IRC 20 (1966) provides recommended practices for the design and construction of Bituminous Penetration Macadam (Full Grout) pavements, specifying materials, grading, and construction methods for durable, well-bonded road surfaces. It covers aggregate selection, bituminous binder types, layer thicknesses, spreading, compaction, and sealing procedures, tailored for Indian climatic and traffic conditions. This standard is essential for civil engineers and road construction professionals involved in flexible pavement design and maintenance.
Overview
IRC 20 (1966) provides recommended practices for the design and construction of Bituminous Penetration Macadam (Full Grout) pavements, specifying materials, grading, and construction methods for durable, well-bonded road surfaces. It covers aggregate selection, bituminous binder types, layer thicknesses, spreading, compaction, and sealing procedures, tailored for Indian climatic and traffic conditions. This standard is essential for civil engineers and road construction professionals involved in flexible pavement design and maintenance.
Audience
Contents
Structure
The IRC 20 Introduction and related clauses provide key specifications and tables for bituminous penetration macadam construction:
Coarse Aggregate Spreading Quantities (Table 2): | Compacted thickness | Quantity (m³/10 m²) | |--------------------|--------------------| | 50 mm | 0.60 | | 75 mm | 0.90 |
Key Aggregate Grading (Table 3): Percent passing for various sieve sizes varies with compacted thickness 50 mm or 75 mm.
Key Aggregate Spreading Quantities (Table 4): | Compacted thickness | Quantity (m³/10 m²) | |--------------------|--------------------| | 50 mm | 0.15 | | 75 mm | 0.18 |
Seal Coat Materials (Table 5): | Material | Size | Quantity per 10 m² | |----------|------|-------------------| | Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ | | Binder | - | 9.8 to 12 kg |
Binder Application Rates (Table 6): | Compacted thickness | Binder Type | Quantity (kg/10 m²) | |--------------------|----------------------|---------------------| | 50 mm | Straight-run bitumen | 50 | | | Road tar RT-4/RT-5 | 60-65 | | 75 mm | Straight-run bitumen | 68 | | | Road tar RT-4/RT-5 | 82-88 |
Construction Notes:
These details are from IRC 20 clauses 1, 2.36, 3.2.3 to 3.2.6, 4.1 to 4.6, and 5.
Sources: Clause 2.36, Clause 3.2.3, Clause 3.2.5, Clause 3.2.6, Clause 4.1, Clause 4.4, Clause 4.5, Clause 4.6, Clause 5
The general requirements per IRC 20 for aggregates and seal coat are as follows:
Coarse Aggregate Spreading Quantities (Table 2):
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.60 |
| 75 mm | 0.90 |
Key Aggregate Grading (Table 3):
| Sieve No. | % Passing for 50 mm | % Passing for 75 mm |
|---|---|---|
| 38 mm | - | - |
| 25 mm | -- | 100 |
| 19 mm | 100 | 35-70 |
| 12 mm | 35-70 | - |
| 9 mm | - | 0-15 |
| 4.75 mm | 0-15 | - |
| 2.36 mm | 0-5 | 0-5 |
Key Aggregate Spreading Quantities (Table 4):
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
Seal Coat Materials (Table 5):
| Material | Size Description | Quantity per 10 m² |
|---|---|---|
| Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ |
| Binder | Straight-run bitumen or road tar of suitable grade | 9.8 to 12 kg |
These specifications ensure proper layering and material quality for road construction as per IRC 20 Clause 3.2.1 to 3.2.6. Physical requirements for aggregates are also mandated but details are not provided in the context.
Sources: Clause 3.2.1, Clause 2.36, Table 3.2.3, Table 3, Table 4, Table 5, Clause 3.2.5, Clause 3.2.6
Key materials specifications for bituminous penetration macadam as per IRC 20 include:
Coarse Aggregate Quantity (Table 2):
Key Aggregate Grading (Table 3): Percent passing by sieve size varies with compacted thickness (50 mm or 75 mm). For example, for 50 mm thickness, 19 mm sieve passes 100%, 12 mm sieve 35-70%, 4.75 mm sieve 0-15%, and 2.36 mm sieve 0-5%. For 75 mm thickness, 25 mm sieve passes 100%, 19 mm sieve 35-70%, 9 mm sieve 0-15%, and 2.36 mm sieve 0-5%.
Key Aggregate Quantity (Table 4):
Seal Coat Materials (Table 5):
These specifications ensure proper gradation and quantities for durable bituminous layers.
Tables reproduced below for clarity.
Sources: Clause 2.36, Clause 3.2.5, Clause 3.2.6
Key specifications and tables for Bituminous Materials per IRC 20 include:
Bituminous binders: Straight-run bitumen grades 80/100, 60/70, 30/40; road tar grades RT-4/RT-5; cutbacks as per climatic conditions (Clause 3.1).
Coarse aggregate spreading quantities: | Compacted thickness | Quantity (m³/10 m²) | |---------------------|--------------------| | 50 mm | 0.60 | | 75 mm | 0.90 |
Key aggregate grading and quantities: | Sieve No. | % Passing (50 mm) | % Passing (75 mm) | |-----------|------------------|------------------| | 38 mm | - | - | | 25 mm | - | 100 | | 19 mm | 100 | 35-70 | | 12 mm | 35-70 | - | | 9 mm | - | 0-15 | | 4.75 mm | 0-15 | - | | 2.36 mm | 0-5 | 0-5 |
Quantities:
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
Seal coat materials and quantities: | Material | Size Description | Quantity (per 10 m²) | |----------|------------------|---------------------| | Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ | | Binder | Straight-run bitumen or Road tar of suitable grade | 9.8 to 12 kg |
Binder application rates: | Compacted thickness | Straight-run bitumen (kg/10 m²) | Road tar RT-4/RT-5 (kg/10 m²) | |---------------------|---------------------------------|------------------------------| | 50 mm | 50 | 60-65 | | 75 mm | 68 | 82-88 |
Construction notes:
These details are from IRC 20 clauses 3.1, 3.2.3, 3.2.5, 3.2.6, 4.1, 4.4, 4.5, and 5.
Sources: Clause 3.1, Clause 2.36, Clause 3.2.3, Clause 3.2.5, Clause 3.2.6, Clause 4.1, Clause 4.4, Clause 4.5, Clause 5
Key specifications and tables for aggregates in IRC 20 are as follows:
Coarse Aggregate Quantity (Table 2):
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.60 |
| 75 mm | 0.90 |
Key Aggregate Grading (Table 3): Percentage passing for different sieve sizes varies with compacted thickness:
| Sieve No. | 50 mm Thickness (%) | 75 mm Thickness (%) |
|---|---|---|
| 38 mm | - | - |
| 25 mm | - | 100 |
| 19 mm | 100 | 35-70 |
| 12 mm | 35-70 | - |
| 9 mm | - | 0-15 |
| 4.75 mm | 0-15 | - |
| 2.36 mm | 0-5 | 0-5 |
Key Aggregate Quantity (Table 4):
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
Seal Coat Materials (Table 5):
| Material | Size Description | Quantity per 10 m² |
|---|---|---|
| Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ |
| Binder | Straight-run bitumen or road tar of suitable grade | 9.8 to 12 kg |
Aggregates must be clean, strong, durable, cubical, and free from deleterious materials.
These tables and specifications govern the selection, grading, and quantities of aggregates for bituminous penetration macadam layers as per IRC 20.
Sources: Clause 2.36, Table 2, Table 3, Table 4, Table 5, Clause 3.2.4, Clause 3.2.5, Clause 3.2.6
Key construction methods for Bituminous Penetration Macadam (BPM) per IRC 20 include:
Weather Limitations: No BPM construction below 16℃ or in damp, foggy, rainy, or dusty conditions (Clause 4.1).
Base Preparation: Uniform grade and section; potholes filled and compacted; priming as per IRC tentative specs (Clause 4.3).
Coarse Aggregate Spreading & Compaction: Spread uniformly with edge protection; compact with 10-ton roller starting at edges, overlapping shoulders by 30 cm; surface tolerance ±12 mm checked by template and straight edge; rolling stops before voids close to allow bitumen penetration (Clause 4.4).
Bituminous Binder Application: Applied at specified rates and temperatures; aggregate must be surface dry; use pressure distributor or nozzle; pouring pots only if permitted (Clause 4.5).
Key Aggregate Application: Spread immediately after bitumen penetration; rolled and broomed until locked; maintain grade and cross-section (Clause 4.6).
Seal Coat: Applied before opening to traffic; binder heated and spread, followed by chippings and rolling (Clause 3.2.6).
Opening to Traffic: Preferably after 24 hours; if earlier, speed limited to 15 km/h (Clause 5).
Tables for quantities and sizes:
| Compacted Thickness | Coarse Aggregate Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.60 |
| 75 mm | 0.90 |
| Compacted Thickness | Key Aggregate Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
| Compacted Thickness | Binder Type | Quantity (kg/10 m²) |
|---|---|---|
| 50 mm | Straight-run bitumen | 50 |
| Road tar RT-4/RT-5 | 60-65 | |
| 75 mm | Straight-run bitumen | 68 |
| Road tar RT-4/RT-5 | 82-88 |
These specifications ensure uniformity, durability, and quality control in BPM construction.
Sources: Clause 2.36, Clause 3.2.5, Clause 3.2.6, Clause 4.1, Clause 4.3, Clause 4.4, Clause 4.5, Clause 4.6, Clause 5
As per IRC 20 Clause 4.1, bituminous penetration macadam shall NOT be constructed when atmospheric temperature is below 16℃, or when the pavement is damp, foggy, rainy, or during dust storms. This ensures proper binder application and compaction. For cold regions, Grade 175/225 bitumen is suggested, and for warm climates, Grade 80/100 is recommended. Road tar grades RT-2 and RT-3 are suggested for hilly and plain areas respectively. Equipment must be in good condition and ready at the site. The aggregate must be dry before binder application, which should be done at specified rates (see Table below). The surface must be checked for uniformity and compacted properly before opening to traffic, preferably after 24 hours, with speed restrictions if opened earlier.
Binder Application Rates (Kg per 10 m²):
| Compacted Thickness | Straight-run Bitumen | Road Tar RT-4/RT-5 |
|---|---|---|
| 50 mm | 50 | 60-65 |
| 75 mm | 68 | 82-88 |
These weather and seasonal limitations ensure quality and durability of bituminous macadam pavements.
Sources: Clause 4.1, Clause 4.5, Table 6 in Clause 4.5
For preparation of base in bituminous penetration macadam as per IRC 20, Clause 4.3: The underlying course must be prepared, shaped, and conditioned to a uniform grade and section. Depressions or potholes should be properly filled and compacted well in advance. Priming may be applied if needed following IRC tentative specifications.
Key tables and specifications include:
Coarse Aggregate Spreading Quantity (Table 2): | Compacted thickness | Quantity (m³/10 m²) | |--------------------|---------------------| | 50 mm | 0.60 | | 75 mm | 0.90 |
Key Aggregate Grading (Table 3): | Sieve No. | 50 mm (%) | 75 mm (%) | |-----------|-----------|-----------| | 38 mm | - | - | | 25 mm | - | 100 | | 19 mm | 100 | 35-70 | | 12 mm | 35-70 | - | | 9 mm | - | 0-15 | | 4.75 mm | 0-15 | - | | 2.36 mm | 0-5 | 0-5 |
Key Aggregate Spreading Quantity (Table 4): | Compacted thickness | Quantity (m³/10 m²) | |--------------------|---------------------| | 50 mm | 0.15 | | 75 mm | 0.18 |
Seal Coat Materials (Table 5): | Material | Size Description | Quantity per 10 m² | |----------|------------------|-------------------| | Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ | | Binder | Straight-run bitumen or Road tar | 9.8 to 12 kg |
Binder Application Rates (Table 6): | Compacted thickness | Binder Type | Quantity (kg/10 m²) | |--------------------|-------------|---------------------| | 50 mm | Bitumen | 50 | | | Road tar RT-4/RT-5 | 60-65 | | 75 mm | Bitumen | 68 | | | Road tar RT-4/RT-5 | 82-88 |
Construction notes:
Weather restrictions: No construction below 16°C or in damp/foggy/rainy conditions (Clause 4.1).
This ensures a well-prepared base for durable bituminous penetration macadam pavement.
Sources: Clause 2.36, Clause 3.2.5, Clause 3.2.6, Clause 4.1, Clause 4.3, Clause 4.4, Clause 4.5, Clause 4.6
For spreading and compacting coarse aggregate in bituminous penetration macadam as per IRC 20:
Spreading quantity (Table 2):
Key aggregate grading (Table 3): Percentage passing sieve sizes varies with compacted thickness (50 mm or 75 mm). For example, for 50 mm thickness, 25 mm sieve passing is 35-70%, 19 mm is 100%, 12 mm is 35-70%, 4.75 mm is 0-15%, and 2.36 mm is 0-5%.
Key aggregate spreading quantity (Table 4):
Seal coat materials (Table 5):
These specifications ensure proper layer thickness and grading for effective compaction and durability (Clause 2.36, 3.2.3 to 3.2.6).
Sources: Clause 2.36, Table 2, Table 3, Table 4, Table 5
The application of bituminous material as per IRC 20 includes key specifications and tables as follows:
Coarse Aggregate Spreading Quantity: | Compacted thickness | Quantity (m³/10 m²) | |--------------------|--------------------| | 50 mm | 0.60 | | 75 mm | 0.90 |
Key Aggregate Grading (Percent Passing): | Sieve No. | 50 mm Thickness | 75 mm Thickness | |-----------|-----------------|-----------------| | 38 mm | - | - | | 25 mm | - | 100 | | 19 mm | 100 | 35-70 | | 12 mm | 35-70 | - | | 9 mm | - | 0-15 | | 4.75 mm | 0-15 | - | | 2.36 mm | 0-5 | 0-5 |
Key Aggregate Quantity: | Compacted thickness | Quantity (m³/10 m²) | |--------------------|---------------------| | 50 mm | 0.15 | | 75 mm | 0.18 |
Seal Coat Materials and Quantities: | Material | Size Description | Quantity (per 10 m²) | |----------|-----------------------------------------|---------------------| | Chipping | 9 mm passing 12 mm retained on 6 mm sieve | 0.09 to 0.11 m³ | | Binder | Straight-run bitumen or Road tar | 9.8 to 12 kg |
Bituminous Binder Application Rates: | Compacted thickness | Binder Type | Quantity (kg/10 m²) | |--------------------|-----------------------|---------------------| | 50 mm | Straight-run bitumen | 50 | | | Road tar RT-4/RT-5 | 60-65 | | 75 mm | Straight-run bitumen | 68 | | | Road tar RT-4/RT-5 | 82-88 |
Construction Notes:
These details are from IRC 20 clauses 3.1, 3.2.5, 3.2.6, 4.5, and 4.6.
Sources: Clause 3.1, Clause 3.2.5, Clause 3.2.6, Clause 4.5, Clause 4.6
For the application of key aggregate in bituminous penetration macadam as per IRC 20, the following key specifications and tables apply:
The size of coarse and key aggregates depends on the compacted thickness of the layer (50 mm or 75 mm) as per Tables 1 and 3.
Quantity of coarse aggregate spread:
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.60 |
| 75 mm | 0.90 |
Key aggregate grading (percent passing sieve):
| Sieve No. | 50 mm thickness | 75 mm thickness |
|---|---|---|
| 38 mm | - | - |
| 25 mm | -- | 100 |
| 19 mm | 100 | 35-70 |
| 12 mm | 35-70 | - |
| 9 mm | - | 0-15 |
| 4.75 mm | 0-15 | - |
| 2.36 mm | 0-5 | 0-5 |
Quantity of key aggregate spread:
| Compacted thickness | Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
These values ensure proper gradation and quantity for effective interlocking and stability of the bituminous layer. The aggregates must be spread using approved methods as per Clause 2.36.
This summary is based on IRC 20 clauses 2.36, 3.2.3, 3.2.5, and related tables.
Sources: Clause 2.36, Clause 3.2.3, Clause 3.2.5
As per IRC 20 Clause 5, the finished bituminous penetration macadam surface shall preferably be opened to traffic 24 hours after rolling. If earlier opening is necessary, vehicle speed must be restricted to 15 km/h. Key specifications related to opening to traffic include:
These ensure the surface is stable and uniform before traffic load (Clause 4.6 and 5).
Key tables relevant to construction and quality control before opening include:
| Compacted Thickness | Binder Quantity (Kg/10 m²) |
|---|---|
| 50 mm | Bitumen: 50; Road Tar: 60-65 |
| 75 mm | Bitumen: 68; Road Tar: 82-88 |
| Compacted Thickness | Coarse Aggregate Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.60 |
| 75 mm | 0.90 |
| Compacted Thickness | Key Aggregate Quantity (m³/10 m²) |
|---|---|
| 50 mm | 0.15 |
| 75 mm | 0.18 |
| Material | Size | Quantity for 10 m² |
|---|---|---|
| Chipping | 9 mm passing 12 mm and retained on 6 mm sieve | 0.09 to 0.11 m³ |
| Binder | - | 9.8 to 12 kg |
These ensure proper surface preparation and durability before opening to traffic.
Sources: Clause 5, Clause 4.6, Clause 2.36, Clause 3.2.5, Clause 3.2.6
Frequently Asked
As per IRC 20 Clause 3.2.4, the coarse aggregate must conform to the grading specified in Table 1. The size of both coarse and key aggregates depends on the intended thickness of the bituminous penetration macadam, as detailed in Tables 1 and 3. The aggregates should be clean, strong, durable, fairly cubical, and free from disintegrated pieces, salts, alkalis, vegetable matter, dust, and coatings. They may be crushed stone, slag, gravel (shingle), or other specified stones. Physical requirements must also be met, ensuring suitability for bituminous macadam layers.
Sources: Clause 3.2.4
The recommended grades of bituminous binders vary with climate as per IRC 20. For very cold regions, grade 175/225 straight-run bitumen is suggested, while for warm climates, grade 80/100 is recommended. Road tar grades RT-2 and RT-3 are suggested for hilly and plain areas respectively. Other commonly used binders include straight-run bitumen grades 80/100, 60/70, 30/40, and road tar grades RT-4 and RT-5. These recommendations ensure suitability to temperature and weather conditions for durability and performance (Clause 4.1 and general context).
Sources: Clause 4.1, Clause None (general context)
For bituminous penetration macadam as per IRC 20, the recommended compacted thicknesses and material quantities per 10 m² are:
Coarse Aggregate:
Key Aggregate:
Seal Coat Materials:
The grading of aggregates varies with thickness, detailed in the provided sieve passing tables. For example, for 50 mm thickness, 100% passes 50 mm sieve and 35-70% passes 25 mm sieve, while for 75 mm thickness, 100% passes 63 mm sieve and 35-70% passes 38 mm sieve (see Tables 2, 3, 4, and 5).
Sources: Clause 2.36, Table 2, Table 3, Table 4, Table 5
To ensure proper penetration during compaction and rolling of bituminous penetration macadam, the coarse aggregate shall be dry rolled with a ten-ton road roller until compacted and keyed, starting from the edges overlapping the shoulder by at least 30 cm and progressing towards the center, with special rolling patterns on curves as per Clause 4.4.1. Rolling must stop before the voids close to the extent that would prevent free and uniform penetration of bitumen and key aggregate. After initial rolling, the surface should be checked with a crown template and 3-metre straight edge to ensure surface irregularities do not exceed 12 mm, correcting as needed. Immediately after bitumen application, key aggregate is spread, rolled, broomed for uniform distribution, and rolled again until locked in the surface, maintaining true grade and cross-section as per Clause 4.6.
Sources: Clause 4.4.1, Clause 4.6
As per IRC 20, bituminous penetration macadam shall not be constructed when the atmospheric temperature is below 16℃, or when the pavement is damp, or during foggy, rainy weather, or dust storms. These weather and seasonal limitations ensure proper bonding and compaction of the bituminous layers (Clause 4.1).
Sources: Clause 4.1