IS 15883 Part 2: 2013 provides comprehensive guidelines on time management for construction project management in India, covering the period from project approval through commissioning and handover. It addresses planning, scheduling, monitoring, and controlling project timelines using techniques like Work Breakdown Structure (WBS), network diagrams, and time-cost tradeoff analysis. This standard is essential for project managers and construction professionals aiming to optimize project duration while balancing resources, costs, and quality.
Overview
IS 15883 Part 2: 2013 provides comprehensive guidelines on time management for construction project management in India, covering the period from project approval through commissioning and handover. It addresses planning, scheduling, monitoring, and controlling project timelines using techniques like Work Breakdown Structure (WBS), network diagrams, and time-cost tradeoff analysis. This standard is essential for project managers and construction professionals aiming to optimize project duration while balancing resources, costs, and quality.
Audience
Contents
Structure
[ \textbf{Productivity Standard (p)} = \text{Productivity Norms} \times \text{Production Efficiency Factor} ]
| Phase | Weightage (%) Example |
|---|---|
| Design | 5 |
| Procurement | 40 |
| Construction | 50 |
| Testing & Commissioning | 5 |
| Sub-Phase | Weightage (%) |
|---|---|
| Raw Material/PO Release | 10 |
| Manufacturing | 35 |
| Testing During Manufacturing | 15 |
| Dispatch | 20 |
| Delivery to Site | 20 |
IS 15883 Part 2: Key References, Formulas & Tables Summary
[ \text{Productivity standard} (p) = \text{Productivity norms} \times \text{Production efficiency factor} ]
Concept: Assign weightages (%) to project activities/phases; plot cumulative planned vs actual progress (S-curve).
Weightage Criteria:
Phases & Sample Weightages:
| Phase | Typical Weightage (%) | Subdivision Example |
|---|---|---|
| Design | 5 | Submissions 35%, Conditional Approval 55%, Final Approval 10% |
| Procurement | 40 | Raw Material 10%, Manufacturing 35%, Testing 15%, Dispatch 20%, Delivery 20% |
| Construction | 50 | Preparatory 15%, Installation 80%, Inspection 5% |
| Testing & Commissioning | 5 | Pre-commissioning 30%, Commissioning 40%, Performance 10%, Integration 20% |
[ \text{Productivity Standard (p)} = \text{Productivity Norms} \times \text{Production Efficiency Factor} ]
S-Curve: Cumulative weighted progress curve shaped like 'S' for project time monitoring.
Weightage Allocation Criteria:
Typical Weightage Distribution for Work Phases:
| Phase | Percent Weightage Example |
|---|---|
| Design | 5% |
| Procurement | 40% |
| Construction | 50% |
| Testing & Commissioning | 5% |
| Sub-Phase | Weightage (%) |
|---|---|
| Preparatory Works | 15 |
| Installation | 80 |
| Checking/Inspection | 5 |
flowchart LR
A[Productivity Norms] --> C[Productivity Standard]
B[Production Efficiency Factor] --> C
This concise summary provides essential definitions, formulas, and tables for productivity and project monitoring as per IS 15883 (Part 2). For detailed tables and examples,
IS 15883 Part 2: General Principles of Time Management
[ \text{Project Duration} = \sum \text{Activity Durations} + \text{Slack/Float} ]
graph TD
A[Start] --> B[Activity 1]
B --> C[Activity 2]
B --> D[Activity 3]
C --> E[Activity 4]
D --> E
E --> F[Finish]
This diagram shows dependencies and parallel activities.
Summary: Time management is a continuous, integrated process involving planning, monitoring, and control, supported by network analysis (IS 14580) and software tools, while considering all project constraints and quality/safety standards.
IS 15883 (Part 2) - Time Management Key Points
| Aspect | Categories |
|---|---|
| Type of Work | Building, Infrastructure, Industrial, Others |
| Project Duration | >5 yrs (Long), 3-5 yrs (Medium), 1-3 yrs (Short), <1 yr (Special Short-term) |
| Project Value | Mega, Large, Medium, Small |
| Execution Speed | Fast track, Normal pace |
flowchart TD
A[Define Project Scope] --> B[Estimate Activity Durations]
B --> C[Sequence Activities]
C --> D[Develop Schedule (Network/Gantt)]
D --> E[Monitor & Control Schedule]
E --> F[Update & Revise Schedule]
This concise framework helps manage project time effectively per IS 15883 Part 2.
IS 15883 (Part 2) - Time Planning & Scheduling Techniques
| Parameter | Formula |
|---|---|
| Total Float | TF = LS - ES = LF - EF |
| Free Float | FF = Earliest ES of successor - EF |
graph TD
A[Start] --> B[Activity 1]
B --> C[Activity 2]
C --> D[Activity 3]
D --> E[Finish]
click B "FS
IS 15883 Part 2: Activity Identification & Network Preparation Key Points
Estimate resources per activity/day using:
[ \text{Resource per day} = \frac{\text{Total resource quantity}}{\text{Activity duration}} ]
Superimpose resource data on time schedule.
Resource levelling includes:
| Relationship Type | Description | Notation |
|---|---|---|
| Finish to Start | Successor starts after predecessor finishes | FS |
| Finish to Start + Lag | Successor starts after lag days post predecessor finish | FS + X days |
(IS 15883 Part 2: 2013, Clauses 6.1.8.2 & 6.1.10)
| Type | Notation | Description |
|---|---|---|
| Finish to Start | FS | Successor starts after predecessor finishes |
| Finish to Start with Lag | FS + X days | Successor starts X days after predecessor finishes |
| Start to Start with Lag | SS + X days | Successor starts X days after predecessor starts |
| Finish to Finish with Lag | FF + X days | Successor finishes X days after predecessor finishes |
| Start to Finish with Lag | SF + X days | Successor finishes X days after predecessor starts |
| Finish to Start with Lead | FS - X days | Successor starts X days before predecessor finishes |
Early Finish (EF):
[
EF = ES + \text{Activity Duration} - 1
]
Late Start (LS):
[
LS = LF - \text{Activity Duration} + 1
]
Total Float (TF):
[
TF = LS - ES = LF - EF
]
Free Float (FF):
[
FF = \text{Earliest ES of successor} - EF - 1
]
Critical Path: Activities with Total Float = 0
Resource Scheduling & Levelling (IS 15883 Part 2)
[ \boxed{ p = \text{Productivity Norms} \times \text{Production Efficiency Factor} } ]
[ \text{Resource Required} = \frac{\text{Work Quantity}}{p \times \text{Activity Duration}} ]
| Step | Description |
|---|---|
| 1. Estimate Productivity | Use norms × efficiency factor |
| 2. Calculate Resource Req. | Work quantity / (productivity × duration) |
| 3. Time Scheduling | Network diagram, forward/backward pass |
| 4. Superimpose Resources | Map resource needs over time |
| 5. Resource Levelling | Reconcile & optimize resource usage & costs |
flowchart TD
A[Estimate Productivity] --> B[Calculate Resource Requirement]
B --> C[Prepare Network Diagram]
C --> D[Forward & Backward Pass]
D --> E[Superimpose Resource Data]
E --> F[
IS 15883 Part 2: Progress Monitoring & Reporting Key Points
[ \text{Earned Value (EV)} = \text{Budgeted Cost of Activity} \times \text{Percent Complete} ]
| Activity | Planned Metric | Actual Metric | Variance (Planned - Actual) | Status |
|---|---|---|---|---|
| A | 100 | 90 | -10 | Behind |
| B | 50 | 55 | +5 | Ahead |
gantt
title Project Progress Monitoring
dateFormat YYYY-MM-DD
section Baseline Plan
Activity A :done, 2024-01-01, 10d
Activity B :done, 2024-01-11, 15d
section Actual Progress
Activity A :active, 2024-01-01, 8d
Activity B :active, 2024-01-13, 12d
section Catch-up Plan
Activity A :crit, 2024-01-09, 4d
Summary:
Use a common metric (earned value/manhours/weightage) for all activities. Track progress daily,
IS 15883 Part 2: Time-Cost Tradeoff & Schedule Compression Key Points
| Parameter | Symbol | Description |
|---|---|---|
| Normal Cost | CN | Cost at normal duration |
| Crash Cost | Cc | Cost at minimum (crash) duration |
| Normal Time | TN | Most likely activity duration |
| Crash Time | Tc | Minimum possible activity duration |
[ \text{Cost slope} = \frac{C_c - C_N}{T_N - T_c} ]
| Parameter | Symbol | Unit | Description | |---------------------|---------|------------|
IS 15883 Part 2: Key Points on Change Management for Schedule Acceleration
| Activity | ES (Early Start) | EF (Early Finish) | LS (Late Start) | LF (Late Finish) | Float = LS-ES |
|---|---|---|---|---|---|
| A | 0 | 5 | 0 | 5 | 0 |
| B | 5 | 10 | 7 | 12 | 2 |
flowchart TD
A[Start] --> B[Activity A]
B --> C[Activity B]
C --> D[Finish]
style B stroke:#f66,stroke-width:2px
style C stroke:#f66,stroke-width:2px
Summary: Use heuristic algorithms (e.g., Modified Siemens) for optimal schedule acceleration, apply PDM/AON with dependency types, perform forward/backward pass for scheduling, and prepare linked network/bar charts
Time-Cost Tradeoff Algorithm (Siemens Approximation Method - SAM) per IS 15883 Part 2
Cost Slope (CS):
[
CS = \frac{C_c - C_N}{T_N - T_c}
]
Where:
Deterministic Activity Duration:
[
T_E = \frac{q}{p \times n}
]
Where:
Probabilistic Activity Duration (PERT formula):
[
T_p = \frac{a + 4m + b}{6}
]
Where:
flowchart TD
A[Start: CPM & Project Normal Duration (PN)] --> B[Set Reduced Duration
Earned Value Management (EVM) Key Formulas & Specifications (IS 15883 Part 2)
EV Calculation:
[ \text{EV} = \text{Baseline Cost} \times % \text{Complete} ]
| Indicator | Formula | Interpretation |
|---|---|---|
| Schedule Performance Indicator (SPI) | (\text{SPI} = \frac{\text{EV}}{\text{PV}}) | SPI > 1: Ahead of schedule; SPI < 1: Behind schedule |
flowchart LR
PV[Planned Value (PV)]
AC[Actual Cost (AC)]
EV[Earned Value (EV)]
SPI[Schedule Performance Indicator (SPI)]
PV --> SPI
EV --> SPI
SPI -->|SPI = EV / PV| Status{Project Status}
Status -->|SPI > 1| Ahead[Ahead of Schedule]
Status -->|SPI < 1| Behind[Behind Schedule]
Use EVM to:
For detailed tables and graphical reports, refer to Annex B of IS 15883 Part 2.
IS 15883 Part 2: Sample Time Monitoring Based on Weightage Concept (S-Curve)
| Phase | Percent Weightage | Sub-Phases (Horizontal Scale) |
|---|---|---|
| Design (X) | 5% | Submissions 35%, Conditional Approval 55%, Final Approval 10% |
| Procurement (Y) | 40% | PO Release 10%, Manufacturing 35%, Testing 15%, Dispatch 20%, Delivery 20% |
| Construction (Z) | 50% | Preparatory 15%, Installation 80%, Inspection 5% |
| Testing & Commissioning (T) | 5% | Pre-commissioning 30%, Commissioning 40%, Performance 10%, System Integration 20% |
graph LR
A[Baseline S-Curve] --> B[Actual S-Curve]
B --> C{Deviation?}
C -->|Yes| D[Analyze WBS Level Details]
C -->|No| E[On Schedule]
D --> F[Take Corrective Actions]
For detailed tables and examples, refer to Annex C and Clause 6.2.5 of IS 15883 Part 2:2013.
Frequently Asked
IS 15883 Part 2 recommends the following methods for project time scheduling:
Loading diagram...
This approach ensures a systematic and dynamic project schedule aligned with IS 15883 Part 2 guidelines.
IS 15883 Part 2 Guidance on Work Breakdown Structure (WBS):
Purpose: Divide the project into manageable hierarchical components suitable for project complexity and duration.
WBS Preparation Approaches (Clause 6.1.3.2):
Hierarchy Levels (Clause 6.1.3.1):
Format & Coding (Clause 6.1.3.4):
Loading diagram...
This structured approach ensures clarity, monitoring ease, and integration with scheduling tools like Gantt charts.
IS 15883 Part 2 suggests the following techniques for managing time-cost tradeoffs in construction projects:
[ \text{Cost slope} = \frac{C_c - C_N}{T_N - T_c} ]
Where:
Loading diagram...
This structured approach ensures cost-effective schedule compression aligned with project goals.
According to IS 15883 Part 2, effective project progress monitoring and reporting involves the following key steps:
Loading diagram...
Key takeaway: Use structured periods, clear communication, metric-based tracking, critical path focus, and iterative corrective actions to ensure effective project progress monitoring and reporting per IS 15883 Part 2.
Role of Resource Scheduling and Levelling in Optimizing Project Timelines (IS 15883 Part 2)
Resource scheduling follows time scheduling and involves allocating manpower, material, and equipment resources daily for each activity and the entire project.
Key roles include:
This ensures:
Thus, resource scheduling and levelling are critical for realistic, economical, and timely project completion.
Loading diagram...
Ask AI about any clause, requirement, or provision in IS 15883 Part 2. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required