IS 13826 Part 4: 1993 specifies the method for conducting the pressure head test on bitumen-based felts used for waterproofing and damp-proofing. This test evaluates the felt's resistance to water leakage under a constant water pressure head, ensuring its effectiveness in preventing water penetration. It is essential for manufacturers, quality control engineers, and construction professionals involved with bituminous waterproofing materials to verify product performance and compliance with Indian standards.
Overview
IS 13826 Part 4: 1993 specifies the method for conducting the pressure head test on bitumen-based felts used for waterproofing and damp-proofing. This test evaluates the felt's resistance to water leakage under a constant water pressure head, ensuring its effectiveness in preventing water penetration. It is essential for manufacturers, quality control engineers, and construction professionals involved with bituminous waterproofing materials to verify product performance and compliance with Indian standards.
Audience
Contents
Structure
Scope Summary:
| Conditioning Type | Temperature | Duration | Test Setup | Acceptance Criteria |
|---|---|---|---|---|
| Hot Conditioning | 65 ± 2°C | 3 hours | 300 mm water head pressure | No leakage observed for 1 hour |
| Cold Conditioning | ≤ 5°C | 3 hours | 300 mm water head pressure | No leakage observed for 1 hour |
flowchart LR
A[Sample Preparation] --> B{Conditioning}
B --> C[Hot: 65 ± 2°C, 3 hr]
B --> D[Cold: ≤ 5°C, 3 hr]
C & D --> E[Apply 300 mm Water Head]
E --> F[Observe Leakage for 1 hr]
F --> G{Leakage?}
G -- No --> H[Pass]
G -- Yes --> I[Fail]
This concise summary covers the scope, conditioning, testing, and rounding rules as per IS 13826 Part 4. For detailed test methods and definitions, refer to IS 4911:1986.
Rounding Off (Clause None):
Final test/analysis values must be rounded per IS 2:1960 rules, retaining the same significant figures as specified.
Conditioning of Test Pieces (Clause 5.2):
| Conditioning Type | Temperature | Duration | Test Conditions |
|---|---|---|---|
| a) Hot Conditioning | 65 ± 2°C | 3 hours | Subjected to 300 mm water pressure head, checked for leakage for 1 hour |
| b) Cold Conditioning | ≤ 5°C | 3 hours | Tested immediately after conditioning under same pressure |
Reporting Requirements:
Definitions:
Refer to IS 4911:1986 for terms related to bituminous waterproofing and damp-proofing.
| Parameter | Value/Standard |
|---|---|
| Test Water Pressure | 300 mm water column |
| Hot Conditioning Temp | 65 ± 2°C |
| Cold Conditioning Temp | ≤ 5°C |
| Conditioning Duration | 3 hours |
| Leakage Check Duration | 1 hour |
flowchart TD
A[Test Pieces] --> B{Conditioning}
B -->|Hot| C[65 ± 2°C for 3 h]
B -->|Cold| D[≤ 5°C for 3 h]
C --> E[Test under 300 mm water pressure]
D --> E
E --> F[Leakage check for 1 hour]
F --> G[Report: Date, Conditioning type, Observation]
For detailed test procedures and quality control, always consult the full standard and related IS codes.
Definitions Reference: Clause 3.0 states that all definitions used in IS 13826 Part 4 refer to IS 4911:1986 — Glossary of terms relating to bituminous waterproofing and damp-proofing of buildings.
Rounding Off: For test results or calculations, values must be rounded as per IS 2:1960 rules, maintaining the same number of significant figures as specified.
| Aspect | Reference Standard | Key Points |
|---|---|---|
| Definitions | IS 4911:1986 | Standard glossary for waterproofing terms. |
| Rounding off values | IS 2:1960 | Follow rules for numerical rounding. |
| Conditioning (Test) | Clause 5.2 of IS 13826 Part 4 | Conditioning at 65±2°C for 3h or ≤5°C for 3h before testing. |
flowchart LR
A[Test Pieces] --> B[Condition at 65±2°C for 3h]
A --> C[Condition at ≤5°C for 3h]
B --> D[Apply 300 mm water pressure]
C --> D
D --> E[Observe leakage for 1 hour]
For detailed definitions, always refer to IS 4911:1986.
IS 13826 Part 4: Apparatus for Pressure Head Test
Hydrostatic pressure head ( P ) (in Pascal) from water column height ( h ) (in meters):
[ P = \rho \times g \times h ]
Where:
[ P = 1000 \times 9.81 \times 0.3 = 2943 , \text{Pa} \approx 2.94 , \text{kPa} ]
flowchart TB
A[Water Reservoir] --> B[300 mm Water Column]
B --> C[Apparatus Holding Circular Test Piece (200 mm dia)]
C --> D[Outlet / Drain]
style C fill:#add8e6,stroke:#000,stroke-width:2px
This setup ensures a constant hydrostatic pressure head of 300 mm on the test piece for leakage evaluation.
Clause 5.1: Preparation of Test Pieces
Clause 5.2: Conditioning of Test Pieces
| Test Pieces | Conditioning Temperature | Duration | Test Condition |
|---|---|---|---|
| 3 pieces | 65 ± 2°C | 3 hours | Tested after conditioning |
| 3 pieces | ≤ 5°C (or as required) | 3 hours | Tested immediately after conditioning |
Reporting Must Include:
| Parameter | Value |
|---|---|
| Test piece diameter | ≥ 200 mm |
| Number of test pieces | 6 (3 hot, 3 cold) |
| Hot conditioning temp. | 65 ± 2°C |
| Cold conditioning temp. | ≤ 5°C (or as required) |
| Conditioning duration | 3 hours |
| Pressure head during test | 300 mm |
| Leakage observation time | 1 hour |
flowchart LR
A[Cut 6 test pieces (≥200 mm)] --> B{Conditioning}
B --> C[3 pieces at 65 ± 2°C for 3h]
B --> D[3 pieces at ≤ 5°C for 3h]
C & D --> E[Place under 300 mm pressure head]
E --> F[Observe leakage for 1 hour]
F --> G[Report date, conditioning type, observations]
This ensures consistent preparation and reliable waterproofing test results per IS 13826 Part 4.
IS 13826 Part 4: Pressure Head Test - Key Points
| Parameter | Value |
|---|---|
| Test Piece Diameter | 200 mm |
| Water Pressure Head | 300 mm |
| Rounding Standard | IS 2:1960 |
flowchart LR
A[Prepare 200 mm Felt Sample] --> B[Mount Sample in Apparatus]
B --> C[Apply 300 mm Water Pressure Head]
C --> D[Observe for Leakage]
D --> E[Record Result]
E --> F[Round Off per IS 2:1960]
This test ensures compliance with water resistance requirements for bitumen felts.
Rounding Off Results (IS 2:1960)
Conditioning of Test Pieces (Clause 5.2)
| Conditioning Type | Temperature | Duration | Test Procedure |
|---|---|---|---|
| a) Hot Conditioning | 65 ± 2°C | 3 hours | Test immediately after conditioning |
| b) Cold Conditioning | ≤ 5°C | 3 hours | Test immediately after conditioning |
Reporting Requirements
flowchart LR
A[Test Piece (Ø 200 mm)] --> B[Constant Water Pressure Head (300 mm)]
B --> C[Leakage Check for 1 hour]
C --> D{Leakage?}
D -->|Yes| E[Record Leakage Observation]
D -->|No| F[Pass Test]
This ensures uniformity in test conditions and clarity in reporting for waterproofing felts.
IS 13826 Part 4: Precision & Interpretation of Results
Rounding Off (IS 2:1960): Final test or analysis results must be rounded off to the same number of significant figures as specified in the standard.
Test Setup (Clause 4.1):
Conditioning (Clause 5.2):
Reporting Requirements:
| Conditioning Temperature | Duration | Number of Test Pieces | Test Parameters |
|---|---|---|---|
| 65 ± 2°C | 3 hours | 3 | 300 mm water head, 1 hour |
| ≤ 5°C | 3 hours | 3 | 300 mm water head, 1 hour |
flowchart TB
A[Circular Test Piece (Ø 200 mm)] --> B[Clamping Plate]
B --> C[Water Column (300 mm Head)]
C --> D[Leakage Observation for 1 Hour]
Note: Use IS 2:1960 for rounding rules to ensure consistent interpretation of numerical results.
IS 13826 Part 4 - Committee Composition Summary
The technical committee for IS 13826 Part 4 is the Water-Proofing and Damp-Proofing Sectional Committee, CED 41. Its composition is detailed in Annex A and includes:
This committee ensures a broad representation from industry, government, research, and consultancy for standard formulation.
graph TD
A[Chairman: Prof. M. S. Shetty] --> B[Members]
B --> C[Industry Representatives]
B --> D[Government Agencies]
B --> E[Research Institutes]
B --> F[Consultants & Others]
C --> C1[Osnar Chemical Pvt Ltd]
C --> C2[Fosroc India Ltd]
D --> D1[CPWD]
D --> D2[Army HQ]
E --> E1[CBRI Roorkee]
E --> E2[NBO Delhi]
F --> F1[Metro Railway]
F --> F2[Polyseal India]
This composition ensures comprehensive expertise for waterproofing and damp-proofing standards under IS 13826 Part 4.
Frequently Asked
IS 13826 Part 4 — Pressure Head Test Specimen Size & Preparation
This ensures uniform testing for leakage under a controlled pressure head.
Loading diagram...
Summary: Use ≥200 mm dia. circular pieces, 6 per sample, clamp with overlap, test under 300 mm water head.
According to IS 13826 Part 4 (Clause 5.2), the conditioning of test pieces before testing is as follows:
This procedure ensures the waterproofing material's performance is evaluated under both elevated and low temperature conditions.
Loading diagram...
According to IS 13826 Part 4, the specified water pressure head applied during the test is:
This is applied on a circular test piece of diameter 200 mm to determine leakage under constant water pressure.
| Parameter | Value |
|---|---|
| Test piece diameter | 200 mm |
| Constant water pressure head | 300 mm water column |
This setup ensures a standardized method to assess waterproofing performance of bitumen felts.
Loading diagram...
This arrangement helps detect any water leakage through the felt under the specified pressure head.
According to IS 13826 Part 4, leakage detection and recording during the pressure head test are done as follows:
This method ensures standardized detection of leakage under controlled pressure and temperature conditions.
Loading diagram...
Summary: Leakage is detected visually during a 1-hour constant 300 mm water head test after conditioning, and observations are systematically recorded.
IS 13826 Part 4 specifically covers the Pressure Head Test for bitumen felts, which is one of several tests in the IS 13826 series designed to evaluate the physical properties of bitumen-based waterproofing felts.
Loading diagram...
This integrated approach ensures bitumen felts meet all essential physical requirements for effective waterproofing.
Ask AI about any clause, requirement, or provision in IS 13826 Part 4. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required