IRC 29-1988 specifies the requirements for design, materials, construction, and quality control of bituminous concrete (asphaltic concrete) used as a wearing course on road pavements in India. It covers aggregate properties, mix design using the Marshall method, laying procedures, compaction, and opening to traffic guidelines. This standard is essential for highway engineers, contractors, and quality control personnel involved in the construction and maintenance of durable, high-performance asphalt pavements.
Overview
IRC 29-1988 specifies the requirements for design, materials, construction, and quality control of bituminous concrete (asphaltic concrete) used as a wearing course on road pavements in India. It covers aggregate properties, mix design using the Marshall method, laying procedures, compaction, and opening to traffic guidelines. This standard is essential for highway engineers, contractors, and quality control personnel involved in the construction and maintenance of durable, high-performance asphalt pavements.
Audience
Contents
Structure
The Introduction of IRC 29 outlines key specifications for bituminous concrete mixes used in road construction. Key points include:
| Sieve (mm) | Grading 1 (25 mm) | Grading 2 (40 & 50 mm) | Grading 3 (50 mm) |
|---|---|---|---|
| 26.5 | - | - | 100 |
| 22.4 | - | 100 | 82-98 |
| 13.2 | 100 | 80-100 | 60-83 |
| 11.2 | 90-100 | 75-95 | 55-77 |
| 5.6 | 60-80 | 55-75 | 45-65 |
| 2.36 | 40-55 | 40-55 | 40-55 |
| 0.3 | 15-25 | 15-25 | 15-25 |
| 0.15 | 10-20 | 10-20 | 10-20 |
| 0.075 | 6-9 | 6-9 | 6-9 |
These form the foundational specifications for materials and mix design in IRC 29 (Introduction and Design Criteria sections).
Sources: Clause 1 Introduction, Clause 2.36, Table 2, Table 3, Table 4
The scope of IRC 29 covers the specifications and guidelines for bituminous concrete for road construction, including materials, mix design, construction, and quality control. Key points include:
These define the overall scope and technical framework for bituminous concrete works under IRC 29.
Sources: Clause 2, Clause 6.1, Clause 6.2, Clause 6.3.4, Table 5, Table 2, Table 3, Clause 5.3, Clause 5.4, Table 4
The key design criteria in IRC 29 include specifications for aggregates and mix design as follows:
Coarse Aggregate Physical Requirements (Table 2):
Aggregate Gradation (Table 3): Specifies percent passing for different sieve sizes for three gradings based on layer thickness (25 mm, 40 mm, 50 mm). For example, for Grading 1 (25 mm thick course), 100% passes 13.2 mm sieve, 40-55% passes 2.36 mm sieve, and 6-9% passes 75 μm sieve.
Mix Design: Binder content fixed to meet mix requirements (Table 1, not shown). Job mix formula includes proportions of coarse aggregate, fine aggregate, filler, and binder, based on laboratory design and must be approved by the Engineer.
Permissible Variations (Table 4): Allowable deviations in aggregate gradation from the job mix formula for quality control.
These criteria ensure durability, strength, and proper gradation for bituminous concrete layers as per IRC 29 Section 3 and related tables.
Sources: Clause 3, Table 2, Table 3, Table 4
Key materials specifications from IRC 29 for bituminous concrete are as follows:
Coarse Aggregate Requirements (Table 2):
Fine Aggregate: Passing 2.36 mm sieve and retained on 75 µm sieve, clean, hard, durable, free from deleterious substances.
Filler: Inert material passing 600 µm sieve, with at least 90% passing 150 µm and 70% passing 75 µm sieve.
Aggregate Gradation (Table 3): Specifies % passing for different sieve sizes for three gradings based on layer thickness (25 mm, 40 mm, 50 mm).
Tack Coat Application (Table 5): Bitumen quantity per 10 m² varies by surface type (5.0-7.5 kg).
These ensure quality and durability of bituminous concrete layers as per IRC 29 Clause 4 and 6.
Sources: Clause 2.36, Table 2, Table 3, Table 5, Clause 4, Clause 6
The key specifications and tables for Mix Design in IRC 29 are as follows:
Physical Requirements of Coarse Aggregate (Table 2):
Aggregate Gradation (Table 3): Specifies % passing for different sieve sizes for three gradings based on layer thickness (25 mm, 40 mm, 50 mm). For example, for Grading 1 (25 mm thick course): 100% passing 13.2 mm sieve, 40-55% passing 2.36 mm sieve, 6-9% passing 75 μm sieve.
Job Mix Formula: Determined by blending aggregates and fixing optimum binder content using the Marshall method (Clause 5.3). It includes proportions of coarse aggregate, fine aggregate, filler, and binder.
Permissible Variations (Table 4): Limits on variation in aggregate gradation from the job mix formula for quality control.
Mix Preparation and Transport: Hot mix plant requirements, temperature control (binder 150°-177°C, aggregate 153°-163°C), thorough mixing, and transport in covered vehicles (Clause 6.4).
Spreading and Compaction: Use of mechanical paver with screed, rolling sequence and roller types, achieving at least 98% density of Marshall specimen (Clause 6.5 and 6.6).
These details ensure the mix meets stability, performance, and durability criteria as per IRC 29.
Tables reproduced below:
Table 2. Physical Requirements of Coarse Aggregate
| Test | Maximum (Per cent) | Test method |
|---|---|---|
| Aggregate Impact Value | 30 - 40 | IS : 2386 (Part IV) |
| Los Angeles Abrasion Value or Flakiness Index | 25 | IS : 2386 (Part I) |
| Stripping Value | 25 | IS : 6241 |
| Water absorption@ Soundness | 1 | IS : 2386 (Part III) |
| (i) Loss with sodium sulphate 5 cycles | 12 | IS : 2386 (Part V) |
| (ii) Loss with magnesium sulphate 5 cycles | 18 | IS : 2386 (Part V) |
Table 3. Aggregate Gradation
| Sieve designation | Grading 1 (25 mm) | Grading 2 (40 & 50 mm) | Grading 3 (50 mm) |
|---|---|---|---|
| 26.5 mm | - | - | 100 |
| 22.4 mm | - | 100 | 82-98 |
| 13.2 mm | 100 | 80-100 | 60-83 |
| 11.2 mm | 90-100 | 75-95 | 55-77 |
| 5.6 mm | 60-80 | 55-75 | 45-65 |
| 2.36 mm | 40-55 | 40-55 | 40-55 |
| 300 μm | 15-25 | 15-25 | 15-25 |
| 150 μm | 10-20 | 10-20 | 10-20 |
| 75 μm | 6-9 | 6-9 | 6-9 |
Table 4. Permissible Variations from the Job Mix Formula (partial data available)
| Sieve Description | Permissible variation by weight to total aggregate (per cent passing) |
|---|---|
| Grading 1 | Grading 2 |
| 26.5 mm | - |
| 22.4 mm | - |
For full details, refer to IRC 29 Clause 5 and Tables 2, 3, and 4.
Sources: Clause 2.36, Table 2, Table 3, Clause 5.3, Table 4, Clause 6.4, Clause 6.5, Clause 6.6
Key construction specifications from IRC 29 Clause 6 include:
Weather and Seasonal Limitations: Laying work shall not be done during rainy, foggy weather, dust storms, or when temperature is ≤10°C in shade (Clause 6.1).
Base Preparation: The base must be shaped, cleaned, and conditioned to specified levels and crossfall. Profile correction or remedial measures are advised if the base is irregular or distressed (Clause 6.2).
Tack Coat Application: A single coat of low viscosity bituminous binder (conforming to IS: 73, 217, 454, or 8887) is applied on a clean surface. Binder heating and spraying rates depend on surface type as per Table 5 below (Clauses 6.3.1 to 6.3.4).
TABLE 5. RATE OF APPLICATION OF TACK COAT
| Type of Surface | Bitumen quantity (kg/10 m²) |
|---|---|
| Normal bituminous surface | 5.0 to 5.5 |
| Dry and hungry bituminous surface | 6.0 to 7.5 |
| Cement concrete pavement | 7.5 |
These ensure proper bonding and durability of bituminous layers during construction.
Sources: Clause 6.1, Clause 6.2, Clause 6.3.1, Clause 6.3.2, Clause 6.3.3, Clause 6.3.4, Table 5
As per IRC 29, Clause 7 (Opening to Traffic), traffic may be allowed only after the completion of the final rolling when the bituminous mix has cooled down to the surrounding temperature. This ensures the pavement has achieved adequate compaction and stability before being subjected to traffic loads. The key specification is that the mix must be fully compacted and cooled to ambient temperature before opening to traffic to prevent damage.
Additionally, Clause 6.6 details the rolling and compaction process, emphasizing that rolling should continue until a density of at least 98% of the laboratory Marshall specimen is achieved and roller marks are eliminated, ensuring pavement quality before opening.
No specific formula is given for opening time, but the cooling to ambient temperature is the controlling criterion.
Summary:
This is critical to ensure durability and performance of the pavement under traffic loads.
Sources: Clause 7, Clause 6.6.2
Key controls for bituminous concrete construction per IRC 29 are summarized as follows:
Aggregate Quality Controls: Coarse aggregate must meet physical requirements such as maximum 30-40% Aggregate Impact Value, max 25% Los Angeles Abrasion or Flakiness Index, max 25% Stripping Value, and max 1% water absorption (exceptionally up to 2%) as per IS 2386 and IS 6241 (Clause 2.36).
Aggregate Gradation: Three gradings are specified for different layer thicknesses (25 mm, 40 mm, 50 mm) with detailed sieve passing percentages (Table 3).
Job Mix Formula: Must be based on representative samples, specifying proportions of coarse aggregate, fine aggregate, filler, and binder content fixed by Marshall method (Clause 5.3).
Permissible Variations: Table 4 defines allowable deviations in aggregate gradation from the job mix formula.
Tack Coat Application: Bitumen quantity for tack coat varies by surface type, e.g., 5.0-5.5 kg/10 m² for normal bituminous surface (Table 5).
These controls ensure quality and durability of bituminous concrete layers.
Sources: Clause 2.36, Table 2, Table 3, Clause 5.3, Table 4, Table 5
Frequently Asked
The specified physical requirements for coarse aggregate in IRC 29 are as follows (per cent maximum limits): Aggregate Impact Value 30-40%, Los Angeles Abrasion Value or Flakiness Index 25%, Stripping Value 25%, Water Absorption 1% (up to 2% in exceptional cases), Soundness loss with sodium sulphate (5 cycles) 12%, and with magnesium sulphate (5 cycles) 18% as per IS 2386 and IS 6241 test methods. Crushed slag, if used, must be air-cooled blast furnace slag with unit weight not less than 1120 kg/m³, max 20% glossy materials, max 6% flat/elongated pieces, max 2% sulphur content, and max 10% water absorption. Fine aggregate shall pass 2.36 mm sieve and be retained on 75 µm sieve, consisting of clean, hard, durable, uncoated material free from deleterious substances. Filler material must be inert, passing 600 µm sieve, with at least 90% passing 150 µm and 70% passing 75 µm sieves. These requirements are detailed in Clause 2.36 and sub-clauses 4.1.3 and 4.1.4.
Sources: Clause 2.36, Clause 4.1.3, Clause 4.1.4
Detailed answer not available.
The recommended procedures for laying and compacting bituminous concrete per IRC 29 are as follows:
Weather Conditions: Laying shall not be done during rain, fog, damp base, dust storms, or when temperature is below 10°C in shade (Clause 6.1).
Base Preparation: The base must be shaped, cleaned, and free of dust or foreign matter. Profile correction or remedial measures should be done if the base is irregular or distressed (Clause 6.2).
Tack Coat Application: Apply a single coat of low viscosity bitumen uniformly using a pressure sprayer just before laying the mix. Rates vary by surface type (e.g., 5.0-5.5 kg/10 m² for normal bituminous surface) as per Table 5 (Clauses 6.3.1 to 6.3.6).
Mix Preparation: Use a hot mix plant ensuring proper aggregate heating (153°-163°C) and binder temperature (150°-177°C) with thorough mixing for uniform coating (Clauses 6.4.1 to 6.4.3).
Transport: Transport mix in clean, covered vehicles if required (Clause 6.4.4).
Spreading: Use a self-propelled mechanical paver with screed for uniform thickness and finish. Manual laying allowed only in restricted areas (Clauses 6.5.1 to 6.5.3).
Compaction: Roll immediately after spreading with a sequence of rollers: breakdown (8-12 tonne 3-wheel steel), intermediate (15-30 tonne pneumatic), and finishing (8-10 tonne tandem). Rolling speed ≤5 km/h; keep roller wheels moist but not oily (Clauses 6.6.1 and 6.6.2).
Opening to Traffic: Allow traffic only after final rolling and cooling to ambient temperature (Clause 7).
This ensures a durable, uniform bituminous concrete layer conforming to specified grades and thicknesses.
Sources: Clause 6.1, Clause 6.2, Clauses 6.3.1 to 6.3.6, Table 5, Clauses 6.4.1 to 6.4.4, Clauses 6.5.1 to 6.5.3, Clauses 6.6.1 and 6.6.2, Clause 7
Quality control tests during production and construction as per IRC 29 include:
These tests ensure uniformity, durability, and performance of bituminous concrete pavement.
Sources: Clause 8.1.1, Clause 2.36, Table 2, Clause 6.4.2, Clause 6.4.3, Clause 5.4, Table 4, Clause 6.3.4, Table 5, Clause 6.6.2
Traffic can be allowed on newly laid bituminous concrete wearing courses after the completion of the final rolling and when the mix has cooled down to the surrounding temperature, as specified in Clause 7 of IRC 29. This ensures that the bituminous concrete has attained sufficient compaction and stability to withstand traffic loads without damage.
Sources: Clause 7
Ask AI about any clause, requirement, or provision in IRC 29. Get instant, clause-cited responses powered by our indexed library.
Free tier includes 150 queries (50 AI + 100 Reference) · No credit card required