Code of practice for no-fines cast in situ cement concrete 1989 Edition
The 1989 Code of Practice provides detailed instructions on the preparation, mixing, placement, and curing of no-fines cast in situ cement concrete, commonly applied in foundations, walls, and damp-proofing. This standard supports engineers and contractors in using no-fines concrete, a lightweight, porous alternative to conventional masonry, especially where moisture resistance and insulation are priorities.
12Sections
67Clauses Indexed
✓AI Search Ready
1989Edition
Building Construction Practices including Painting Varnishing and Allied FinishingCategory
The 1989 Code of Practice provides detailed instructions on the preparation, mixing, placement, and curing of no-fines cast in situ cement concrete, commonly applied in foundations, walls, and damp-proofing. This standard supports engineers and contractors in using no-fines concrete, a lightweight, porous alternative to conventional masonry, especially where moisture resistance and insulation are priorities.
Audience
Who Uses This Standard
Civil Engineering Professionals
Structural Design Engineers
Project Construction Supervisors
Site Managers
Quality Assurance Engineers
Concrete Material Specialists
Building Construction Contractors
Contents
Key Topics Covered
✓Characteristics and definition of no-fines concrete
✓Specifications for cement and aggregates
✓Optimizing mix ratios and water-cement proportions
✓Procedures and equipment for mixing
✓Transportation, placement, and compaction techniques
✓Design and requirements for formwork
✓Construction practices for walls including reinforcement and tying
✓Planning for embedded services and fixings
✓Methods for plastering and finishing surfaces
✓Curing protocols and weather protection
✓Sampling methods, testing, and strength assessment
✓Precautions for construction and expansion joints
✓Special treatment for openings and lintel reinforcement
✓Handling concreting in adverse weather conditions
Structure
Table of Contents
1Scope and Key Specifications▼
Scope Overview
Covers materials and methods for no-fines concrete including test specimens.
Details specifications for cement, aggregates, mixing, and testing procedures.
Incorporates references to relevant Indian Standards for cement, aggregates, and concrete practices.
Essential Tables
Max Stone Size (mm)
Cement to Aggregate Ratio (Volume)
Optimum Water-Cement Ratio
Target 28-day Compressive Strength (N/mm²)
20
1 : 8
0.40
5.5
20
1 : 9
0.42
4.9
20
1 : 10
0.45
3.5
20
1 : 12
0.48
3.5
40
1 : 10
0.48
3.5
40
1 : 12
0.50
2.6
Note: These values serve as guidelines; site-specific mix validation is recommended.
Important Dimensions
Rubber gasket thickness: 1.6 mm
Diameter of air vent holes: 6 mm
Bearing plate size: 147 mm × 147 mm × 5 mm thick
Referenced Indian Standards
IS 269, IS 383, IS 456, IS 516, IS 1199, IS 455, IS 1489 among others
Mix Design Flowchart
flowchart TD
A[Select Aggregate Size] --> B[Determine Cement to Aggregate Ratio]
B --> C[Identify Optimum Water-Cement Ratio]
C --> D[Prepare Concrete Mix]
2Relevant Indian Standards▼
Summary of Referenced Indian Standards
Key standards cited in IS 12727 include:
IS Number
Description
IS 269 : 1976
Specifications for Ordinary Portland Cement
IS 383 : 1970
Specifications for Coarse and Fine Aggregates
IS 455 : 1976
Specifications for Portland Slag Cement
IS 456 : 1978
Code of Practice for Plain and Reinforced Concrete
IS 516 : 1959
Test Methods for Concrete Strength
IS 1199 : 1959
Sampling and Analysis of Concrete
IS 1489 : 1976
Specifications for Portland Pozzolana Cement
IS 1791 : 1985
Requirements for Batch Concrete Mixers
IS 4845 : 1968
Terminology and Definitions for Hydraulic Cement
IS 6461 (Parts)
Glossary and Concrete Testing Practices
IS 7861 (Parts)
Guidelines for Concreting in Extreme Weather
IS 8041 : 1978
Specifications for Rapid Hardening Portland Cement
Notes:
These standards cover material quality, testing, and construction processes essential for no-fines concrete.
IS 456 is the principal standard for concrete design and practice.
Testing protocols ensure compliance and durability.
Integrated Standard Usage Flow
flowchart LR
A[IS 12727] --> B[IS 456: Concrete Practice]
A --> C[IS 383: Aggregates]
A --> D[IS 269, 455, 1489: Cement Specifications]
A --> E[IS 516, 1199: Testing Procedures]
A --> F[IS 1791: Mixer Specifications]
A --> G[IS 6461: Terminology]
3Definitions and Terminology▼
Key Definitions per IS 12727
Terminology is aligned with IS 4845:1968 for hydraulic cement and IS 6461 (Parts 1, 2, 5-10) for concrete-related terms.
Critical Dimensions
Item
Dimension
Rubber Gasket
1.6 mm thickness
Air Vent Hole
Diameter 6 mm
Bearing Plate
147 mm × 147 mm × 5 mm thick
Referenced Standards for Terminology
IS 269, IS 383, IS 456, IS 516, IS 1791, IS 7861 among others
Summary Diagram
graph LR
A[IS 12727 Terminology] --> B[IS 4845: Hydraulic Cement]
A --> C[IS 6461 Parts: Concrete Glossary]
B --> D[Definitions for Cement]
C --> E[Definitions for Aggregates, Formwork, Properties]
4Materials Specifications▼
Materials Overview
Optimum Water-Cement Ratio (Clause 5.2 & Table 1):
Each cement-aggregate combination has a specific water-cement ratio that maximizes strength.
Proper cement paste coverage and point contact between aggregates is crucial.
Suitable materials include wooden planks (with optional steel sheet lining) or steel plates reinforced with steel angles.
Formwork must be securely fixed and braced to prevent deformation.
Surfaces should be smooth with tightly sealed joints; avoid on-site cutting, fitting, or nailing.
Modular formwork units assembled with bolts or clips allow rapid erection and removal by unskilled workers.
Surfaces in contact with concrete are coated with soap solution before pouring.
Removal of formwork is generally done after 3 days.
Strength Parameters (Clause 11.5)
Property
Value (Proportion of 28-day Cube Strength fc)
Tensile Strength
0.12 × fc
Flexural Strength
0.23 × fc
Cylinder Strength
0.61 × fc
Bond Strength
0.19 × fc
±10% variation acceptable.
Compression failure approximately 0.5 × cube strength.
Additional References
Transporting, placing, compacting, and curing as per IS 456:1978 Clauses 14.2.1 & 14.2.2.
Provision of 4 air vent holes of 6 mm diameter (Clause 4).
Compliance with IS 456:1978 Clause 14.3 for concrete formwork.
Summary Flow
flowchart TD
A[Formwork Design] --> B[Use Wood or Steel Materials]
A --> C[Lightweight Due to Low Pressure]
A --> D[Modular Units, No On-Site Nailing]
A --> E[Soap Solution Coating]
A --> F[Remove After 3 Days]
7Transportation, Placement, Compaction, Curing, and Workmanship▼
Guidelines for Handling No-Fines Concrete
Transportation (Clause 7.1):
Transport concrete without segregation or loss of ingredients.
Maintain workability; avoid premature setting.
Do not add water on-site to regain workability.
Placement and Formwork (Clause 6.1):
Use lightweight, economical formwork (wooden planks with/without steel lining or steel plates).
Ensure formwork is rigid, smooth, and reusable.
Inspect and approve formwork before concreting.
Remove formwork after a minimum of 3 days.
Compaction:
Achieve full compaction to eliminate voids.
Employ suitable tools such as vibrators for uniform compaction.
Curing (Clauses 4.3 & 5.2):
Use water complying with IS 456:1978.
Maintain moisture for at least 7 days.
Proper curing prevents cracks and enhances durability.
Workmanship:
Ensure uniform mixing and accurate proportions.
Use optimum water-cement ratios as per guidelines.
Avoid filling aggregate voids with excessive cement paste.
Table: Optimum Water-Cement Ratio & Strength
Max Stone Size (mm)
Mix Ratio (Cement : Aggregate)
Optimum Water-Cement Ratio
28-day Compressive Strength (N/mm²)
20
1 : 8
0.40
5.5
20
1 : 9
0.42
4.9
20
1 : 10
0.45
3.5
20
1 : 12
0.48
3.5
40
1 : 10
0.48
3.5
40
1 : 12
0.50
2.6
8Fixings and Service Provisions▼
Wall Tie Requirements (Clause 7.5.3)
Mild steel wall ties ensure floor-to-wall connection.
Minimum size of two reinforcing bars depends on building length:
Building Length (m)
Minimum Diameter of Two Bars (mm)
Up to 10
10
Up to 18
12
Up to 35
14
Wall ties should be continuous without interruption by multi-floor windows.
Hooks or splices of ties must overlap by 500 mm.
Ties are fixed to adjacent floor reinforcement or lintels.
For window openings, place two 10 mm diameter bars beneath sills with 500 mm overlap on both sides.
Maintain minimum concrete cover of 50 mm, and apply 3 mm cement slurry coating on reinforcement to prevent corrosion.
Service Provision (Clause 8.2)
Plan for services such as holes, ducts, and chases before casting by incorporating cores in formwork.
Avoid cutting hardened no-fines concrete to prevent structural damage.
Additional Recommendations
Use adequate stirrups with wall ties where high-strength no-fines concrete walls are constructed.
Process Flow
flowchart TD
A[Service Planning] --> B[Insert Cores in Shuttering]
B --> C[Cast Concrete]
C --> D[Avoid Cutting After Setting]
E[Wall Ties] --> F[Size As per Building Length]
F --> G[Continuous Ties with 500 mm Overlap]
G --> H[Fix to Floor Reinforcement or Lintel]
H --> I[Window Sill Reinforcement: Two 10 mm Bars]
9Plastering Procedures▼
Plastering Layers and Thickness (Clause 9.1)
Coat
Thickness (mm)
Sand Gradation (mm)
First Coat (Pricked)
2 to 3
0 to 3
Second Coat (Floating)
5 to 8
0 to 1 or 0 to 2
Total plaster thickness ranges between 10 and 12 mm.
Applicable for exterior and interior walls.
Mortar Mix Ratios (Clause 9.2)
Coat
Cement
Lime
Sand (by loose volume)
First
1
1.5*
8 to 10
Second
0
1
3
Note: Lime quantity in first coat is 1.5 times the cement volume.
Water-Cement Ratio and Strength (Clauses 5.2 & 5.4)
Mix Ratio (Cement : Aggregate)
Optimum Water-Cement Ratio
Compressive Strength (N/mm²)
1:8
0.40
5.5
1:9
0.42
4.9
1:10
0.45
3.5
1:12
0.48 - 0.50
2.6 to 3.5
Summary
Apply plaster in two coats totaling 10-12 mm thickness.
Mortar composition varies between coats with different cement and lime ratios.
Water-cement ratio is critical to achieve desired strength.
Sand gradation is coarser for base coat and finer for finishing.
10Precautions During Wall Construction▼
Reinforcement at Window Openings (Clause 10.0 & Fig. 1)
Place two 10 mm diameter mild steel bars beneath window sills.
Bars should overlap window rebates by 500 mm on both sides.
Maintain minimum concrete cover of 50 mm.
Treat reinforcement with a 3 mm thick cement slurry coating to prevent corrosion and enhance bonding.
Wall Ties (Clause 7.5.3 & Table 2)
Building Length (m)
Minimum Diameter of Two Bars (mm)
Up to 10
10
Up to 18
12
Up to 35
14
Wall ties should be distributed throughout the walls, avoiding interruptions by multi-floor windows.
Hooks or spliced ties must overlap by 500 mm.
Fix ties securely to adjacent floor reinforcement or lintels.
Construction Joints (Clause 7.5.1)
The bond at joints between fresh and hardened no-fines concrete is weaker.
Take measures such as roughening surfaces and using bonding agents to improve joint strength.
Expansion Joints (Clause 7.5.2)
Provide expansion joints at intervals of 35 meters to control shrinkage cracking.
Summary Flow
flowchart TD
A[Wall Construction Precautions] --> B[Window Opening Reinforcement]
A --> C[Wall Tie Installation]
A --> D[Construction Joint Treatment]
A --> E[Expansion Joint Placement]
B --> F[Two 10 mm Bars Under Sill]
B --> G[500 mm Overlap]
B --> H[50 mm Cover + 3 mm Cement Slurry]
C --> I[Size According to Building Length]
C --> J[500 mm Overlap of Ties]
D --> K[Surface Preparation & Bonding Agents]
E --> L[Expansion Joints Every 35 m]
11Sampling and Strength Testing of Concrete▼
Sampling Procedures
Collect concrete samples following IS 1199:1959, ensuring samples represent the entire batch.
Sampling should occur immediately after mixing.
Strength Testing (Clause 11.5)
Primary strength evaluation is based on 28-day cube compressive strength (fc).
Related strength parameters are proportional to fc as follows:
Strength Type
Ratio to 28-day Cube Strength (fc)
Tensile Strength
0.12 × fc
Flexural Strength
0.23 × fc
Cylinder Strength
0.61 × fc
Bond Strength
0.19 × fc
Allowable variance is ±10%.
Compression failure occurs at roughly 50% of cube strength.
Standards Referenced
IS 1199:1959 for sampling and analysis
IS 516:1959 for testing methods
IS 456:1978 for concrete practice
Notes
Typical cube size is 150 mm × 150 mm × 150 mm.
Cure specimens as per IS 516 prior to testing.
Test outcomes inform quality control and mix adjustments.
Testing Flowchart
flowchart LR
A[Concrete Batch] --> B[Sample as per IS 1199]
B --> C[Prepare Test Cubes]
C --> D[Cure for 28 Days per IS 516]
D --> E[Conduct Compression Test]
E --> F[Calculate Strength Parameters]
F --> G[Tensile = 0.12 × fc]
F --> H[Flexural = 0.23 × fc]
F --> I[Cylinder = 0.61 × fc]
F --> J[Bond = 0.19 × fc]
Annex AList of Referenced Indian Standards▼
Referenced Standards Overview
IS 12727 refers to the following Indian Standards critical for materials, testing, and construction methods:
IS Number
Title
IS 269 : 1976
Ordinary and Low Heat Portland Cement Specs
IS 383 : 1970
Coarse and Fine Aggregates for Concrete
IS 455 : 1976
Portland Slag Cement Specifications
IS 456 : 1978
Code of Practice for Plain and Reinforced Concrete
IS 516 : 1959
Methods of Test for Concrete Strength
IS 1199 : 1959
Sampling and Analysis of Concrete
IS 1489 : 1976
Portland Pozzolana Cement Specifications
IS 1791 : 1985
Requirements for Batch Concrete Mixers
IS 4845 : 1968
Definitions and Terminology for Hydraulic Cement
IS 6461 (Parts)
Glossary and Concrete-related Practices
IS 7861 (Parts)
Code of Practice for Extreme Weather Concreting
IS 8041 : 1978
Rapid Hardening Portland Cement
Notes
These standards ensure quality control in materials, mixing, testing, and construction processes.
IS 456 and IS 516 are fundamental for concrete design and strength testing.
IS 383 and IS 269 specify aggregate and cement quality requirements respectively.
IS 1791 governs the specifications for concrete mixers.
Overview Diagram
flowchart LR
A[IS 12727] --> B[Material Specifications (IS 269, 383, 455, 1489)]
A --> C[Testing Procedures (IS 516, 1199)]
A --> D[Construction Practices (IS 456, 1791, 7861)]
Frequently Asked
Popular Questions About IS 12727
?What are the recommended aggregate sizes and types for no-fines concrete under IS 12727?▼
IS 12727 recommends using nominally graded coarse aggregates of 20 mm or 40 mm size for no-fines concrete. Aggregates should be single-sized without fines to maintain large void spaces for permeability. The grading tolerances allow up to 5% oversized and 10% undersized material. The mix includes only coarse aggregate, cement, and water, with cement paste coating of approximately 1 to 2.5 mm thickness around aggregates. These specifications ensure a lightweight, permeable concrete suitable for foundations, floors, damp proof courses, and walls requiring moisture resistance.
?How should no-fines concrete be mixed and what is the optimum water-cement ratio?▼
No-fines concrete mixing involves combining coarse aggregate, cement, and water only, with the coarse aggregate usually single-sized to preserve voids. For water absorbent aggregates like brick ballast, about 33% water by weight of cement should be added to saturated surface dry aggregate. The optimum water-cement ratio typically ranges between 0.40 and 0.50 depending on mix proportions and aggregate size, ensuring proper cement paste coating without blocking voids. Trial mixes on site are necessary to finalize water content and mix proportions to achieve desired strength and permeability.
?What are the guidelines for placing and compacting no-fines concrete on site?▼
No-fines concrete should be placed in horizontal layers not exceeding 500 mm thickness, continuously around the structure to avoid weak planes. Placement must be immediate after mixing to maintain quality, ensuring uniform cement slurry coating of aggregates without separation. Compaction is done by rodding or gentle ramming only; vibration is avoided to prevent segregation. Minimum structural wall thickness should be 230 mm. All operations must be supervised by qualified personnel, following specified precautions to ensure uniform strength and durability.
?How does IS 12727 address reinforcement and wall tie requirements in no-fines concrete walls?▼
IS 12727 specifies mild steel wall ties to maintain floor-to-wall interaction, with the size of two reinforcing bars depending on building length: 10 mm bars for up to 10 m, 12 mm bars for up to 18 m, and 14 mm bars for up to 35 m. Wall ties must be continuous without interruption by multi-floor windows, with hooked or spliced overlaps of 500 mm, and fixed to adjacent floor reinforcement or lintels. Window openings require two 10 mm bars under sills with 500 mm overlap on both sides. Reinforcement must have a minimum 50 mm concrete cover and be coated with approximately 3 mm cement slurry to prevent corrosion and improve bonding.
?What curing procedures are specified to ensure adequate strength and durability of no-fines concrete?▼
Curing of no-fines concrete test cubes involves maintaining 90% relative humidity and a temperature of 27 ± 2°C for 24 to 48 hours in moulds, followed by brief water immersion and sealing in polythene bags until testing. Field curing requires protecting fresh concrete from intense sun and wind using damp sheets and water spraying, beginning after initial set to avoid washing out cement. Curing should continue for at least seven days to prevent moisture loss, facilitate hydration, and achieve durable, strong concrete. Insufficient curing may lead to incomplete hydration and subsequent deterioration.
✦
Need Detailed Clause Answers?
Ask AI about any clause, requirement, or provision in IS 12727. Get instant, clause-cited responses powered by our indexed library.