IS 15883 Part 22013AI Search Enabled✦ AI Generated

Construction project management - Guidelines, Part 2: Time Management

IS 15883 Part 2: 2013 provides comprehensive guidelines on time management for construction project management in India, covering the period from project approval through commissioning and handover. It addresses planning, scheduling, monitoring, and controlling project timelines using techniques like Work Breakdown Structure (WBS), network diagrams, and time-cost tradeoff analysis. This standard is essential for project managers and construction professionals aiming to optimize project duration while balancing resources, costs, and quality.

15Sections
125Clauses Indexed
AI Search Ready
2013Edition
Construction Management including safety in ConstructionCategory
Alternative search terms: IS 15883 Part 2 PDF, IS 15883 Part 2 pdf free download, IS 15883 Part 2 free download pdf, IS15883Part2 PDF, IS-15883-Part-2 PDF, IS 15883 Part 2 2013 PDF, IS 15883 Part 2:2013 PDF, IS 15883 Part 2-2013 PDF, IS 15883 Part 2 (2013) PDF, IS 15883 Part 2 2013 edition PDF, IS 15883 Part 2 edition 2013 PDF

What This Standard Covers

IS 15883 Part 2: 2013 provides comprehensive guidelines on time management for construction project management in India, covering the period from project approval through commissioning and handover. It addresses planning, scheduling, monitoring, and controlling project timelines using techniques like Work Breakdown Structure (WBS), network diagrams, and time-cost tradeoff analysis. This standard is essential for project managers and construction professionals aiming to optimize project duration while balancing resources, costs, and quality.

Who Uses This Standard

  • Construction Project Managers
  • Planning and Scheduling Engineers
  • Construction Consultants
  • Contractors and Subcontractors
  • Project Control Specialists
  • Construction Supervisors
  • Owners and Developers

Key Topics Covered

Work Breakdown Structure (WBS) preparation and application
Project time scheduling using network analysis and bar charts
Critical path method and dependency relationships
Time-cost tradeoff and schedule compression techniques
Progress monitoring and performance reporting
Use of S-curves for time monitoring
Resource scheduling and levelling
Management of time variances and corrective actions
Integration of time management with cost, quality, and safety
Milestone setting and monitoring
Change management to accelerate schedules
Use of management information systems (MIS) for time control

Table of Contents

1Scope

IS 15883 Part 2: Scope - Key Formulas, Tables & Specifications

1. Scope Variation Monitoring (Clause 6.2.4)

  • Scope changes (due to design, owner instructions, unforeseen conditions, etc.) require:
    • Reworking time planning and baseline schedule.
    • Revised resource planning.
    • Impact analysis on time and cost.
    • Agreement between owner and contractor.
  • Scope variation may alter the critical path and overall project timeline.
  • Time monitoring/control must be based on the revised baseline schedule.

2. Productivity Standards (Clause 6.1.5)

[ \textbf{Productivity Standard (p)} = \text{Productivity Norms} \times \text{Production Efficiency Factor} ]

  • Productivity Norms: Output per scheduling unit time (e.g., output/day), from IS 7272 (Part 1), CPWD, MORTH, or historical data.
  • Production Efficiency Factor: Multiplier adjusting norms for actual job conditions.

3. S-Curve Time Monitoring (Annex C, Clause 6.2.5)

  • Assign weightages (%) to project activities based on:
    • Criticality
    • Tender cost
    • Level of effort
  • Weightages distributed across phases: Design, Procurement, Construction, Testing & Commissioning.
  • Example phase weightages:
PhaseWeightage (%) Example
Design5
Procurement40
Construction50
Testing & Commissioning5
  • Sub-phase distributions (e.g., Procurement):
Sub-PhaseWeightage (%)
Raw Material/PO Release10
Manufacturing35
Testing During Manufacturing15
Dispatch20
Delivery to Site20
  • S-Curve plots cumulative weightage (%) vs time, useful for variance analysis and progress monitoring.

4. Baseline Schedule & Metrics Distribution

  • Metrics assigned up to Level 3 WBS.
  • Weightages distributed vertically (work packages) and horizontally (time phases).
  • Enables planned vs actual progress comparison.

Summary Diagram: Scope Variation &

2References

IS 15883 Part 2: Key References, Formulas & Tables Summary


1. Productivity Standards (Clause 6.1.5)

  • Formula:

[ \text{Productivity standard} (p) = \text{Productivity norms} \times \text{Production efficiency factor} ]

  • Definitions:
    • Productivity norms: Output per unit time (e.g., output/day), sourced from IS 7272 (Part 1), CPWD rates, MORTH data, or historical/project experience.
    • Production efficiency factor: Multiplier adjusting norms for actual job conditions.

2. Referenced Standards (Clause 1.3)

  • IS 7272 (Part 1): Labour output norms
  • IS 7337: Project management glossary
  • IS 10400: Inventory control glossary
  • IS 14580 (Parts 1 & 2): Network analysis for project management
  • IS 15198: Human resource development glossary
  • IS 15883 (Part 1): Construction project management general guidelines

3. Rounding Off (IS 2:1960)

  • Final test/analysis values must be rounded off as per IS 2 rules, maintaining the same significant figures as specified.

4. Time Monitoring via S-Curve (Clause 6.2.5, Annex C)

  • Concept: Assign weightages (%) to project activities/phases; plot cumulative planned vs actual progress (S-curve).

  • Weightage Criteria:

    • Criticality of work package
    • Tendering cost
    • Level of effort
  • Phases & Sample Weightages:

PhaseTypical Weightage (%)Subdivision Example
Design5Submissions 35%, Conditional Approval 55%, Final Approval 10%
Procurement40Raw Material 10%, Manufacturing 35%, Testing 15%, Dispatch 20%, Delivery 20%
Construction50Preparatory 15%, Installation 80%, Inspection 5%
Testing & Commissioning5Pre-commissioning 30%, Commissioning 40%, Performance 10%, Integration 20%
  • S-Curve Use:
3Definitions

Key Definitions & Formulas from IS 15883 (Part 2)

1. Productivity Standard (Clause 6.1.5)

  • Formula:

[ \text{Productivity Standard (p)} = \text{Productivity Norms} \times \text{Production Efficiency Factor} ]

  • Where:
    • Productivity Norms: Output of resources per minimum scheduling unit (e.g., output/day), obtained from IS 7272 (Part 1), CPWD rates, MORTH data, or historical data.
    • Production Efficiency Factor: Multiplier adjusting norms to actual job conditions.

2. Standards Referenced for Definitions (Clause 1.3)

  • IS 7337: Glossary of terms in project management.
  • IS 10400: Glossary of terms in inventory control.
  • IS 15198: Glossary of terms in human resource development.

3. Rounding Off (General Clause)

  • Follow IS 2:1960 for rounding off numerical values, maintaining the same significant digits as specified.

4. Time Monitoring & Weightage Concept (Annex C, Clause 6.2.5)

  • S-Curve: Cumulative weighted progress curve shaped like 'S' for project time monitoring.

  • Weightage Allocation Criteria:

    • Criticality of work package.
    • Tentative cost.
    • Level of effort.
  • Typical Weightage Distribution for Work Phases:

PhasePercent Weightage Example
Design5%
Procurement40%
Construction50%
Testing & Commissioning5%
  • Sub-Phases Example for Construction:
Sub-PhaseWeightage (%)
Preparatory Works15
Installation80
Checking/Inspection5

Summary Diagram: Productivity Standard Calculation

flowchart LR
    A[Productivity Norms] --> C[Productivity Standard]
    B[Production Efficiency Factor] --> C

This concise summary provides essential definitions, formulas, and tables for productivity and project monitoring as per IS 15883 (Part 2). For detailed tables and examples,

4General Principles of Time Management

IS 15883 Part 2: General Principles of Time Management

Key Processes (Clause 4.4)

  • Time Planning: Define scope, estimate durations, sequence activities.
  • Time Monitoring: Track progress vs. schedule.
  • Time Control: Update and adjust schedule dynamically.

Steps for Time Management

  1. Define project scope.
  2. Estimate activity durations.
  3. Sequence activities with dependencies (see IS 14580 Parts 1 & 2 for network analysis).
  4. Develop project schedule.
  5. Monitor and control schedule continuously.

Important Considerations (Clause 4.2.1)

  • Integrate time management with cost, quality, safety, scope.
  • Base time frame on:
    • Past project experience.
    • Location & weather.
    • Stakeholder constraints.
    • Resource availability.
    • Quality and safety requirements.

Recommended Tools

  • Use construction management software for scheduling and updates.

Basic Formula for Project Duration Estimation:

[ \text{Project Duration} = \sum \text{Activity Durations} + \text{Slack/Float} ]

Activity Sequencing Example (Precedence Diagram Method):

graph TD
  A[Start] --> B[Activity 1]
  B --> C[Activity 2]
  B --> D[Activity 3]
  C --> E[Activity 4]
  D --> E
  E --> F[Finish]

This diagram shows dependencies and parallel activities.


Summary: Time management is a continuous, integrated process involving planning, monitoring, and control, supported by network analysis (IS 14580) and software tools, while considering all project constraints and quality/safety standards.

5Time Management During Project Phases

IS 15883 (Part 2) - Time Management Key Points

Time Management Processes (Clause 4.4)

  • a) Time Planning: Define scope, estimate durations, sequence activities, develop schedule.
  • b) Time Monitoring: Track progress against schedule.
  • c) Time Control: Take corrective actions to maintain schedule.

Steps for Time Planning

  1. Define project scope.
  2. Estimate activity durations.
  3. Sequence activities with dependencies.
  4. Develop project schedule (network diagrams, bar/Gantt charts).
  5. Monitor and control schedule dynamically.

Project Classification for Time Planning (Clause 6.1.2)

AspectCategories
Type of WorkBuilding, Infrastructure, Industrial, Others
Project Duration>5 yrs (Long), 3-5 yrs (Medium), 1-3 yrs (Short), <1 yr (Special Short-term)
Project ValueMega, Large, Medium, Small
Execution SpeedFast track, Normal pace

Scheduling Deliverables (Clause 6.1.10)

  • Prepare network diagrams and bar/Gantt charts for each sub-project.
  • Link sub-project schedules into a master control schedule.
  • Use Line of Balance (LOB) for repetitive or linear projects.
  • Refer IS 14580 (Parts 1 & 2) for network/bar chart preparation.

Typical Time Planning Flow (Fig. 1 summary)

flowchart TD
    A[Define Project Scope] --> B[Estimate Activity Durations]
    B --> C[Sequence Activities]
    C --> D[Develop Schedule (Network/Gantt)]
    D --> E[Monitor & Control Schedule]
    E --> F[Update & Revise Schedule]

Recommendations

  • Use construction management software for efficient scheduling.
  • Periodically monitor and update schedules.
  • Consider interfaces among disciplines for integrated scheduling.

This concise framework helps manage project time effectively per IS 15883 Part 2.

6Time Planning and Scheduling Techniques

IS 15883 (Part 2) - Time Planning & Scheduling Techniques

Key Concepts:

  • Time Scheduling: Assign start and finish dates using network diagrams (Precedence Diagram Method / Activity on Node per IS 14580 Part 2).
  • Dependency Types (Fig. 2):
    • FS (Finish to Start)
    • FS + Lag (Finish to Start with lag)
    • SS + Lag (Start to Start with lag)
    • FF + Lag (Finish to Finish with lag)
    • SF + Lag (Start to Finish with lag)
    • FS - Lead (Finish to Start with lead)

Stepwise Approach (6.1.2 to 6.1.10):

  1. Assess Project Characteristics:
    • Type (Building, Infrastructure, Industrial, Others)
    • Duration (Short <1yr, Medium 1-3yrs, Long >5yrs)
    • Value (Mega, Large, Medium, Small)
    • Execution Speed (Fast track, Normal)
  2. Finalize Method Statement & Design Basis.
  3. Prepare Network Diagram and perform:
    • Forward Pass (calculate Early Start/Finish)
    • Backward Pass (calculate Late Start/Finish)
  4. Calculate:
    • Total Float = LS - ES or LF - EF
    • Free Float = Earliest ES of successor - EF of current activity
  5. Identify Critical Path (activities with zero float).
  6. Prepare Deliverables:
    • Early/Late Start & Finish dates
    • Total & Free Float
    • Critical Path & Project Duration
    • Network diagrams & Gantt charts (linked sub-projects)

Scheduling Techniques:

  • Use Line of Balance (LOB) for repetitive/linear projects.
  • Employ software tools for automation.

Float Calculations:

ParameterFormula
Total FloatTF = LS - ES = LF - EF
Free FloatFF = Earliest ES of successor - EF

graph TD
  A[Start] --> B[Activity 1]
  B --> C[Activity 2]
  C --> D[Activity 3]
  D --> E[Finish]

  click B "FS
7Activity Identification and Network Preparation

IS 15883 Part 2: Activity Identification & Network Preparation Key Points


1. Activity Identification (Clause 6.1.4)

  • Identify all project activities clearly.
  • Define dependencies among activities using types of relationships:
    • FS (Finish to Start)
    • FS + Lag
    • SS + Lag
    • FF + Lag
    • SF + Lag
    • FS - Lead

2. Network Preparation & Time Scheduling (Clause 6.1.8.2)

  • Use Precedence Diagram Method (Activity on Node) as per IS 14580 (Part 2).
  • Steps:
    • Prepare network diagram with activities and dependencies.
    • Perform Forward Pass and Backward Pass to calculate:
      • Early Start (ES), Early Finish (EF)
      • Late Start (LS), Late Finish (LF)
      • Total Float (TF) = LS - ES or LF - EF
      • Free Float (FF)
    • Identify Critical Path (activities with zero total float).
    • Calculate overall project duration.

3. Time Management Deliverables (Clause 6.1.10)

  • Deliverables include:
    • Network diagrams and Gantt charts per sub-project.
    • Master control schedule by linking sub-project schedules.
    • Use Line of Balance (LOB) for repetitive/linear projects.
  • Refer IS 14580 (Parts 1 & 2) for diagram/chart preparation.

4. Resource Scheduling (Clause 6.1.8.3)

  • Estimate resources per activity/day using:

    [ \text{Resource per day} = \frac{\text{Total resource quantity}}{\text{Activity duration}} ]

  • Superimpose resource data on time schedule.

  • Resource levelling includes:

    • Reconciling resource needs with availability.
    • Optimizing for uniform resource usage.
    • Aligning cost schedules with cash flow.
    • Ensuring project finishes on optimum date.

Summary Table: Dependency Relationships

Relationship TypeDescriptionNotation
Finish to StartSuccessor starts after predecessor finishesFS
Finish to Start + LagSuccessor starts after lag days post predecessor finishFS + X days
8Time Scheduling and Dependency Relationships

Key Formulas & Specifications for Time Scheduling and Dependency Relationships

(IS 15883 Part 2: 2013, Clauses 6.1.8.2 & 6.1.10)


Dependency Relationships (Types & Notations)

TypeNotationDescription
Finish to StartFSSuccessor starts after predecessor finishes
Finish to Start with LagFS + X daysSuccessor starts X days after predecessor finishes
Start to Start with LagSS + X daysSuccessor starts X days after predecessor starts
Finish to Finish with LagFF + X daysSuccessor finishes X days after predecessor finishes
Start to Finish with LagSF + X daysSuccessor finishes X days after predecessor starts
Finish to Start with LeadFS - X daysSuccessor starts X days before predecessor finishes

Time Scheduling Steps

  1. Prepare Network Diagram (Precedence Diagram Method - IS 14580 Part 2)
  2. Forward Pass Calculation:
    • Early Start (ES) and Early Finish (EF) for each activity
  3. Backward Pass Calculation:
    • Late Start (LS) and Late Finish (LF) for each activity

Key Calculations

  • Early Finish (EF):
    [ EF = ES + \text{Activity Duration} - 1 ]

  • Late Start (LS):
    [ LS = LF - \text{Activity Duration} + 1 ]

  • Total Float (TF):
    [ TF = LS - ES = LF - EF ]

  • Free Float (FF):
    [ FF = \text{Earliest ES of successor} - EF - 1 ]

  • Critical Path: Activities with Total Float = 0


Time Scheduling Deliverables

  • Early & Late Start/Finish dates for each activity
  • Total & Free Float values
  • Critical activities and project critical path
  • Project duration

Reporting & Tools

  • Use Network Diagrams and Gantt Charts for visualization
  • For repetitive or linear projects, use **Line of Balance (
9Resource Scheduling and Levelling

Resource Scheduling & Levelling (IS 15883 Part 2)


Key Formulas:

  1. Productivity Standard (Clause 6.1.5):

[ \boxed{ p = \text{Productivity Norms} \times \text{Production Efficiency Factor} } ]

  • p: Productivity standard (output per scheduling unit, e.g., resources/day)
  • Productivity norms: From IS 7272 (Part 1), CPWD, MORTH, or historical data
  • Production efficiency factor: Adjusts norms to actual site conditions
  1. Resource Requirement per Activity per Day (Clause 6.1.8.3):

[ \text{Resource Required} = \frac{\text{Work Quantity}}{p \times \text{Activity Duration}} ]


Resource Scheduling Deliverables (6.1.8.3):

  • Daily resource amounts for each activity (manpower, material, equipment)
  • Daily resource amounts for entire project duration

Resource Levelling Steps (6.1.8.3):

  • Reconcile resource demand with availability
  • Optimize for uniform resource usage
  • Align cost schedules with cash flow
  • Adjust schedules to meet optimum finish date

Time Scheduling (Clause 6.1.8.2):

  • Use Precedence Diagram Method (IS 14580 Part 2)
  • Dependency types: FS, FS+lag, SS+lag, FF+lag, SF+lag, FS-lead
  • Calculate Early Start/Finish, Late Start/Finish, Float, Critical Path

Summary Table: Resource Scheduling Workflow

StepDescription
1. Estimate ProductivityUse norms × efficiency factor
2. Calculate Resource Req.Work quantity / (productivity × duration)
3. Time SchedulingNetwork diagram, forward/backward pass
4. Superimpose ResourcesMap resource needs over time
5. Resource LevellingReconcile & optimize resource usage & costs

flowchart TD
    A[Estimate Productivity] --> B[Calculate Resource Requirement]
    B --> C[Prepare Network Diagram]
    C --> D[Forward & Backward Pass]
    D --> E[Superimpose Resource Data]
    E --> F[
10Progress Monitoring and Reporting

IS 15883 Part 2: Progress Monitoring & Reporting Key Points

Common Project Metrics (Clause 6.2.5)

  • Earned Value (budgeted cost of work performed)
  • Manhour estimates
  • Pre-agreed weightage (criticality/importance)
  • Combination of above

Activity Tracking Steps (Clause 6.2.2)

  • Compare actual vs planned status
  • Analyze deviations & impact on schedule
  • Forecast future progress
  • Prepare catch-up plan if delays exist
  • Monitor baseline critical path & update critical activities

Project Status Report Contents

  • Planned vs achieved progress (tabular/graphical)
  • Past performance & rate analysis
  • Critical activities status & forecast
  • Look-ahead program status

Graphical Reporting (Clause 6.2.5)

  • Weighted summation of all WBS activities
  • Baseline vs Actual vs Catch-up curves (see Fig. 5 & 6)
  • Horizontal shift = time delay
  • Vertical gap = progress shortfall

Sample Formula for Earned Value (Annex B)

[ \text{Earned Value (EV)} = \text{Budgeted Cost of Activity} \times \text{Percent Complete} ]

Typical Table for Progress Reporting (Annex C style)

ActivityPlanned MetricActual MetricVariance (Planned - Actual)Status
A10090-10Behind
B5055+5Ahead

gantt
    title Project Progress Monitoring
    dateFormat  YYYY-MM-DD
    section Baseline Plan
    Activity A       :done, 2024-01-01, 10d
    Activity B       :done, 2024-01-11, 15d
    section Actual Progress
    Activity A       :active, 2024-01-01, 8d
    Activity B       :active, 2024-01-13, 12d
    section Catch-up Plan
    Activity A       :crit, 2024-01-09, 4d

Summary:
Use a common metric (earned value/manhours/weightage) for all activities. Track progress daily,

11Time-Cost Tradeoff and Schedule Compression

IS 15883 Part 2: Time-Cost Tradeoff & Schedule Compression Key Points


1. Time-Cost Tradeoff Concept (Clause 6.1.8.4, Annex A)

  • Goal: Reduce project duration (PN) to a target duration (PR) with minimal increase in direct cost.
  • Approach: Buy time on critical path activities by increasing direct costs (more labor, equipment).
  • Time-Cost Curve:
ParameterSymbolDescription
Normal CostCNCost at normal duration
Crash CostCcCost at minimum (crash) duration
Normal TimeTNMost likely activity duration
Crash TimeTcMinimum possible activity duration
  • Cost Slope (Cost per day saved):

[ \text{Cost slope} = \frac{C_c - C_N}{T_N - T_c} ]


2. Siemens Approximation Method (SAM) Steps

  • Perform CPM to find normal project duration (PN).
  • Set target reduced duration (PR), where PN > PR.
  • Identify all project paths and their durations.
  • Calculate cost slope for activities on critical/inadequately shortened paths.
  • Calculate effective cost slope = cost slope / number of critical paths containing the activity.
  • Select activity with lowest effective cost slope for crashing.
  • Shorten activity by minimum of:
    • Available reduction time for activity,
    • Required reduction on critical path(s).
  • Repeat until project duration ≤ PR.

3. Schedule Compression (Clause 6.3.5.1)

  • Also called acceleration measures.
  • Use time-cost tradeoff principles to buy time cost-effectively.
  • Employ heuristics like modified Siemens method.
  • Aim to meet deadlines with optimal cost increase.

4. Time Scheduling Essentials (Clause 6.1.8.2)

  • Use Precedence Diagram Method (PDM) per IS 14580 (Part 2).
  • Calculate early/late start & finish, float, critical path.
  • Deliverables include network diagrams and Gantt charts.

Summary Table: Time-Cost Tradeoff Parameters

| Parameter | Symbol | Unit | Description | |---------------------|---------|------------|

12Change Management for Schedule Acceleration

IS 15883 Part 2: Key Points on Change Management for Schedule Acceleration

Acceleration Measures (Clause 6.3.5.1)

  • Purpose: Buy time cost-effectively to meet deadlines.
  • Also called: Time-cost trade-off process (Annex A).
  • Method: Use heuristic algorithms like the Modified Siemens Method to find optimum acceleration.

Time Scheduling (Clause 6.1.8.2)

  • Use Precedence Diagram Method (PDM) or Activity on Node (AON).
  • Types of dependencies (Fig. 2):
    • FS (Finish to Start)
    • FS + Lag, SS + Lag, FF + Lag, SF + Lag
    • FS - Lead (lead time)
  • Perform:
    • Forward pass (early start/finish)
    • Backward pass (late start/finish)
  • Calculate:
    • Total float, free float
    • Critical path & critical activities
    • Project duration

Time Management Deliverables (Clause 6.1.10)

  • Prepare network diagrams and bar/Gantt charts for sub-projects.
  • Link to form a master control schedule.
  • Use Line of Balance (LOB) for repetitive/linear projects.
  • Refer IS 14580 (Parts 1 & 2) for scheduling standards.

Typical Forward and Backward Pass Calculations

ActivityES (Early Start)EF (Early Finish)LS (Late Start)LF (Late Finish)Float = LS-ES
A05050
B5107122

flowchart TD
    A[Start] --> B[Activity A]
    B --> C[Activity B]
    C --> D[Finish]

    style B stroke:#f66,stroke-width:2px
    style C stroke:#f66,stroke-width:2px

Summary: Use heuristic algorithms (e.g., Modified Siemens) for optimal schedule acceleration, apply PDM/AON with dependency types, perform forward/backward pass for scheduling, and prepare linked network/bar charts

Annex ATime-Cost Tradeoff Algorithm

Time-Cost Tradeoff Algorithm (Siemens Approximation Method - SAM) per IS 15883 Part 2

Key Formulas:

  • Cost Slope (CS):
    [ CS = \frac{C_c - C_N}{T_N - T_c} ]
    Where:

    • (C_c) = Crash cost
    • (C_N) = Normal cost
    • (T_N) = Normal time
    • (T_c) = Crash time
  • Deterministic Activity Duration:
    [ T_E = \frac{q}{p \times n} ]
    Where:

    • (q) = Work quantity
    • (p) = Resource productivity
    • (n) = Number of resource groups
  • Probabilistic Activity Duration (PERT formula):
    [ T_p = \frac{a + 4m + b}{6} ]
    Where:

    • (a) = Optimistic duration
    • (m) = Most likely duration
    • (b) = Pessimistic duration

SAM Algorithm Steps:

  1. Calculate project normal duration (P_N) using CPM.
  2. Set reduced project duration (P_R) ((P_N > P_R)).
  3. Identify all project paths and their lengths (sum of normal times).
  4. Find activities on critical/inadequately shortened paths.
  5. Calculate effective cost slope for each activity:
    [ \text{Effective CS} = \frac{\text{Cost Slope}}{\text{Number of inadequately shortened paths containing the activity}} ]
  6. Select activity with lowest effective cost slope on paths needing shortening.
  7. Shorten activity by minimum of:
    • Remaining unallocated time for activity
    • Smallest shortening demand on paths containing the activity
  8. Repeat until all paths meet (P_R).

Notes:

  • Assumes linear time-cost relationship between normal and crash points.
  • Limits exist beyond which crashing is ineffective or counterproductive.
  • Useful for schedule compression with minimum cost increase.
flowchart TD
    A[Start: CPM & Project Normal Duration (PN)] --> B[Set Reduced Duration
Annex BEarned Value Management Techniques

Earned Value Management (EVM) Key Formulas & Specifications (IS 15883 Part 2)


Basic Elements:

  • Planned Value (PV) or BCWS: Budgeted cost for scheduled work.
  • Actual Cost (AC) or ACWP: Actual cost incurred.
  • Earned Value (EV) or BCWP: Budgeted cost of work performed.

EV Calculation:

[ \text{EV} = \text{Baseline Cost} \times % \text{Complete} ]


Key Performance Indicators:

IndicatorFormulaInterpretation
Schedule Performance Indicator (SPI)(\text{SPI} = \frac{\text{EV}}{\text{PV}})SPI > 1: Ahead of schedule; SPI < 1: Behind schedule

Reporting & Monitoring:

  • Use common measurement parameters (EV, manhours, or weighted importance) across all WBS activities.
  • Summarize project status graphically or tabularly at all WBS levels.
  • Weighted summation of sub-activities generates overall project status.

Visual Summary of EVM Elements and SPI:

flowchart LR
    PV[Planned Value (PV)]
    AC[Actual Cost (AC)]
    EV[Earned Value (EV)]
    SPI[Schedule Performance Indicator (SPI)]

    PV --> SPI
    EV --> SPI
    SPI -->|SPI = EV / PV| Status{Project Status}
    Status -->|SPI > 1| Ahead[Ahead of Schedule]
    Status -->|SPI < 1| Behind[Behind Schedule]

Use EVM to:

  • Track progress
  • Forecast performance
  • Reduce schedule and cost overruns

For detailed tables and graphical reports, refer to Annex B of IS 15883 Part 2.

Annex CSample Time Monitoring Based on Weightage Concept (S-Curve)

IS 15883 Part 2: Sample Time Monitoring Based on Weightage Concept (S-Curve)

Key Concepts:

  • Project Metric: A common parameter (weightage %) assigned to each activity reflecting its importance, cost, and effort.
  • S-Curve: Cumulative planned and actual progress plotted against time, shaped like an 'S', used for time monitoring.
  • Weightage Allocation Criteria:
    • Criticality/importance
    • Tentative cost
    • Effort required

Weightage Distribution (Typical Example):

PhasePercent WeightageSub-Phases (Horizontal Scale)
Design (X)5%Submissions 35%, Conditional Approval 55%, Final Approval 10%
Procurement (Y)40%PO Release 10%, Manufacturing 35%, Testing 15%, Dispatch 20%, Delivery 20%
Construction (Z)50%Preparatory 15%, Installation 80%, Inspection 5%
Testing & Commissioning (T)5%Pre-commissioning 30%, Commissioning 40%, Performance 10%, System Integration 20%

Procedure:

  1. Assign weightages to work packages and phases.
  2. Distribute weightages horizontally over activity durations.
  3. Sum weightages cumulatively to plot baseline S-curve.
  4. Track actual progress similarly to plot actual S-curve.
  5. Analyze deviations (vertical/horizontal gaps) for time control.
  6. Prepare catch-up curves if behind schedule.

Sample S-Curve Interpretation:

graph LR
A[Baseline S-Curve] --> B[Actual S-Curve]
B --> C{Deviation?}
C -->|Yes| D[Analyze WBS Level Details]
C -->|No| E[On Schedule]
D --> F[Take Corrective Actions]

Benefits:

  • Unified progress measurement.
  • Visual tool for decision-making.
  • Drill-down analysis at WBS levels.
  • Forecast and catch-up planning.

For detailed tables and examples, refer to Annex C and Clause 6.2.5 of IS 15883 Part 2:2013.

Popular Questions About IS 15883 Part 2

?What methods does IS 15883 Part 2 recommend for project time scheduling?

IS 15883 Part 2 recommends the following methods for project time scheduling:

Recommended Methods

  • Precedence Diagram Method (PDM) or Activity on Node (AON) as per IS 14580 (Part 2).
  • Use of dependency relationships:
    • Finish to Start (FS)
    • Finish to Start with Lag (FS + X days)
    • Start to Start with Lag (SS + X days)
    • Finish to Finish with Lag (FF + X days)
    • Start to Finish with Lag (SF + X days)
    • Finish to Start with Lead (FS - X days)

Steps for Scheduling

  1. Prepare the network diagram based on activity data and dependencies.
  2. Perform forward pass and backward pass calculations to determine:
    • Early start/finish and late start/finish dates
    • Total float and free float
    • Critical activities and critical path
    • Project duration

Deliverables

  • Network diagrams and bar/Gantt charts for each sub-project
  • Master control schedule linking sub-projects
  • Use Line of Balance (LOB) technique for repetitive or linear projects

Additional Notes

  • Time management includes planning, monitoring, and control.
  • Periodic schedule updates and interdisciplinary coordination are essential.
  • Use of construction management software is encouraged for automation.

Loading diagram...

This approach ensures a systematic and dynamic project schedule aligned with IS 15883 Part 2 guidelines.

?How does the standard guide the preparation and use of Work Breakdown Structures (WBS)?

IS 15883 Part 2 Guidance on Work Breakdown Structure (WBS):

  • Purpose: Divide the project into manageable hierarchical components suitable for project complexity and duration.

  • WBS Preparation Approaches (Clause 6.1.3.2):

    • By Project Stages: Pre-construction, construction, commissioning & handover.
    • By Functional Disciplines: Civil, plumbing, electrical, HVAC, etc.
    • By Organizational Structure: Based on department or reporting hierarchy.
    • By Physical Location: Each floor or zone as a sub-project.
  • Hierarchy Levels (Clause 6.1.3.1):

    1. Total project
    2. Sub-projects
    3. Work packages
    4. Minor tasks/activities
  • Format & Coding (Clause 6.1.3.4):

    • Tree or outline style.
    • Lowest nodes = activities for scheduling.
    • Use a standardized alpha-numeric coding system reflecting hierarchy and classification.
    • Enables clear identification and tracking of milestones.

Typical WBS Structure Example:

Loading diagram...

This structured approach ensures clarity, monitoring ease, and integration with scheduling tools like Gantt charts.

?What techniques are suggested for managing time-cost tradeoffs in construction projects?

IS 15883 Part 2 suggests the following techniques for managing time-cost tradeoffs in construction projects:

Key Technique: Siemens Approximation Method (SAM)

  • Objective: Reduce project duration (schedule crashing) with minimal increase in direct cost.
  • Principle: Use the cost slope to identify activities where time can be bought cheaply by adding resources.
  • Cost Slope Formula:

[ \text{Cost slope} = \frac{C_c - C_N}{T_N - T_c} ]

Where:

  • (C_c) = Crash cost (cost at shortest duration)
  • (C_N) = Normal cost
  • (T_N) = Normal time
  • (T_c) = Crash time (minimum duration)

SAM Algorithm Steps:

  1. Calculate project normal duration (PN) via CPM.
  2. Define reduced project duration (PR) as per stakeholder needs.
  3. Identify all project paths and their durations.
  4. Select activities on critical paths needing shortening.
  5. Calculate effective cost slope (cost slope divided by number of critical paths the activity lies on).
  6. Shorten activities with the lowest effective cost slope first.
  7. Continue until project duration meets PR.

Other Acceleration Measures:

  • Adoption of efficient construction technology and equipment-intensive methods.
  • Constructability analysis during project control phase.
  • Consider resource availability, quality, safety, and constraints to optimize time without compromising other project dimensions.

Loading diagram...

This structured approach ensures cost-effective schedule compression aligned with project goals.

?How can project progress be effectively monitored and reported according to this standard?

According to IS 15883 Part 2, effective project progress monitoring and reporting involves the following key steps:

1. Performance Periods & Communication (Clause 5.1.2)

  • Divide the project into performance periods.
  • At each period start, confirm all stakeholders know planned activities and milestone dates.
  • At period end, submit performance reports comparing actual progress vs targets.
  • Investigate and correct time variances, considering cumulative minor scope changes.
  • Focus on critical path activities and those close to critical.
  • Revise targets if delays occur and communicate changes.
  • Repeat this cycle for each period.

2. Project Metrics & Graphical Representation (Clause 5.2.2)

  • Assign project metrics (e.g., earned value, manhours) to activities up to WBS Level 3 or 4.
  • Plot cumulative metrics vs timeline (X-axis: time, Y-axis: metric).
  • Compare baseline and actual progress curves; horizontal offset = time deviation, vertical offset = progress deviation.
  • Drill down into WBS for deviation causes.

3. Activity Tracking & Reporting (Clause 6.2.2 & 6.2.5)

  • Regularly update baseline schedule.
  • Track deviations, forecast progress, and prepare catch-up plans.
  • Monitor critical path and emerging critical activities.
  • Prepare project status reports with:
    • Planned vs achieved progress,
    • Past performance analysis,
    • Critical activity status,
    • Look-ahead program updates.
  • Use a common project metric (earned value, manhours, weightage) for summarization.

Summary Diagram of Monitoring Cycle

Loading diagram...

Key takeaway: Use structured periods, clear communication, metric-based tracking, critical path focus, and iterative corrective actions to ensure effective project progress monitoring and reporting per IS 15883 Part 2.

?What role does resource scheduling and levelling play in optimizing project timelines?

Role of Resource Scheduling and Levelling in Optimizing Project Timelines (IS 15883 Part 2)

Resource scheduling follows time scheduling and involves allocating manpower, material, and equipment resources daily for each activity and the entire project.

Key roles include:

  • Reconciling resource demand with availability to avoid shortages or excesses.
  • Optimizing resource usage uniformly over the project duration, preventing peaks and troughs.
  • Aligning resource schedules with cash flow to ensure financial feasibility.
  • Adjusting resource and time schedules to meet the optimum project finish date without compromising quality or cost.

This ensures:

  • Efficient use of resources,
  • Avoidance of idle time or bottlenecks,
  • Control over project duration and cost escalation,
  • Balanced workload enhancing safety and quality.

Thus, resource scheduling and levelling are critical for realistic, economical, and timely project completion.

Loading diagram...

Need Detailed Clause Answers?

Ask AI about any clause, requirement, or provision in IS 15883 Part 2. Get instant, clause-cited responses powered by our indexed library.

Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required