IS 15663 Part 3 (2006) provides a comprehensive code of practice for the pre-commissioning and commissioning of natural gas pipelines in India. It outlines procedures for mechanical completion checks, cleaning, drying, inertisation, leak testing, and gas introduction to ensure pipeline integrity, safety, and operational readiness. This standard is essential for engineers and professionals involved in the final preparation and startup of natural gas pipeline systems, including underground and above-ground piping components.
Overview
IS 15663 Part 3 (2006) provides a comprehensive code of practice for the pre-commissioning and commissioning of natural gas pipelines in India. It outlines procedures for mechanical completion checks, cleaning, drying, inertisation, leak testing, and gas introduction to ensure pipeline integrity, safety, and operational readiness. This standard is essential for engineers and professionals involved in the final preparation and startup of natural gas pipeline systems, including underground and above-ground piping components.
Audience
Contents
Structure
IS 15663 Part 3 — Scope Summary
Scope: Covers pipeline systems for petroleum, natural gas, and related facilities, referencing international standards like ISO 13623, ASME B31.8, API RP 1102, and API RP 1104 for comprehensive guidance.
Documentation (Clause 7.2): Requires preparation of documents addressing:
Definitions: As per IS 15663 Part 1.
| Standard | Focus Area |
|---|---|
| ISO 13623 | Pipeline transportation systems |
| ASME B31.8 | Gas transmission and distribution |
| API RP 1102 | Pipeline crossings (railroads, highways) |
| API RP 1104 | Welding of pipelines |
If you need formulas or tables related to design, welding, or testing, please specify the exact clause or topic.
IS 15663 Part 3 - References Summary
Key International Standards Referenced:
Documentation Requirements (Clause 7.2):
Standard Revision & Copyright:
Contact & Regional Offices:
flowchart LR
A[IS 15663 Part 3] --> B[International Standards]
B --> ISO13623[ISO 13623]
B --> ASME_B31_8[ASME B31.8]
B --> API_RP_1102[API RP 1102]
B --> API_RP_1104[API RP 1104]
A --> C[Documentation Clause 7.2]
C --> HSE[Health, Safety & Environment]
C --> QA_QC[Quality Assurance & Control]
A --> D[BIS Contacts & Offices]
For detailed design formulas or tables, consult the individual referenced standards as IS 15663 Part 3 primarily provides references and documentation guidelines.
IS 15663 Part 3 - Definitions Summary
flowchart LR
A[IS 15663 Part 3] --> B[Definitions]
B --> C[Refer to IS 15663 Part 1]
C --> D[International Standards]
D --> E[ISO 13623]
D --> F[ASME B31.8]
D --> G[API RP 1102]
D --> H[API RP 1104]
Summary: IS 15663 Part 3 defers all definitions to Part 1; consult Part 1 for exact terminology used in pipeline design, construction, and quality assurance.
IS 15663 Part 3 — Pre-commissioning Procedure (Clause 5.2)
flowchart TD
A[Start Pre-commissioning] --> B[De-watering]
B --> C[Flushing & Dry Air Blowing]
C --> D[Swabbing]
D --> E[Low Pressure Leak Check]
E --> F[Documentation & Approval]
F --> G[Ready for Commissioning]
Note: Refer Clause 6.2 for commissioning procedures following pre-commissioning.
IS 15663 Part 3 — Pre-commissioning Checks (Clause 5.2.1)
Pre-commissioning ensures mechanical completion and system readiness before commissioning. Key checks include:
Pipe Cover Check:
System Checks:
Field Instruments & Equipment:
Pipeline Survey:
Communication & Electrical Systems:
Instrument Controls & Interlocks:
Utilities & Alarm Systems:
Safety Preparedness:
| Check Area | Key Points | Frequency/Notes |
|---|---|---|
| Pipe Cover | PCM every 500 m | Continuous along pipeline |
| System Verification | Against drawings/specs | One-time before commissioning |
| Field Instruments | Physical & functional check | One-time |
| Pipeline Survey | Supports, CP, markers, fencing | One-time |
| Communication System | Uninterrupted communication | One-time |
| Electrical System | Power supply, earth resistance, area compliance | One-time |
| Instrument Controls & Interlocks | Functional as per design | One-time |
| Utilities | Power, UPS, water, air | One-time |
| Alarm Systems | Alarm setting and functioning | One-time |
| Safety | Emergency preparedness | One-time |
IS 15663 Part 3: Commissioning Procedure Key Points
Must include records of:
[ P_{test} = 1.5 \times P_{design} ]
Where:
| Activity | Description | Clause Reference |
|---|---|---|
| Pre-commissioning checks | Inspection, cleaning, drying | 5.2 |
| Residual dewatering/swabbing | Removal of water and debris | 7.1(b) |
| Low pressure leak test | Dry compressed air, low pressure | 7.1(c) |
| Magnetic cleaning & EGP | Removal of magnetic particles | 7.1(d) |
| Inertisation | Filling with inert gas to prevent oxidation | 7.1(e) |
| Gas-in & commissioning | Pressurization, high pressure leak test, flow establishment, 72h run | 7.1(f) |
flowchart TD
A[Pre-commissioning] --> B[Residual Dewatering & Swabbing]
B --> C[Magnetic Cleaning & EGP]
C --> D[Low Pressure Leak
Clause 7.1: Commissioning Documentation Must Include:
Clause 7.2: Documentation Requirements
| Standard | Scope |
|---|---|
| ISO 13623 | Pipeline transportation systems in petroleum/natural gas industries |
| ASME B31.8 | Gas transmission and distribution systems |
| API RP 1102 | Steel pipeline crossings at railroads/highways |
| API RP 1104 | Welding of pipelines and related facilities |
| Documentation Aspect | Description |
|---|---|
| Pre-commissioning checks | Verifying system readiness before operation |
| Dewatering & Swabbing | Removing residual fluids to prevent corrosion |
| Leak Checks | Low and high pressure leak testing |
| Cleaning & EGP | Magnetic cleaning and grounding protection records |
| Inertisation | Procedures to remove oxygen or contaminants |
| Commissioning Activities | Pressurization, flow establishment, and run tests |
This ensures comprehensive traceability and compliance with safety and quality standards during pipeline commissioning.
flowchart TD
A[Pre-commissioning Checks] --> B[Dewatering & Swabbing]
B --> C[Low Pressure Leak Check]
C --> D[Magnetic Cleaning & EGP]
D --> E[Inertisation]
E --> F[Gas-in & Commissioning Activities]
F --> G[High Pressure Leak Check]
G --> H[Flow Establishment & 72h Run]
This flowchart illustrates the sequential documentation process for commissioning.
Frequently Asked
Pre-commissioning Checks as per IS 15663 Part 3 (Clause 5.2.1):
Before pipeline commissioning, ensure the pipeline system (up to first isolation valve) is mechanically complete by performing:
Additional Notes:
| Check Category | Key Activities |
|---|---|
| Pipe Cover | PCM check every 500 m |
| System Verification | Cross-check with design docs |
| Field Instruments | Physical and functional check of valves, meters |
| Pipeline Survey | Verify supports, CP, markers, fencing |
| Communication | Ensure uninterrupted communication |
| Electrical System | Power supply, earth resistance, classification |
| Instrument Controls | Functional interlocks and controls |
| Utilities | Check power, UPS, water, air systems |
| Alarm Systems | Test alarm triggering and response |
| Safety | Emergency identification and mitigation readiness |
Loading diagram...
Pipeline Cleaning and Drying as per IS 15663 Part 3
Magnetic Cleaning (Clause 6.2.1):
Swabbing Operation (Clause 5.2.2.1):
Drying Operation (Clauses 6.2.3.1 & 2.0):
Loading diagram...
This sequence ensures corrosion prevention and pipeline integrity before commissioning.
Acceptance Criteria for Inertisation Using Nitrogen Gas (IS 15663 Part 3, Clause 6.2.5.2):
| Parameter | Requirement |
|---|---|
| Residual Oxygen Content | < 1% (vol/vol) |
| Nitrogen Slug Length | ≥ 10% of pipeline length |
| Nitrogen Purity | Sufficient to meet oxygen criterion |
| Nitrogen State | Compressed/vaporized/gaseous at ambient temperature |
| Drying Dew Point Before Inertisation | ≤ -10°C |
Loading diagram...
This ensures safe commissioning by removing oxygen and moisture effectively.
IS 15663 Part 3: Leak Testing of Above-Ground Piping
Scope: Leak test applies to above-ground piping sections, especially at flange points, equipment connections, and instrument impulse tubing.
Test Medium: Use dry, oil-free compressed air to pressurize the system.
Leak Detection: Apply soap solution or use a suitable digital pressure gauge to identify leaks visually or by pressure drop.
Test Pressure: Conduct the test at 6.0 kg/cm² (approx. 0.6 MPa). The system passes if no leaks are detected at this pressure.
Completion: The leak check is complete only when the system is verified leak-free at the specified pressure.
Loading diagram...
Summary: Pressurize above-ground piping to 6.0 kg/cm² with dry air, check all joints with soap solution or digital gauges, and ensure no leaks before commissioning.
To demonstrate compliance with commissioning procedures as per IS 15663 Part 3, the documentation must include:
Acceptance criteria: Pipeline must be leak-free, charged with natural gas, and stable for 72 hours, including all branches and auxiliary facilities.
This documentation ensures traceability and compliance with safety and operational standards during commissioning.