.
Thickness:
Clause 3.1.1: Thickness depends on service conditions (load, usage). No fixed thickness; select based on application.
Materials (Clause 2.1):
Glass sheet (~30x30 cm) or rubber mat or polyethylene sheet (≥0.1 mm thick) or PVC flooring sheet (~60x60 cm).
Putty, adhesive plasticine, or suitable mastic for sealing edges during testing.
Rounding Off Values (Clause 0.6):
Final test or calculation values must be rounded per IS 2-1960 rules.
Retain the same number of significant digits as specified in the standard.
Summary Table for Flooring Thickness (Typical Guidance)
Service Condition
Approximate Thickness (mm)
Light domestic use
2.0 – 2.5
Medium commercial use
3.0 – 4.0
Heavy industrial use
4.5 – 6.0
Note: Refer to detailed service conditions in the full code for exact thickness.
flowchart TD
A[Service Conditions] --> B[Select Flooring Thickness]
B --> C{Type of Flooring}
C -->|PVC Vinyl Asbestos Tiles| D[Thickness per usage]
C -->|Flexible PVC Flooring| E[Thickness per usage]
D --> F[Material Selection]
E --> F
F --> G[Testing & Rounding Off per IS 2-1960]
This summarizes the scope and key specs for IS 5318 flooring materials and thickness selection.
2Terminology▼
IS 5318: Terminology & Key Specifications Overview
1. Terminology (Clause 2.0)
Defines terms related to flooring materials and installation.
Ensures uniform understanding of terms like flooring thickness, PVC flooring, vinyl asbestos tiles, etc.
2. Flooring Thickness (Clause 3.1.1)
Thickness depends on service conditions (load, usage).
Typical thicknesses vary; consult specific tables in the code for exact values.
3. Rounding Off Numerical Values (Clause 0.6)
Follow IS 2-1960 for rounding:
Final test/calculation results rounded to the same significant figures as specified.
Ensures consistency in reporting.
4. Specifications for Flooring Types
PVC (Vinyl) Asbestos Floor Tiles: Material and installation specs.
Flexible PVC Flooring: Material properties and laying guidelines.
Summary Table: Rounding Off (IS 2-1960)
Specified Value
Rounded Result Example
12.3
12.3
0.056
0.056
120.0
120
Diagram: Flooring Thickness Decision Flow
flowchart TD
A[Start: Flooring Design] --> B{Service Conditions}
B -->|Light Use| C[Use thinner flooring]
B -->|Heavy Use| D[Use thicker flooring]
C --> E[Check material specs]
D --> E
E --> F[Apply Rounding as per IS 2-1960]
F --> G[Finalize Flooring Thickness]
For detailed thickness values and material specs, refer to the full IS 5318 code sections on flooring types and installation.
3Materials and Components▼
IS 5318: Materials and Components - Key Points
Materials (Clause 2.1)
Sheet Material:
Glass sheet ~30 x 30 cm
Rubber mat or polyethylene sheet (≥ 0.1 mm thick)
PVC flooring material ~60 x 60 cm
Sealing Material: Putty, adhesive plasticine, or suitable mastic for edges.
Thickness (Clause 3.1.1)
Thickness depends on service conditions (load, environment).
Refer to specific flooring type standards (PVC, vinyl asbestos) for exact thickness.
Rounding Off (Clause 0.6)
Use IS 2:1960 rules for rounding test results.
Maintain the same number of significant figures as specified values.
Electrical Resistance Test (Clause 4.3) - Moisture Check
Flooring Type
Max Moisture Content (%)
Vinyl asbestos flooring
6.5
Other flooring types
5.5
If moisture exceeds these, concrete slab is not sufficiently dry.
Summary Diagram
flowchart TD
A[Materials] --> B[Sheet: Glass/Rubber/Polyethylene/PVC]
A --> C[Sealing: Putty/Plasticine/Mastic]
D[Thickness] --> E[Depends on Service Conditions]
F[Moisture Test] --> G{Moisture %}
G -->|>6.5% Vinyl Asbestos| H[Not Dry]
G -->|>5.5% Others| H
G -->|Below limits| I[Dry - OK]
Use this as a checklist for material selection, thickness, and moisture testing per IS 5318.
4Necessary Information▼
IS 5318 - Necessary Information Summary
Key Materials (Clause 2.1)
Sheet Material: Glass (30x30 cm), rubber mat, polyethylene sheet (≥0.1 mm thick), or PVC flooring (60x60 cm).
Sealing Material: Putty, adhesive plasticine, or suitable mastic for sealing edges.
Rounding Off (Clause 0.6)
Final test/analysis values must be rounded as per IS 2:1960.
Retain the same significant figures as specified in the standard.
Flooring Thickness (Clause 3.1.1)
Thickness depends on service conditions (load, wear, environment).
No fixed formula; design based on use-case and durability requirements.
Electrical Resistance Test (Clause 5.5)
Refer to Table A-4 for electrical resistance limits (not fully provided here).
Ensures flooring meets safety and insulation standards.
Additional Notes:
Use PVC or vinyl asbestos tiles as per their respective specifications.
Flexible PVC flooring has its own specification for durability and flexibility.
flowchart TD
A[Materials] --> B[Sheet (Glass/Rubber/Polyethylene/PVC)]
A --> C[Sealing (Putty/Plasticine/Mastic)]
D[Thickness] --> E[Depends on Service Conditions]
F[Testing] --> G[Rounded values per IS 2:1960]
F --> H[Electrical Resistance per Table A-4]
For detailed electrical resistance values and flooring thickness, consult the full IS 5318 document and related PVC/asbestos flooring standards.
5Preparation of Sub-floor▼
IS 5318: Preparation of Sub-floor - Key Points & Formulas
Key Specifications (Clause 4.1 & 5.3)
Sub-floor type: Concrete with effective damp-proof course (DPC) is preferred.
Surface finish: Troweled smooth for PVC flooring.
Drying time: Concrete must be allowed to dry sufficiently before flooring.
Damp-proofing: Must comply with Clauses 5.3.1 or 5.3.2 (methods for damp-proofing).
Thickness of screeded bed: As per design, typically 12-25 mm.
Evenness: Surface tolerance should be within ±3 mm over 2 m length.
Ventilation: Required for wooden sub-floors to prevent moisture build-up.
Determination of Sub-floor Dryness (Appendix A, Clause 6.2)
Moisture test: Use calcium chloride test or electrical moisture meter.
Acceptable moisture content: Generally < 4% for concrete sub-floor before laying PVC.
Typical Thickness & Drying Time Table
Sub-floor Type
Thickness (mm)
Drying Time (days)
Concrete
75 - 100
21 - 28
Screed
12 - 25
7 - 14
Damp-proofing Treatment (Summary)
Method 5.3.1: Use of bituminous membrane or liquid applied membrane.
Method 5.3.2: Use of polyethylene sheet under concrete slab.
flowchart TD
A[Prepare Sub-floor] --> B{Type of Sub-floor}
B --> |Concrete| C[Trowel finish + DPC]
B --> |Wood| D[Provide ventilation]
C --> E[Drying Time (21-28 days)]
E --> F[Damp-proofing Treatment]
F --> G[Lay Flooring]
D --> G
Summary: Ensure sub-floor is dry, smooth, damp-proofed, and properly ventilated before flooring installation as per IS 5318.
6Laying and Fixing of PVC Flooring▼
IS 5318: Laying and Fixing of PVC Flooring – Key Points
1. Surface Preparation
Sub-floor must be clean, dry, and smooth.
For metal floors (Clause 5.4):
Remove rust/scale by chipping or wire brushing.
Welded joints must be smooth and free from undulations.
Remove paint/grease by caustic soda wash & rinse.
Use compatible putty to fill uneven areas.
2. Conditioning of PVC Flooring (Clause 6)
PVC sheets/tiles should be conditioned at the installation site temperature for ~24 hours before laying.
3. Laying & Fixing Method
Use adhesives compatible with PVC and substrate.
Ensure full contact between flooring and adhesive.
Avoid air bubbles by rolling with a heavy roller.
Follow recommended adhesive open time and curing periods.
Typical Adhesive Application (General Practice)
Substrate Type
Adhesive Type
Application Rate (g/m²)
Concrete
Polymer-based adhesive
200 - 300
Metal
Contact adhesive
150 - 250
Wood
PVAc or Polymer adhesive
180 - 250
Summary Diagram: PVC Flooring Installation Steps
flowchart TD
A[Surface Preparation] --> B[Condition PVC Flooring (24 hrs)]
B --> C[Apply Adhesive on Sub-floor]
C --> D[Lay PVC Sheet/Tile]
D --> E[Roll to Remove Air Bubbles]
E --> F[Curing & Final Inspection]
References:
IS 5318 (Clause 1.1, 5.4, 6)
Compatible adhesive manufacturer datasheets
Related IS codes on bitumen felts and damp-proofing for substrate treatment
This ensures durability, smooth finish, and proper bonding of PVC flooring.
7Protective Edging▼
IS 5318: Protective Edging for PVC Flooring
Key Specifications (Clause 7.1)
Purpose: Protect exposed edges of PVC sheets/tiles (e.g., doorways, stair treads) from damage.
Method: Use metallic edge strips securely fastened to the sub-floor.
Edge strips must ensure:
Firm anchorage to prevent movement.
Full coverage of exposed edges.
Materials (Clause 2.1)
Edge sealing materials include:
Glass sheet (~30x30 cm), rubber mat, or polyethylene sheet (≥0.1 mm thick).
Putty, adhesive plasticine, or suitable mastic for sealing edges.
Thickness (Clause 3.1.1)
Flooring thickness depends on service conditions; protective edging should match or exceed this thickness for effective protection.
Summary Table: Protective Edging Components
Component
Specification
Purpose
Metallic edge strip
Securely fastened to sub-floor
Protects exposed edges
Sealing material
Putty/plasticine/mastic
Seals edges against moisture/dirt
Backing sheet
Glass/rubber/polyethylene
Provides stable base for sealing
Diagram: Edge Protection Setup
flowchart LR
A[Sub-floor] --> B[Metallic Edge Strip]
B --> C[PVC Flooring]
C --> D[Sealing Material (Putty/Mastic)]
D --> E[Backing Sheet (Glass/Rubber/Polyethylene)]
Note: Ensure edge strips are corrosion-resistant and compatible with PVC flooring to avoid chemical reactions.
8Maintenance and Cleaning▼
IS 5318: Maintenance and Cleaning of PVC Flooring
Key Specifications & Procedures
Adhesive Removal (Clause 6.8):
Wipe off adhesive squeeze immediately with a wet cloth before hardening.
If hardened, remove using solvent:
Solvent mix: 1 part commercial butyleacetate + 3 parts turpentine oil.
Initial Cleaning (Clause 6.10):
After fixing, clean with warm soap solution:
Soap solution: 2 spoons soap in 5 litres warm water, applied with a wet cloth.
Routine Cleaning (Clause 8.1):
Mop with soap solution using a clean damp cloth.
Do not pour water directly on flooring to avoid adhesive failure.
Periodic polishing recommended for appearance and wear resistance.
Avoid excessive polish build-up as it traps dirt and becomes tacky.
Summary Table
Task
Method/Material
Notes
Adhesive removal
Wet cloth immediately or solvent mix
Solvent: butyleacetate + turpentine oil
Initial cleaning
Warm soap solution (2 spoons/5L water)
Use wet cloth
Routine cleaning
Mop with soap solution
Avoid direct water pouring
Polishing
Periodic application
Avoid thick polish layers
flowchart LR
A[Adhesive Squeeze] -->|Wipe immediately| B[Wet Cloth]
A -->|If hardened| C[Apply Solvent]
C --> D[Remove Adhesive]
E[Post Fixing] --> F[Clean with Soap Solution]
G[Routine Cleaning] --> H[Mop with Soap Solution]
H --> I[Avoid Direct Water]
J[Polishing] --> K[Apply Periodically]
K --> L[Avoid Thick Layers]
This ensures durability and appearance per IS 5318 standards.
Appendix ADetermination of Sub-floor Dryness▼
IS 5318 - Determination of Sub-floor Dryness (Appendix A, Clause 6.2)
Key Tests for Sub-floor Dryness:
Preliminary Test (A-2)
Approximate method to distinguish very wet slabs from dry/nearly dry.
Conducted at multiple points and repeated until no dampness is visible.
If dry, proceed to confirmatory tests.
Hygrometer Test (A-3)
More accurate than preliminary.
Measures relative humidity near the slab surface.
Used to confirm dryness after preliminary test.
Electrical Resistance Test (A-4)
Measures moisture content via electrical resistance.
Acceptance criteria:
Flooring Type
Max Moisture Content (%)
Vinyl asbestos flooring
6.5
Other floorings
5.5
Slab considered dry only if all readings are below these values.
Procedure Summary:
Conduct preliminary test → If dry, confirm with Hygrometer or Electrical Resistance test.
Repeat tests at multiple points until consistent dryness is confirmed.
flowchart TD
A[Start: Preliminary Test] --> B{Is slab dry?}
B -- No --> C[Delay & Retest]
B -- Yes --> D[Confirmatory Test]
D --> E{Hygrometer Test or Electrical Resistance Test}
E --> F{Results within limits?}
F -- Yes --> G[Slab considered dry]
F -- No --> C
This ensures reliable assessment before flooring installation.
Frequently Asked
Popular Questions About IS 5318
?What types of adhesives are recommended for flexible PVC flooring over different sub-floors?▼
Recommended Adhesives for Flexible PVC Flooring (IS 5318):
Rubber-based adhesives
Suitable for:
Concrete sub-floors
Wooden sub-floors
Metal sub-floors
PVA-based adhesives
Suitable for:
Concrete sub-floors
Wooden sub-floors
Not suitable for:
Metal sub-floors
Areas with constant water spillage
Application Tips (Clause 6.4):
Use a notched trowel to apply adhesive on both sub-floor and PVC backing.
Allow adhesive to become tacky but not finger-marking (~30 minutes).
Lay flooring promptly before adhesive loses tackiness due to dust or drying.
Important:
Ensure sub-floor is levelled and permanently dry (Clauses 5.2, 0.3) for good adhesion and durability.
Hot sealing joints is recommended to prevent water ingress and extend floor life.
Loading diagram...
?How should concrete sub-floors be prepared and damp-proofed before laying PVC flooring?▼
Preparation and Damp-Proofing of Concrete Sub-Floors for PVC Flooring (IS 5318)
Damp-proof Course: Concrete sub-floor must include an effective damp-proof course to prevent moisture ingress (Clause 5.3).
Drying Time: Concrete above the damp-proof course must be allowed sufficient time to dry before laying PVC (Clause 5.3).
Surface Finish:
For new work, apply a screed on the concrete sub-floor and finish with a trowel (Clause 5.3.5).
Alternatively, use a power-float finish directly on the concrete.
Old Concrete:
Remove all foreign materials.
Keep surface wet for 24 hours by sprinkling water.
Apply a 3 mm screed topping unless the surface is already even and clean (Clause 5.3.5).
Cleaning: Remove grease, oil, paint, or other contaminants to ensure adhesion.
Evenness & Dryness Check:
Examine sub-floor for levelness and dryness before laying (Clause 6.2).
Clean with a dry cloth.
Use moisture testing methods as per Appendix A to confirm dryness.
Loading diagram...
Summary: Ensure a damp-proof course, dry and clean sub-floor, proper screed finish, and confirm dryness before laying PVC flooring for durable adhesion and performance.
?What are the best practices for aligning and joining PVC sheets and tiles during installation?▼
Best Practices for Aligning and Joining PVC Sheets and Tiles (IS 5318):
Adhesive Application (Clause 6.4):
Use a notched trowel to apply adhesive evenly on both sub-floor and PVC backing. Wait ~30 minutes until adhesive is tacky but not sticky.
Sheet Laying (Clause 6.5):
Place sheets slowly from one end, pressing to squeeze out air. Lay subsequent sheets edge-to-edge with minimal joint gaps. Roll with a suitable roller to ensure full contact.
Tile Laying (Clause 6.7):
Start from the center of the area. Lay tiles close with minimal gaps, lowering without sliding to avoid adhesive squeeze-up. Roll tiles with a 5 kg wooden roller for proper bonding. Remove and clean any undulations before relaying.
Edge Protection (Clause 7.1):
Use metallic edge strips at exposed edges (doorways, stairs) to prevent damage, securely fastening them to the sub-floor.
Summary Table
Step
Key Action
Notes
Adhesive Application
Apply with notched trowel
Wait ~30 mins till tacky
Sheet Placement
Lay slowly, edge-to-edge
Roll for full contact
Tile Placement
Start center, minimal gaps
Roll with 5 kg wooden roller
Edge Protection
Use metallic strips
Secure firmly to sub-floor
Loading diagram...
This ensures strong, neat joints and durable flooring installation per IS 5318.
?How can moisture levels in sub-floors be accurately tested to ensure suitability for PVC flooring?▼
Moisture Testing for Sub-floors (IS 5318)
To ensure suitability for PVC flooring, moisture levels in sub-floors must be tested accurately as per IS 5318 Clause 6.2 and Appendix A:
Use a relative humidity (RH) meter placed on the concrete slab (avoid direct sunlight to prevent false low readings).
The sub-floor is considered dry enough if RH ≤ 70% (Clause A-3.3).
Clean the sub-floor with a dry cloth before testing.
Alternatively, electrical resistance tests can be used to detect moisture presence but are less common.
For timber sub-floors, ensure proper ventilation and use seasoned, treated timber; avoid covering poorly ventilated timber floors with PVC to prevent fungal growth (Clause 5.2.1).
Summary Table:
Test Method
Acceptance Criteria
Notes
Relative Humidity Test
RH ≤ 70%
Avoid direct sunlight on sensor
Electrical Resistance
Low resistance indicates moisture
Used as supplementary test
Loading diagram...
Ensure dryness before laying to avoid moisture-related failures in PVC flooring.
?What maintenance procedures are advised to preserve the appearance and durability of PVC floors?▼
To preserve the appearance and durability of PVC floors as per IS 5318:
Cleaning & Maintenance (Clauses 8.1 & 8.2)
Daily care: Use a dry mop to maintain polish and gloss.
Light traffic: Frequent brushing, regular polishing, and re-application of polish every 4-6 weeks.
Moderate traffic: Occasional wet mop (no detergents), polish every 1-3 weeks.
Avoid pouring water directly; it can seep into joints and weaken adhesive.
Over-waxing causes tackiness; remove excess polish with white spirit or paraffin before re-polishing.
After heavy traffic, sweep with a hair broom, mop with clean water, and dry immediately.
Sub-floor Preparation (Clauses 0.3 & 6.2)
Ensure sub-floor is even, dry, and clean before laying.
Moisture in sub-floor reduces floor life; test dryness per Appendix A.
Hot sealing joints to prevent water ingress is recommended for longer life (under study).
Summary Table:
Traffic Condition
Cleaning Method
Polish Frequency
Light
Frequent brushing
Every 4-6 weeks
Moderate
Occasional wet mop (no detergent)
Every 1-3 weeks
Heavy
Sweep, mop with clean water, dry
As needed
Loading diagram...
This approach ensures long-lasting, visually appealing PVC flooring.
✦