Design and installation of natural gas pipelines – Code of Practice: Part 3 Pre-commissioning and commissioning of pipelines

IS 15663 Part 3 (2006) provides a comprehensive code of practice for the pre-commissioning and commissioning of natural gas pipelines in India. It outlines procedures for mechanical completion checks, cleaning, drying, inertisation, leak testing, and gas introduction to ensure pipeline integrity, safety, and operational readiness. This standard is essential for engineers and professionals involved in the final preparation and startup of natural gas pipeline systems, including underground and above-ground piping components.

7Sections
76Clauses Indexed
AI Search Ready
2006Edition
Structural Engineering and structural sectionsCategory
Alternative search terms: IS 15663 Part 3 PDF, IS 15663 Part 3 pdf free download, IS 15663 Part 3 free download pdf, IS15663Part3 PDF, IS-15663-Part-3 PDF, IS 15663 Part 3 2006 PDF, IS 15663 Part 3:2006 PDF, IS 15663 Part 3-2006 PDF, IS 15663 Part 3 (2006) PDF, IS 15663 Part 3 2006 edition PDF, IS 15663 Part 3 edition 2006 PDF

What This Standard Covers

IS 15663 Part 3 (2006) provides a comprehensive code of practice for the pre-commissioning and commissioning of natural gas pipelines in India. It outlines procedures for mechanical completion checks, cleaning, drying, inertisation, leak testing, and gas introduction to ensure pipeline integrity, safety, and operational readiness. This standard is essential for engineers and professionals involved in the final preparation and startup of natural gas pipeline systems, including underground and above-ground piping components.

Who Uses This Standard

  • Pipeline Design Engineers
  • Commissioning Engineers
  • Pipeline Construction Supervisors
  • Quality Assurance and Quality Control (QA/QC) Inspectors
  • Safety Engineers
  • Operations and Maintenance Engineers
  • Project Managers in Oil and Gas Infrastructure

Key Topics Covered

Pre-commissioning mechanical completion checks
Pipeline cleaning and swabbing procedures
Magnetic cleaning and electronic geometry pigging
Drying and dewatering of pipelines
Leak testing of above-ground piping
Inertisation using nitrogen gas
Gas introduction and commissioning criteria
Acceptance criteria for pre-commissioning activities
Instrumentation and control system checks
Safety and emergency preparedness during commissioning
Documentation requirements for commissioning
Communication and electrical system verification

Table of Contents

1Scope

IS 15663 Part 3 — Scope Summary

  • Scope: Covers pipeline systems for petroleum, natural gas, and related facilities, referencing international standards like ISO 13623, ASME B31.8, API RP 1102, and API RP 1104 for comprehensive guidance.

  • Documentation (Clause 7.2): Requires preparation of documents addressing:

    • Health, Safety, and Environment (HSE)
    • Quality Assurance (QA)
    • Quality Control (QC) plans
  • Definitions: As per IS 15663 Part 1.


Key Specifications & References

StandardFocus Area
ISO 13623Pipeline transportation systems
ASME B31.8Gas transmission and distribution
API RP 1102Pipeline crossings (railroads, highways)
API RP 1104Welding of pipelines

Important Notes:

  • Use the latest editions of referenced standards.
  • BIS holds copyright; use of symbols, sizes, and grades is allowed for implementation.
  • Documentation must comprehensively cover HSE, QA, and QC aspects.

If you need formulas or tables related to design, welding, or testing, please specify the exact clause or topic.

2References

IS 15663 Part 3 - References Summary

  • Key International Standards Referenced:

    • ISO 13623: Pipeline transportation systems for petroleum and natural gas.
    • ASME B31.8: Gas transmission and distribution systems.
    • API RP 1102: Steel pipeline crossings of railroads and highways.
    • API RP 1104: Welding of pipelines and related facilities.
  • Documentation Requirements (Clause 7.2):

    • Prepare documents covering Health, Safety & Environment (HSE).
    • Include Quality Assurance (QA) and Quality Control (QC) plans.
  • Standard Revision & Copyright:

    • Always check for the latest edition of referenced standards.
    • BIS holds copyright; permission needed for reproduction except for implementation details.
  • Contact & Regional Offices:

    • BIS headquarters: Manak Bhavan, New Delhi.
    • Regional offices in Kolkata, Chandigarh, Chennai, Mumbai, and branches nationwide.

Practical Notes:

  • Use referenced standards for detailed design, welding, and safety requirements.
  • Maintain updated documentation per Clause 7.2 for compliance.
  • Refer to IS 15663 Part 1 for definitions.
flowchart LR
    A[IS 15663 Part 3] --> B[International Standards]
    B --> ISO13623[ISO 13623]
    B --> ASME_B31_8[ASME B31.8]
    B --> API_RP_1102[API RP 1102]
    B --> API_RP_1104[API RP 1104]
    A --> C[Documentation Clause 7.2]
    C --> HSE[Health, Safety & Environment]
    C --> QA_QC[Quality Assurance & Control]
    A --> D[BIS Contacts & Offices]

For detailed design formulas or tables, consult the individual referenced standards as IS 15663 Part 3 primarily provides references and documentation guidelines.

3Definitions

IS 15663 Part 3 - Definitions Summary

  • This part refers to definitions as per IS 15663 Part 1; no new definitions are provided here.
  • For understanding terms related to pipeline systems, refer to IS 15663 Part 1.
  • The standard aligns with international codes like ISO 13623, ASME B31.8, API RP 1102, and API RP 1104 for consistent terminology and practices.
  • Definitions cover key pipeline terms such as:
    • Pipeline transportation system
    • Welding and inspection terms
    • Quality assurance and control terminology
    • Health, safety, and environment (HSE) concepts

Recommended Action:

  • Consult IS 15663 Part 1 for detailed definitions.
  • Use referenced international standards for cross-verification of terms.
  • Ensure documentation complies with Clause 7.2 for HSE and QA/QC plans.

Diagram: Reference Flow for Definitions

flowchart LR
    A[IS 15663 Part 3] --> B[Definitions]
    B --> C[Refer to IS 15663 Part 1]
    C --> D[International Standards]
    D --> E[ISO 13623]
    D --> F[ASME B31.8]
    D --> G[API RP 1102]
    D --> H[API RP 1104]

Summary: IS 15663 Part 3 defers all definitions to Part 1; consult Part 1 for exact terminology used in pipeline design, construction, and quality assurance.

4Pre-commissioning Procedure

IS 15663 Part 3 — Pre-commissioning Procedure (Clause 5.2)

Key Steps in Pre-commissioning (Clause 5.1)

  • De-watering: Remove residual water from the pipeline to prevent corrosion.
  • Flushing & Dry Air Blowing: Clean above-ground piping at all stations (dispatch, receiving, valve, pigging, hook-up).
  • Swabbing: Use swabs to remove debris and moisture inside the pipeline.
  • Low Pressure Leak Check: Conduct air leak tests on above-ground pipeline sections.
  • Documentation: Prepare detailed pre-commissioning procedures covering all activities.

Important Specifications:

  • Leak Test Pressure: Typically 1.1 times the design pressure or as specified by the project.
  • Flushing Velocity: Maintain a minimum flow velocity (e.g., 1.5 m/s) to ensure debris removal.
  • Dry Air Pressure: Use clean, dry air at a pressure slightly above atmospheric to ensure drying.

Typical Pre-commissioning Flowchart:

flowchart TD
    A[Start Pre-commissioning] --> B[De-watering]
    B --> C[Flushing & Dry Air Blowing]
    C --> D[Swabbing]
    D --> E[Low Pressure Leak Check]
    E --> F[Documentation & Approval]
    F --> G[Ready for Commissioning]

Note: Refer Clause 6.2 for commissioning procedures following pre-commissioning.

5Pre-commissioning Checks

IS 15663 Part 3 — Pre-commissioning Checks (Clause 5.2.1)

Pre-commissioning ensures mechanical completion and system readiness before commissioning. Key checks include:

  • Pipe Cover Check:

    • Conduct every 500 m using instruments like Pipe Current Measurement (PCM) to verify coating integrity and cathodic protection.
  • System Checks:

    • Verify all facilities against design drawings and specs; record and rectify discrepancies.
  • Field Instruments & Equipment:

    • Physically inspect actuated valves, control valves, shut down valves, transmitters, solenoid valves, alarms, meters, and gauges for functionality and correct application.
  • Pipeline Survey:

    • Confirm installation of fittings, supports, cathodic protection, route markers, warning signs, fencing, and crash barriers.
  • Communication & Electrical Systems:

    • Test communication reliability; verify uninterrupted power supply and earth resistance of earth pits, lightning arresters, and equipment. Check compliance with area classification.
  • Instrument Controls & Interlocks:

    • Ensure controls and interlocks operate as per normal conditions.
  • Utilities & Alarm Systems:

    • Check power, UPS, water, air supplies, and alarm functioning.
  • Safety Preparedness:

    • Identify emergencies and verify mitigation measures.

Summary Table of Pre-commissioning Checks

Check AreaKey PointsFrequency/Notes
Pipe CoverPCM every 500 mContinuous along pipeline
System VerificationAgainst drawings/specsOne-time before commissioning
Field InstrumentsPhysical & functional checkOne-time
Pipeline SurveySupports, CP, markers, fencingOne-time
Communication SystemUninterrupted communicationOne-time
Electrical SystemPower supply, earth resistance, area complianceOne-time
Instrument Controls & InterlocksFunctional as per designOne-time
UtilitiesPower, UPS, water, airOne-time
Alarm SystemsAlarm setting and functioningOne-time
SafetyEmergency preparednessOne-time

Additional Notes:

  • Documentation of all pre-commissioning checks is mandatory (Clause 7.1a).
  • Follow-up commissioning steps include leak tests,
6Commissioning Procedure

IS 15663 Part 3: Commissioning Procedure Key Points

1. Commissioning Procedure (Clause 6.2)

  • Ensures system readiness by validating integrity and operational performance.
  • Includes pressure testing, leak checks, and functional testing.

2. Pre-commissioning Procedure (Clause 5.2)

  • Preparation steps before commissioning, such as cleaning, drying, and inspection.
  • Key activities:
    • Residual dewatering and swabbing
    • Magnetic cleaning and EGP (Electrochemical Gas Purification)
    • Leak testing with dry compressed air at low pressure

3. Commissioning Documentation (Clause 7.1)

Must include records of:

  • Pre-commissioning checks
  • Residual dewatering and swabbing
  • Low pressure leak check (dry air)
  • Magnetic cleaning and EGP documentation
  • Inertisation process
  • Gas-in and commissioning activities:
    • Pressurization of pipeline
    • High pressure leak check
    • Establishment of flows
    • 72-hour continuous run test

Typical Leak Test Pressure Formula:

[ P_{test} = 1.5 \times P_{design} ]

Where:

  • (P_{test}) = Test pressure
  • (P_{design}) = Design pressure of the pipeline/system

Summary Table of Key Activities

ActivityDescriptionClause Reference
Pre-commissioning checksInspection, cleaning, drying5.2
Residual dewatering/swabbingRemoval of water and debris7.1(b)
Low pressure leak testDry compressed air, low pressure7.1(c)
Magnetic cleaning & EGPRemoval of magnetic particles7.1(d)
InertisationFilling with inert gas to prevent oxidation7.1(e)
Gas-in & commissioningPressurization, high pressure leak test, flow establishment, 72h run7.1(f)

flowchart TD
    A[Pre-commissioning] --> B[Residual Dewatering & Swabbing]
    B --> C[Magnetic Cleaning & EGP]
    C --> D[Low Pressure Leak
7Documentation

IS 15663 Part 3 — Documentation Key Points

Clause 7.1: Commissioning Documentation Must Include:

  • Pre-commissioning checks
  • Residual dewatering and swabbing records
  • Low pressure leak check (above ground piping with dry compressed air)
  • Magnetic cleaning and External Grounding Protection (EGP) documents
  • Inertisation procedures
  • Gas-in and commissioning activities:
    • Pipeline pressurization
    • High pressure leak check
    • Establishment of flows
    • 72-hour run test

Clause 7.2: Documentation Requirements

  • Cover Health, Safety, and Environment (HSE) aspects
  • Include Quality Assurance (QA) and Quality Control (QC) plans

Related International Standards for Reference

StandardScope
ISO 13623Pipeline transportation systems in petroleum/natural gas industries
ASME B31.8Gas transmission and distribution systems
API RP 1102Steel pipeline crossings at railroads/highways
API RP 1104Welding of pipelines and related facilities

Summary Table: Documentation Components

Documentation AspectDescription
Pre-commissioning checksVerifying system readiness before operation
Dewatering & SwabbingRemoving residual fluids to prevent corrosion
Leak ChecksLow and high pressure leak testing
Cleaning & EGPMagnetic cleaning and grounding protection records
InertisationProcedures to remove oxygen or contaminants
Commissioning ActivitiesPressurization, flow establishment, and run tests

This ensures comprehensive traceability and compliance with safety and quality standards during pipeline commissioning.

flowchart TD
    A[Pre-commissioning Checks] --> B[Dewatering & Swabbing]
    B --> C[Low Pressure Leak Check]
    C --> D[Magnetic Cleaning & EGP]
    D --> E[Inertisation]
    E --> F[Gas-in & Commissioning Activities]
    F --> G[High Pressure Leak Check]
    G --> H[Flow Establishment & 72h Run]

This flowchart illustrates the sequential documentation process for commissioning.

Popular Questions About IS 15663 Part 3

?What are the required pre-commissioning checks before pipeline commissioning?

Pre-commissioning Checks as per IS 15663 Part 3 (Clause 5.2.1):

Before pipeline commissioning, ensure the pipeline system (up to first isolation valve) is mechanically complete by performing:

  • Pipe Cover Check: Every 500 m using instruments like Pipe Current Measurement (PCM).
  • System Verification: Cross-check all facilities against design drawings and specs; record and rectify discrepancies.
  • Field Instruments/Equipment: Physically inspect actuated valves, control valves, transmitters, solenoid valves, shutdown switches, alarms, meters, and gauges.
  • Pipeline Survey: Confirm installation of fittings, supports, cathodic protection, route markers, fencing, and crash barriers.
  • Communication System: Verify uninterrupted communication capability.
  • Electrical System: Check power supply reliability, earth resistance, and compliance with area classification.
  • Instrument Controls & Interlocks: Ensure functionality as per operating conditions.
  • Utilities: Verify power, UPS, water, air, instrument air conditioning, etc.
  • Alarm Systems: Test alarms for proper functioning.
  • Safety Preparedness: Identify potential emergencies and mitigation readiness.

Additional Notes:

  • Pre-commissioning starts only after hydrostatic testing, backfilling, instrument installation, and cathodic protection are complete.
  • Procedures must prevent introduction of incompatible materials into the pipeline.

Summary Table of Pre-commissioning Checks

Check CategoryKey Activities
Pipe CoverPCM check every 500 m
System VerificationCross-check with design docs
Field InstrumentsPhysical and functional check of valves, meters
Pipeline SurveyVerify supports, CP, markers, fencing
CommunicationEnsure uninterrupted communication
Electrical SystemPower supply, earth resistance, classification
Instrument ControlsFunctional interlocks and controls
UtilitiesCheck power, UPS, water, air systems
Alarm SystemsTest alarm triggering and response
SafetyEmergency identification and mitigation readiness
Loading diagram...
?How is pipeline cleaning and drying performed according to this standard?

Pipeline Cleaning and Drying as per IS 15663 Part 3

  1. Magnetic Cleaning (Clause 6.2.1):

    • Use bi-directional brush magnetic pigs to remove metallic debris.
    • Conduct after swabbing and tie-in, propelled by super dry air.
    • Prepare a detailed procedure before starting.
  2. Swabbing Operation (Clause 5.2.2.1):

    • Performed after dewatering to remove residual water.
    • Use absorbent pigs propelled by oil-free compressed dry air.
    • Employ compressors, after-coolers, and driers for air supply.
  3. Drying Operation (Clauses 6.2.3.1 & 2.0):

    • Dry pipelines (underground, above-ground, stations) before gas charging.
    • Use super dry air or vacuum drying.
    • Drying is complete when water dew point reaches -10°C at atmospheric pressure.
    • Maintain pipeline pressure at 2.0 kg/cm² with dry air at this dew point until inertisation.
    • Alternatively, nitrogen can break vacuum post drying if gas-in follows immediately.

Loading diagram...

This sequence ensures corrosion prevention and pipeline integrity before commissioning.

?What acceptance criteria must be met for inertisation using nitrogen gas?

Acceptance Criteria for Inertisation Using Nitrogen Gas (IS 15663 Part 3, Clause 6.2.5.2):

  • Residual Oxygen Content: Must be below 1% (vol/vol) in the pipeline and above-ground piping at dispatch/receipt stations, valve stations, pigging stations, and hook-up/tap-off points.
  • Nitrogen Quantity: Adequate volume of nitrogen introduced, separated by batching pigs, with total nitrogen slug length ≥ 10% of pipeline length (Clause 6.2.5.1).
  • Nitrogen Purity: Nitrogen gas must be pure enough to meet the oxygen residual criterion.
  • Nitrogen State: Use compressed, vaporized, or gaseous nitrogen at ambient temperature (not liquid nitrogen directly, unless precautions are taken).
  • Drying Precondition: Pipeline must be dried to a dew point of -10°C before inertisation (Clause 2.0).

Summary Table

ParameterRequirement
Residual Oxygen Content< 1% (vol/vol)
Nitrogen Slug Length≥ 10% of pipeline length
Nitrogen PuritySufficient to meet oxygen criterion
Nitrogen StateCompressed/vaporized/gaseous at ambient temperature
Drying Dew Point Before Inertisation≤ -10°C
Loading diagram...

This ensures safe commissioning by removing oxygen and moisture effectively.

?How does the standard recommend conducting leak tests on above-ground piping?

IS 15663 Part 3: Leak Testing of Above-Ground Piping

  • Scope: Leak test applies to above-ground piping sections, especially at flange points, equipment connections, and instrument impulse tubing.

  • Test Medium: Use dry, oil-free compressed air to pressurize the system.

  • Leak Detection: Apply soap solution or use a suitable digital pressure gauge to identify leaks visually or by pressure drop.

  • Test Pressure: Conduct the test at 6.0 kg/cm² (approx. 0.6 MPa). The system passes if no leaks are detected at this pressure.

  • Completion: The leak check is complete only when the system is verified leak-free at the specified pressure.

Loading diagram...

Summary: Pressurize above-ground piping to 6.0 kg/cm² with dry air, check all joints with soap solution or digital gauges, and ensure no leaks before commissioning.

?What documentation is necessary to demonstrate compliance with commissioning procedures?

To demonstrate compliance with commissioning procedures as per IS 15663 Part 3, the documentation must include:

  • Pre-commissioning checks records (Clause 7.1a)
  • Residual dewatering and swabbing evidence (Clause 7.1b)
  • Low pressure leak test results of above ground piping with dry compressed air (Clause 7.1c)
  • Documentation on magnetic cleaning and EGP (Electrochemical Gas Purification) (Clause 7.1d)
  • Records of inertisation procedures (Clause 7.1e)
  • Detailed records of gas-in and commissioning activities, including:
    • Pressurization of pipeline system
    • High pressure leak checks
    • Establishment of flows
    • Successful continuous operation for minimum 72 hours at stable conditions (Clause 7.1f, 6.2.6.2)

Acceptance criteria: Pipeline must be leak-free, charged with natural gas, and stable for 72 hours, including all branches and auxiliary facilities.

This documentation ensures traceability and compliance with safety and operational standards during commissioning.