IRC 47 (1972) provides tentative specifications for the construction of built-up spray grout, a two-layer bituminous base or binder course for road pavements. It is designed as an alternative to conventional water bound macadam, especially where water is scarce or traffic cannot be interrupted. The standard covers materials, aggregate grading, binder types, construction procedures, and quality control measures to ensure durable and uniform pavement layers suitable for base courses but not as wearing surfaces.
Overview
IRC 47 (1972) provides tentative specifications for the construction of built-up spray grout, a two-layer bituminous base or binder course for road pavements. It is designed as an alternative to conventional water bound macadam, especially where water is scarce or traffic cannot be interrupted. The standard covers materials, aggregate grading, binder types, construction procedures, and quality control measures to ensure durable and uniform pavement layers suitable for base courses but not as wearing surfaces.
Audience
Contents
Structure
IRC 47 introduces Built-up Spray Grout (BSG) as an alternative to conventional water bound macadam, suitable for base or binder courses but not as wearing courses. BSG consists of two compacted layers of crushed coarse aggregates with bituminous binder applied after each layer, finished with key aggregates, total thickness not exceeding 75 mm (Clause 1 Introduction). The binder can be straight-run bitumen (IS:73), road tar (IS:215), or approved cutback, with grades selected per climate (Clause 4.1). Aggregates must be clean, strong, durable, and cubical, meeting physical requirements in Table 1 below (Clause 4.2.2). Grading of coarse and key aggregates is specified in Table 2 (Clause 4.2.3). Construction requires dry, clean base preparation and binder application rates per Table 3 (Clause 5.3).
Sources: Clause 1 Introduction, Clause 4.1, Clause 4.2.2, Clause 4.2.3, Clause 5.3
The scope of IRC 47 covers the tentative specifications for built-up spray grout used in road construction. Key points include:
The relevant table for binder quantity per 10 m² is:
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam surface | 7.5 kg - 10 kg |
| b. On an existing black top surface | 6 kg - 8 kg |
This ensures proper adhesion and surface preparation for spray grout application.
Sources: Clause 5.1, Clause 5.3, Table 3 in Clause 2.36
Key materials specifications from IRC 47 for built-up spray grout are as follows:
Binder Types (Clause 4.1.1):
Aggregates (Clause 4.2):
| Property | Base Course Max. | Binder Course Max. | Test Method |
|---|---|---|---|
| Abrasion value (Los Angeles) | 50% | 40% | IS:2386 (Part IV) |
| Aggregate impact value | 40% | 30% | IS:2386 (Part IV) |
| Flakiness index | 25% | 25% | IS:2386 (Part I) |
| Stripping value | 25% | 25% | IS:6241 |
| Water absorption | 1% | 1% | IS:2386 (Part III) |
| Soundness (slag only) | 12% loss (5 cycles) | 12% loss | IS:2386 (Part V) |
| Bulk density (slag only) | Min. 1120 kg/m³ | Min. 1120 kg/m³ | IS:2386 (Part III) |
| Sieve Size (mm) | Coarse Aggregate % Passing | Key Aggregate % Passing |
|---|---|---|
| 50 | 100 | - |
| 25 | 35-70 | - |
| 20 | - | 100 |
| 12.5 | 0-15 | 35-70 |
| 4.75 | - | 0-15 |
| 2.36 | 0-5 | 0-5 |
These materials ensure durability and bonding in built-up spray grout base or binder courses but are not for wearing courses. The binder grade depends on climate (Clause 4.1.2).
Sources: Clause 4.1.1, Clause 4.1.2, Clause 4.2.1, Clause 4.2.2, Clause 4.2.3, Table 1, Table 2
Key specifications for aggregates in built-up spray grout per IRC 47 Clause 4.2 are as follows:
Aggregates must be crushed stone, slag, gravel, or similar, clean, strong, durable, cubical, and free from deleterious materials (Clause 4.2.1).
Physical requirements for coarse and key aggregates are given in Table 1:
| Property | Base Course Max. | Binder Course Max. | Test Method |
|---|---|---|---|
| Abrasion value (Los Angeles) | 50% | 40% | IS: 2386 (Part IV) |
| Aggregate impact value | 40% | 30% | IS: 2386 (Part IV) |
| Flakiness index | 25% | 25% | IS: 2386 (Part I) |
| Stripping value | 25% | 25% | IS: 6241 |
| Water absorption (except slag) | 1% | 1% | IS: 2386 (Part III) |
| Soundness (slag only, sodium sulphate 5 cycles) | 12% | 12% | IS: 2386 (Part V) |
| Bulk density (slag only) | Min. 1120 kg/m³ | Min. 1120 kg/m³ | IS: 2386 (Part III) |
| Sieve Size (mm) | Coarse Aggregate (%) | Key Aggregate (%) |
|---|---|---|
| 50 | 100 | - |
| 25 | 35-70 | - |
| 20 | - | 100 |
| 12.5 | 0-15 | 35-70 |
| 4.75 | - | 0-15 |
| 2.36 | 0-5 | 0-5 |
These ensure durability and proper bonding in spray grout construction. For detailed construction steps and binder application rates, see Clauses 5.5 to 5.11.
Sources: Clause 4.2.1, Clause 4.2.2, Table 1, Clause 4.2.3, Table 2
The binder for built-up spray grout in IRC 47 shall be one of the following as per Clause 4.1.1:
The binder grades depend on climatic conditions as per Clause 4.1.2.
For application, the binder is heated to the appropriate temperature and applied uniformly to the base at rates specified in Table 3 (Clause 5.3):
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam | 7.5 kg - 10 kg |
| b. On an existing black top | 6 kg - 8 kg |
This binder is applied after each compacted coarse aggregate layer to bond the layers, finishing with key aggregates on top, with total thickness not exceeding 75 mm (Clause 5.10).
Sources: Clause 4.1.1, Clause 4.1.2, Clause 5.3, Clause 5.10
Key construction specifications for built-up spray grout per IRC 47 include:
Weather and Seasonal Limitations: Construction shall not proceed if atmospheric temperature in shade is below 16℃, or if pavement is damp, foggy, rainy, or dusty (Clause 5.1).
Preparation of Base: The base must be uniformly graded, dry, and thoroughly cleaned by sweeping and brushing. For stabilized soil or porous aggregates, apply a bituminous primer as per IRC:16-1965 and cure before construction (Clause 5.3).
Bituminous Binder Application: Binder heated to specified temperature and applied uniformly at rates given in the table below, preferably by sprayer, just before spreading coarse aggregates (Clause 5.3).
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam | 7.5 kg - 10 kg |
| b. On an existing black top | 6 kg - 8 kg |
Aggregate Requirements: Aggregates must be clean, strong, durable, and cubical. Physical properties and grading are specified in Tables 1 and 2 (Clause 4.2).
Construction Layers: Two-layer composite construction with compacted crushed coarse aggregates and bituminous binder after each layer, total thickness not exceeding 75 mm. Not recommended for wearing course (Clause 5.10).
These ensure proper bonding, durability, and performance of the built-up spray grout base or binder course.
Sources: Clause 5.1, Clause 5.3, Clause 5.10, Table 5. CONSTRUCTION | Clause 2.36, Table 1 and Table 2 | Clause 4.2
For preparation of the base in built-up spray grout construction as per IRC 47 Clause 5.3, the underlying course must be shaped and conditioned to a uniform grade and section. Any depressions or potholes should be properly filled and compacted well in advance. The surface must be dry and thoroughly cleaned by sweeping, brushing, and blowing to remove all dust and foreign matter. For old blacktop surfaces, ensure they are clean and dry. For stabilized soil or porous aggregates, apply a suitable bituminous primer as per IRC:16-1965 and allow curing before construction. The binder should be heated to the specified temperature and applied uniformly at rates given in the table below, preferably by sprayer, just before spreading coarse aggregates.
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam surface | 7.5 kg - 10 kg |
| b. On an existing black top surface | 6 kg - 8 kg |
This ensures proper bonding and a uniform base for subsequent layers. The surface preparation and binder application are critical for durability and performance of the built-up spray grout base course.
Sources: Clause 5.3
For spreading and compacting the first layer of coarse aggregates in built-up spray grout construction as per IRC 47:
Spreading (Clause 5.5.1): Coarse aggregates shall be spread and hand packed at a rate of 0.5 m³ per 10 m² to a uniform depth, maintaining alignment and profile using a camber template.
Rolling (Clause 5.5.2): Compaction is done with a 3-wheel power roller (8-10 tonnes) or equivalent vibratory roller, starting from edges towards center, ensuring surface variation does not exceed 12 mm from camber template or 3 m straight edge.
Rolling must stop before voids close to prevent bitumen penetration issues.
Binder Application (Clause 5.6): After rolling, apply binder heated to suitable temperature at 12.5 to 15.0 kg per 10 m² uniformly with mechanical sprayers. Aggregates must be surface dry before application.
Key Specifications Table for Binder Quantity on Base (Clause 2.36):
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam | 7.5 kg - 10 kg |
| b. On an existing black top | 6 kg - 8 kg |
These steps ensure uniform spreading, proper compaction, and adequate binder application for the first layer.
Sources: Clause 5.5.1, Clause 5.5.2, Clause 5.6, Clause 2.36
The first application of binder in built-up spray grout construction per IRC 47 involves applying heated binder uniformly over the compacted first layer of coarse aggregates. As per Clause 5.6 and 12.5, the binder quantity should be between 12.5 kg to 15.0 kg per 10 m² of road surface. The binder must be heated to the appropriate temperature for its type and grade and applied preferably with mechanical sprayers. Before application, the coarse aggregates must be surface dry to full depth. The binder types allowed include straight-run bitumen (IS: 73), road tar (IS: 215), or approved cutbacks, with grades selected based on climatic conditions (e.g., bitumen 80/100, 60/70, 30/40 or road tar R.T.4, R.T.5) as per Clause 4.1.1 and 4.1.2.
Additionally, the binder application rate for tack coat on base varies by base type (Clause 5.3):
| Type of base | Quantity per 10 m² |
|---|---|
| On water bound macadam surface | 7.5 kg - 10 kg |
| On existing black top surface | 6 kg - 8 kg |
This ensures proper bonding before spreading the next aggregate layer. The process is critical for achieving a durable, bonded base or binder course but not suitable as a wearing course.
Sources: Clause 5.6, Clause 12.5, Clause 4.1.1, Clause 4.1.2, Clause 5.3
For spreading and compacting the second layer of coarse aggregates in built-up spray grout construction as per IRC 47:
Immediately after applying the binder on the first layer (12.5 to 15.0 kg per 10 m²), coarse aggregates shall be spread at the rate of 0.5 m³ per 10 m² uniformly and compacted similarly to the first layer (Clause 5.7).
The spreading must be true to alignment and profile, using a camber template for uniformity (Clause 5.5.1).
Rolling should be done with a 8 to 10 tonne three-wheel power roller or equivalent vibratory roller, starting from edges towards the center, overlapping by one third width, and on superelevated portions from lower to upper edge (Clause 5.5.2).
Surface irregularities exceeding 12 mm must be corrected, and rolling should stop before voids close to prevent binder penetration issues (Clause 5.5.2).
After compacting the second layer, a second binder application of 12.5 to 15.0 kg per 10 m² is applied (Clause 5.8).
This two-layer composite construction yields a thickness not exceeding 75 mm and is finished with key aggregates (Clause 5.10).
Sources: Clause 5.5.1, Clause 5.5.2, Clause 5.6, Clause 5.7, Clause 5.8, Clause 5.10
The second application of binder in built-up spray grout construction is applied after compacting the second layer of coarse aggregates. As per Clause 5.8, the binder quantity shall be 12.5 kg to 15.0 kg per 10 m². This binder is heated to the appropriate temperature and applied uniformly, preferably with mechanical sprayers. Following this, key aggregates are spread and compacted to form a uniform closed surface (Clause 5.9). The binder types suitable include straight-run bitumen (grades 80/100, 60/70, 30/40), road tar (RT4, RT5), or approved cutbacks (Clause 4.1.1 and 4.1.2). The binder application rate on different bases is given in the table below (Clause 5.3):
| Type of base | Quantity per 10 m² of road surface |
|---|---|
| a. On a water bound macadam | 7.5 kg - 10 kg |
| b. On an existing black top | 6 kg - 8 kg |
The process ensures bonding between layers and a durable base or binder course, but this construction is not suitable as a wearing course (Clause 5.10).
Sources: Clause 5.8, Clause 5.9, Clause 4.1.1, Clause 4.1.2, Clause 5.3
The application of key aggregate in built-up spray grout as per IRC 47 involves placing a top layer of key aggregates over two compacted layers of coarse aggregates bonded with bituminous binder, with a total thickness not exceeding 75 mm (Clause 5.10). The key aggregates must conform to grading and physical requirements to ensure durability and bonding. The binder used can be straight-run bitumen (grades 80/100, 60/70, 30/40), road tar (R.T. 4 or R.T. 5), or approved cutback (Clause 4.1.1 and 4.1.2). Key aggregates grading and physical properties are specified in Tables 1 and 2 below. The binder application rate depends on the base type (Table 3). The construction involves spreading, compacting coarse aggregates, applying binder, and finishing with key aggregates as per Clause 5.5 and 5.6.
Sources: Clause 5.10, Clause 4.1.1, Clause 4.1.2, Clause 4.2.1, Clause 4.2.2, Clause 4.2.3, Clause 5.5, Clause 5.6
For Surface Finish and Quality Control in built-up spray grout as per IRC 47 Clause 5.10 and related sections, key specifications include:
Binder Types: Straight-run bitumen (IS:73), road tar (IS:215), or approved cutback; grades depend on climate (e.g., bitumen 80/100, 60/70, 30/40).
Aggregate Requirements: Clean, strong, durable, cubical fragments free from impurities.
Physical Properties of Aggregates:
| Property | Base Course Max. | Binder Course Max. | Test Method |
|---|---|---|---|
| Abrasion value (Los Angeles) | 50% | 40% | IS:2386 (Part IV) |
| Aggregate impact value | 40% | 30% | IS:2386 (Part IV) |
| Flakiness index | 25% | 25% | IS:2386 (Part I) |
| Stripping value | 25% | 25% | IS:6241 |
| Water absorption | 1% | 1% | IS:2386 (Part III) |
| Soundness (slag only) | 12% | 12% | IS:2386 (Part V) |
| Bulk density (slag only) | Min. 1120 kg/m³ | Min. 1120 kg/m³ | IS:2386 (Part III) |
| Sieve Size | Coarse Aggregate | Key Aggregate |
|---|---|---|
| 50 mm | 100 | - |
| 25 mm | 35-70 | - |
| 20 mm | - | 100 |
| 12.5 mm | 0-15 | 35-70 |
| 4.75 mm | - | 0-15 |
| 2.36 mm | 0-5 | 0-5 |
These ensure proper surface finish and quality control for spray grout base or binder courses.
Sources: Clause 5.10, Table 1, Table 2
As per IRC 47 Clause 5.11, the built-up spray grout surface must have the wearing course applied before opening to traffic because it is an open-graded construction. However, in special cases, limited traffic may be allowed with vehicle speeds restricted to 16 km/h. The construction involves two layers of coarse aggregates compacted with bituminous binder applied after each layer at 12.5 to 15.0 kg per 10 m² (Clauses 5.6, 5.8). Key aggregates are then spread at 0.13 m³ per 10 m² and rolled to embed them fully (Clause 5.9). Surface evenness tolerances are: longitudinal profile variation max 12 mm over 3 m straight edge, max 30 undulations >10 mm per 300 m; cross profile variation max 8 mm checked with camber template (Clause 5.10).
Sources: Clause 5.11, Clause 5.6, Clause 5.8, Clause 5.9, Clause 5.10
As per IRC 47 Clause 5.1, built-up spray grout construction shall NOT be done when the atmospheric temperature in shade is below 16°C, or when the pavement is damp, foggy, rainy, or during dust storms. This ensures proper curing and bonding. The base surface must be dry and thoroughly cleaned before construction (Clause 5.3). For bituminous binder application, the binder shall be heated to the specified temperature and applied uniformly at rates given in Table 3 (Clause 5.3). The binder quantity for the first and second layers is 12.5 to 15.0 kg per 10 m² (Clause 12.5 and 5.8). Key aggregates are applied at 0.13 m³ per 10 m² immediately after the second binder application (Clause 5.9). The surface finish tolerances are: longitudinal profile variation max 12 mm over 3 m straight edge, and cross profile variation max 8 mm with camber template (Clause 5.10). Opening to traffic is allowed only after wearing course application or with speed restriction of 16 km/h (Clause 5.11).
Sources: Clause 5.1, Clause 5.3, Clause 12.5, Clause 5.8, Clause 5.9, Clause 5.10, Clause 5.11
Frequently Asked
As per IRC 47 Clause 4.1.1 and 4.1.2, the recommended types of bituminous binders are:
The suggested grades of binders, depending on climatic conditions, are:
| Binder Type | Grades |
|---|---|
| Straight-run bitumen | 80/100, 60/70, 30/40 |
| Road tar | R.T. 4, R.T. 5 |
These binders are specified for use in built-up spray grout construction as base or binder courses but not as wearing courses.
Sources: Clause 4.1.1, Clause 4.1.2
The aggregates used in built-up spray grout must be clean, strong, durable, and fairly cubical, free from disintegrated pieces, salts, alkali, vegetable matter, dust, and coatings as per general requirements. The physical properties for coarse and key aggregates are specified in Table 1, with limits such as a maximum Los Angeles abrasion value of 50% for base course and 40% for binder course, aggregate impact value max 40% and 30% respectively, flakiness index max 25%, stripping value max 25%, water absorption max 1% (except slag), soundness loss max 12% for slag, and minimum bulk density of 1120 kg/m³ for slag (all tests per IS standards). The grading of aggregates must conform to Table 2, for example, coarse aggregate passing 50 mm sieve is 100%, 25 mm sieve 35-70%, and key aggregate passing 20 mm sieve is 100%, 12.5 mm sieve 35-70%, etc. These ensure suitability for base or binder course in built-up spray grout construction (Clause 4.2.1 to 4.2.3).
Sources: Clause 4.2.1, Clause 4.2.2, Clause 4.2.3
Before applying built-up spray grout, the base surface must be prepared by shaping and conditioning it to a uniform grade and section, ensuring any depressions or potholes are properly filled and compacted well in advance. The surface must be dry and thoroughly cleaned by sweeping off caked earth and foreign matter, brushing with hard then soft brushes, and finally blowing with sacks or gunny bags to remove fine dust. For old blacktop surfaces, ensure they are clean, dry, and free of sand, dirt, and loose debris. For stabilized soil or porous aggregates, apply and cure a suitable bituminous primer as per IRC:16-1965 before construction. The binder should be heated to the specified temperature and uniformly applied at rates given in Table 3, preferably by spraying, just ahead of spreading coarse aggregates (Clause 5.3).
Sources: Clause 5.3
The construction of the two layers of spray grout involves these key steps: First, prepare and clean the base thoroughly, ensuring it is dry and free of dust or foreign matter as per Clause 5.3. Apply a bituminous primer if the base is stabilized soil or porous aggregates. For the first layer, spread coarse aggregates and compact them properly. Then apply binder heated to the specified temperature uniformly at 12.5 to 15.0 kg per 10 m², ensuring aggregates are surface dry before application (Clause 12.5). Immediately after, spread the second layer of coarse aggregates at 0.5 m² per 10 m² and compact as described in Clause 5.7. After compaction, apply the binder again at 12.5 to 15.0 kg per 10 m² (Clause 5.8). Finally, spread key aggregates at 0.13 m³ per 10 m² and roll until a uniform closed surface is achieved (Clause 5.9). Compaction should follow the procedures in Clause 5.5. Weather conditions must be suitable, avoiding temperatures below 16℃ or damp/foggy conditions (Clause 5.1).
Sources: Clause 2.36, Clause 5.1, Clause 5.3, Clause 5.5, Clause 5.7, Clause 5.8, Clause 5.9, Clause 12.5
Built-up spray grout is an open-graded construction intended for base or binder courses and should not be used as a wearing course. As per Clause 5.11, the wearing course must be applied before opening the built-up spray grout to traffic. However, in special circumstances, the Engineer-in-charge may allow limited traffic at a restricted speed of 16 km/h immediately after construction. Therefore, built-up spray grout cannot be opened to normal traffic immediately without a wearing course.
Sources: Clause 5.11, Clause 5.10, Clause 4.1.1
Ask AI about any clause, requirement, or provision in IRC 47. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required