IS 1200 Part 27:1992 specifies the standardized method for measuring earthwork executed by mechanical appliances in building and civil engineering projects. It addresses measurement techniques for various soil types, rock, and materials below ground level, including procedures for excavation, filling, and related activities using machinery such as dozers, scrapers, and loaders. This standard is essential for engineers, contractors, and quantity surveyors to ensure accurate, consistent quantification of earthwork for project planning, cost estimation, and payment.
Overview
IS 1200 Part 27:1992 specifies the standardized method for measuring earthwork executed by mechanical appliances in building and civil engineering projects. It addresses measurement techniques for various soil types, rock, and materials below ground level, including procedures for excavation, filling, and related activities using machinery such as dozers, scrapers, and loaders. This standard is essential for engineers, contractors, and quantity surveyors to ensure accurate, consistent quantification of earthwork for project planning, cost estimation, and payment.
Audience
Contents
Structure
IS 1200 Part 27: Scope & Measurement Key Points
Measurement Units:
Embankments & Fillings (Clause 4.4.1):
Tree Removal (Clause 4.9.1):
| Quantity | Unit | Precision |
|---|---|---|
| Length | meters (m) | 0.01 m (≤ 25 m) / 0.1 m (> 25 m) |
| Area | square meters (m²) | 0.01 m² |
| Volume | cubic meters (m³) | 0.01 m³ |
flowchart TD
A[Start Measurement] --> B{Dimension > 25 m?}
B -- Yes --> C[Measure to 0.1 m]
B -- No --> D[Measure to 0.01 m]
C --> E[Calculate Area & Volume]
D --> E
E --> F[Record Area (0.01 m²) & Volume (0.01 m³)]
F --> G[For Embankments: Measure layers & consolidation]
G --> H[End]
This ensures standardized, accurate quantification of earthworks and related civil engineering tasks as per IS 1200 Part 27.
| Parameter | Specification/Rule |
|---|---|
| Tree Girth Measurement | > 30 cm at 1 m height; count number for removal |
| Tree Removal Coverage | Includes removal + deposit within 50 m |
| Rounding Off Values | Follow IS 2:1960 rules for numerical rounding |
| Earthwork Measurement | Based on mechanical excavation, carriage, and filling |
flowchart TD
A[Start: Site Preparation] --> B[Identify Trees > 30 cm girth]
B --> C[Pre-measure & Count Trees]
C --> D[Mechanical Earthwork]
D --> E[Removal & Deposit within 50 m]
E --> F[Measurement & Rounding off (IS 2:1960)]
F --> G[Final Quantity for Payment]
For detailed tables and machine productivity rates, refer to the full IS 1200 Part 27 document.
IS 1200 Part 27: Classification of Soils (Clause 3)
| Soil Type | Description | Measurement Unit |
|---|---|---|
| Ordinary soil & mud concrete | Below ground level | Cubic metres (m³) |
| Shingle & river bed boulders | Detachable stones in river beds | Cubic metres (m³) |
| Soling, hard core, macadam | Road/path base layers | Cubic metres (m³) |
| Lime concrete & stone masonry | Below ground level | Cubic metres (m³) |
| Soft conglomerate & laterite | Detachable by picks/shovel | Cubic metres (m³) |
flowchart TD
A[Earthwork] --> B[Classification of Soil]
B --> C[Soil & Mud Concrete]
B --> D[Shingle & Boulders]
B --> E[Soling & Hard Core]
B --> F[Lime Concrete & Masonry]
B --> G[Soft Conglomerate & Laterite]
A --> H[Measurement]
H --> I[Cubic Metres]
H --> J[Layer Thickness]
H --> K[Slope Formation]
H --> L[Consolidation Method]
Use this classification to measure earthwork accurately and apply appropriate specifications for excavation and filling as per IS 1200 Part 27.
IS 1200 Part 27: Method of Measurement for Earth Work by Mechanical Appliances
Dimension Measurement (Clause 2.3):
Measurement Units:
[ \text{Volume} = \text{Area of cross-section} \times \text{Length between sections} ]
Where cross-sectional area is calculated by averaging successive cross-sections.
| Quantity Type | Precision |
|---|---|
| Linear dimension (>25 m) | 0.1 m |
| Linear dimension (≤25 m) | 0.01 m |
| Area | 0.01 m² |
| Volume | 0.01 m³ |
flowchart TD
A[Start Measurement] --> B{Dimension > 25m?}
B -- Yes --> C[Measure to 0.1 m]
B -- No --> D[Measure to 0.01 m]
C & D --> E[Calculate Area (0.01 m²)]
E --> F[Calculate Volume (0.01 m³)]
F --> G[Apply Rounding per IS 2:1960]
G --> H[Record Net Quantity]
This ensures consistent and accurate measurement of earthwork done by mechanical means as per IS 1200 Part 27.
IS 1200 Part 27: Measurement Units Summary
Length Measurement:
Area Measurement:
Volume (Cubical Content) Measurement:
Rounding Rules:
| Quantity | Unit | Precision |
|---|---|---|
| Length ≤ 25 m | meters (m) | 0.01 m |
| Length > 25 m | meters (m) | 0.1 m |
| Area | m² | 0.01 m² |
| Volume | m³ | 0.01 m³ |
flowchart LR
A[Start Measurement] --> B{Dimension ≤ 25 m?}
B -- Yes --> C[Measure to nearest 0.01 m]
B -- No --> D[Measure to nearest 0.1 m]
C & D --> E[Calculate Area to 0.01 m²]
E --> F[Calculate Volume to 0.01 m³]
F --> G[Apply IS 2:1960 rounding rules]
G --> H[Record final measurement]
This ensures precise, consistent, and standardized measurement for earthworks and other civil engineering works under IS 1200 Part 27.
IS 1200 Part 27: Measurement Procedures - Key Points
| Quantity | Formula / Method | Unit |
|---|---|---|
| Length (L) | Measured directly with tape/total station | m |
| Area (A) | Length × Breadth | m² |
| Volume (V) | Area × Depth or cross-sectional area × length | m³ |
flowchart TD
A[Start Measurement] --> B{Dimension > 25 m?}
B -- Yes --> C[Measure to nearest 0.1 m]
B -- No --> D[Measure to nearest 0.01 m]
C --> E[Calculate Area & Volume]
D --> E
E --> F[Round off as per IS 2:1960]
F --> G[Record Net Measurement]
This ensures standardization and accuracy in civil engineering measurement, especially for earthworks done mechanically.
IS 1200 Part 27: Measurement from Borrow Pits and Fillings
Measurement Method (Clause 4.2 & 4.3):
Excavation Measurement (Clause 4.2):
Filling & Embankment (Clause 4.4.1):
[ \text{Volume} = \text{Area} \times \text{Average height difference} ]
Where height difference = level after compaction - original ground level.
| Parameter | Accuracy/Value | Remarks |
|---|---|---|
| Level measurement | ±5 mm | Use staff and level |
| Volume unit | Cubic metres (m³) | Rounded to nearest decimal |
| Layer thickness for fill | 0.5 m | Measure in successive layers |
| Rock excavation reduction | 50% | To account for voids |
flowchart TD
A[Original Ground Level] --> B[Site Clearance]
B --> C[Fill Placement in Layers (0.5 m)]
C --> D[Compaction at Desired Density]
D --> E[Level Measurement]
E --> F[Volume Calculation]
Note: Always specify fill density and consolidation method before measurement.
IS 1200 Part 27: Measurement of Embankments and Backfilling
[ \text{Volume of Fill} = \sum \left( \text{Area of cross-section} \times \text{Layer thickness} \right) ]
Where cross-sectional area is calculated from levels taken at intervals.
| Parameter | Specification |
|---|---|
| Unit | Cubic metres (m³) |
| Leveling Accuracy | ±5 mm |
| Layer Thickness | Specified per project |
| Stage Interval | 1.5 m |
| Rock Excavation Reduction Factor | 50% (for voids) |
flowchart TD
A[Start Measurement] --> B[Record Original Ground Level]
B --> C[Clear Site]
C --> D[Deposit Fill in Layers]
D --> E[Record Fill Level after Compaction]
E --> F[Calculate Volume = Fill Level - Original Level]
F --> G[Adjust for Voids if Rock Present]
G --> H[Final Volume in m³]
This ensures accurate volume estimation for embankments and backfilling per IS 1200 Part 27.
Lead Measurement (Clause 4.5.1):
Measurement Precision (Clause 2.3):
25 m → nearest 0.1 m
Measurement Method (Clause 4.2):
| Lead Distance Range | Unit of Measurement | Rounding Rule |
|---|---|---|
| ≤ 500 m | Actual distance | Exact |
| > 500 m and ≤ 5 km | 500 m units | ≥ 0.5 unit = 1, < 0.5 ignore |
| > 5 km | 1 km units | ≥ 0.5 unit = 1, < 0.5 ignore |
[ \text{Payable Volume} = \text{Total Excavation} - 0.5 \times \text{Ordinary Rock Volume} ]
flowchart TD
A[Measure Total Excavation] --> B[Measure Ordinary Rock Volume]
B --> C[Reduce Ordinary Rock Volume by 50%]
C --> D[Calculate Soil Excavation = Total - Reduced Rock]
D --> E[Payable Excavation Quantities]
This ensures accurate
IS 1200 Part 27: Measurement of Spoil Heaps - Key Points
Spoil Heap Measurement (Clause 4.6):
Spoil heaps consolidated over time must be measured and recorded separately.
Measurement Method (Clauses 4.2, 4.3, 4.4.1):
[ V = \sum \left( \frac{A_1 + A_2}{2} \times h \right) ]
| Parameter | Specification |
|---|---|
| Level accuracy | ±5 mm |
| Volume unit | Cubic metres (m³) |
| Stage interval | 1 to 5 m vertical steps |
| Rock volume reduction | 50% allowance for voids |
| Layer thickness (fill) | To be specified |
| Consolidation status | Must be stated separately |
flowchart TD
A[Start Measurement] --> B[Record Original Ground Level]
B --> C[Excavation or Fill in Layers]
C --> D[Measure Levels at 1-5 m Intervals]
D --> E[Calculate Cross-sectional Areas]
E --> F[Compute Volume by Trapezoidal Rule]
F --> G{Is Spoil Heap Consolidated?}
G -- Yes --> H[Measure & Record Separately]
G -- No --> I[Include in Total Volume]
H & I --> J[Finalize Measurement]
This
IS 1200 Part 27: Measurement of Hard Rock Excavation
Definition (Clause 3.1.5):
Hard rock requires blasting or chiselling before excavation. After blasting, it is treated as ordinary rock.
Measurement Method (Clause 4.2):
Non-measurable Items (Clause 2.7):
Includes setting out, site clearance, unauthorized battering, slips removal, water bailing, and pipe/cable handling.
| Parameter | Specification |
|---|---|
| Level reading accuracy | ± 5 mm |
| Depth/height calculation | ± 5 mm |
| Cubic content rounding | Nearest 0.1 m³ |
| Ordinary rock volume payable | Measured volume × 50% (voids allowance) |
| Hard rock after blasting | Measured as ordinary rock |
flowchart TD
A[Start Excavation] --> B{Is rock hard?}
B -- Yes --> C[Blast/Chisel rock]
C --> D[Measure excavation with staff & level]
B -- No --> D
D --> E[Calculate volume to nearest 0.1 m³]
E --> F{Mixed ordinary rock & soil?}
F -- Yes --> G[Measure ordinary rock separately]
G --> H[Reduce ordinary rock volume by 50%]
H --> I[Calculate difference as soil volume]
F -- No --> I
I --> J[Finalize quantities for payment]
This ensures accurate, standardized measurement for excavation involving hard rock, aligning with IS 1200 Part 27.
IS 1200 Part 27: Measurement of Planking and Strutting
| Item | Unit | Remarks |
|---|---|---|
| Planking & Strutting | m² of face supported | Includes wastage, fixing, removal |
| Permanent Planking/Strutting | m² | Measured separately |
flowchart TD
A[Excavated Earth Face] --> B[Planking & Strutting]
B --> C[Measurement of Face Supported (m²)]
C --> D{Temporary or Permanent?}
D -->|Temporary| E[Measure with fixing & removal]
D -->|Permanent| F[Measure separately]
This ensures consistent and accurate billing and documentation of earth support works per IS 1200 Part 27.
Key points from Clause 4.9.1:
| Parameter | Specification |
|---|---|
| Girth for pre-measurement | > 30 cm at 1 m above ground level |
| Measurement unit | Number of trees |
| Included in measurement | Removal + depositing within 50 m |
| Trees ≤ 30 cm girth | Not separately measured |
flowchart TD
A[Identify Trees on Site] --> B{Girth > 30 cm?}
B -- Yes --> C[Pre-measure number of trees]
B -- No --> D[Include in general site clearance]
C --> E[Remove & Deposit within 50 m]
D --> E
E --> F[Measurement recorded as number of trees removed]
For detailed execution, refer to IS 1200 Part 27 Clause 4.9 and related site clearance clauses.
IS 1200 Part 27: Booking of Dimensions - Key Points
Order of Dimensions (Clause 2.2):
Dimensions must be booked consistently in the sequence:
Length → Breadth/Width → Height/Depth/Thickness
Measurement Precision (Clause 2.3):
Item Description (Clause 2.6):
Must include loading and unloading details.
Embankments & Filling (Clause 4.4.1):
| Parameter | Unit | Precision | Notes |
|---|---|---|---|
| Length ≤ 25 m | meters (m) | 0.01 m | - |
| Length > 25 m | meters (m) | 0.1 m | - |
| Area | square meters (m²) | 0.01 m² | Calculated from booked lengths |
| Volume | cubic meters (m³) | 0.01 m³ | Includes slope & layering |
flowchart LR
A[Booking of Dimensions] --> B[Length]
B --> C[Breadth/Width]
C --> D[Height/Depth/Thickness]
D --> E[Measurement Precision]
E --> F[Linear: 0.01 or 0.1 m]
E --> G[Area: 0.01 m²]
E --> H[Volume: 0.01 m³]
A --> I[Description]
I --> J[Loading & Unloading]
A --> K[Embankment Measurement]
K --> L[Include slope formation]
K --> M[Layer thickness & consolidation]
K --> N[
IS 1200 Part 27: Clubbing of Items - Key Points
These are considered included in item rates:
| Aspect | Specification |
|---|---|
| Clubbing allowed | Yes, with detailed item description |
| Loading/unloading included | Yes |
| Not measured separately | Setting out, site clearance, water bailing, etc. |
| Trees removal | >30 cm girth, counted by number |
flowchart TD
A[Items for Measurement] --> B{Can items be clubbed?}
B -- Yes --> C[Check detailed description match]
B -- No --> D[Measure separately]
C --> E[Include loading/unloading]
E --> F[Exclude works listed in Clause 2.7]
F --> G[Final item measurement]
Note: Always refer to the detailed item description in IS 1200 Part 27 for precise measurement and clubbing rules.
Frequently Asked
IS 1200 Part 27 covers the method of measurement of earthwork done by mechanical appliances in building and civil engineering works.
| Material Type | Excavation Method | Notes |
|---|---|---|
| Natural soil | Mechanical excavation | Includes clay, sand, gravel |
| Rock (limestone, etc.) | Mechanical + blasting | May require splitting/blasting |
| Concrete (below ground) | Mechanical excavation | Plain, reinforced, prestressed |
This standard ensures uniform measurement practices for earthwork by mechanical means, improving accuracy and consistency in project execution.
Lead and Lift Measurement in Earthwork (IS 1200 Part 27)
Lead (Clause 4.5.1):
Lift (Clause 4.7):
Measurement Accuracy (Clause 4.2 & 4.3):
Summary:
Lead is carefully measured and rounded as per distance; lift is included in overall volume and not measured separately for mechanical earthwork.
Loading diagram...
Precision and Units for Earthwork Measurement as per IS 1200 Part 27:
Units:
Dimension Measurement Precision:
Level and Depth Precision:
Area and Volume Precision:
Special Notes:
| Parameter | Unit | Precision |
|---|---|---|
| Dimension (≤ 25 m) | meters (m) | 0.01 m |
| Dimension (> 25 m) | meters (m) | 0.1 m |
| Level/Depth | meters (m) | 0.005 m (5 mm) |
| Area | m² | 0.01 m² |
| Volume (Earthwork) | m³ | 0.01 m³ |
This ensures accurate and consistent measurement for earthwork by mechanical means.
IS 1200 Part 27 addresses earthwork measurement under special conditions as follows:
Clause 2.4 mandates separate measurement for earthwork:
Clause 4.2 specifies measurement methods:
Clause 4.3 covers cases where direct measurement is inconvenient:
Summary: Special condition earthworks are measured separately with high precision, using levels and staff, and adjusted for voids or fill compaction where direct measurement is difficult.
Loading diagram...
This ensures accurate and fair measurement under challenging earthwork conditions.
According to IS 1200 Part 27, the guidelines for measuring planking, strutting, and tree removal during earthwork are:
| Item | Measurement Unit | Notes |
|---|---|---|
| Planking & Strutting | Square metres of face area | Includes fixing, wastage, removal |
| Permanent Planking | Square metres | Measured separately |
| Trees (>30 cm girth) | Number | Removal + deposit within 50 m |
This ensures accurate quantification for payment and resource planning in earthworks involving mechanical appliances.
Ask AI about any clause, requirement, or provision in IS 1200 Part 27. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required